Every notice, lien, enforcement, release, and bond claim document used on Georgia construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A Georgia subcontractor or supplier not in privity with the contractor generally needs a Notice to Contractor within 30 days, a Claim of Lien recorded within 90 days after last furnishing, a lien action within 365 days after recording, and a Notice of Commencement of Lien Action within 30 days after suit (O.C.G.A. §§ 44-14-361.5, 44-14-361.1).

The Notice to Contractor is required only when a compliant Notice of Commencement has been filed. It goes to the owner or the owner's agent and to the contractor, within 30 days after the Notice of Commencement is filed or first furnishing, whichever is later (§ 44-14-361.5).

Within 2 business days after recording the Claim of Lien, the claimant sends a copy to the owner, and also to the contractor when a Notice of Commencement was filed. An owner or contractor can shorten the suit period to 60 days with a Notice of Contest of Lien (§ 44-14-368).

On public projects, a remote claimant gives the contractor a 30-day Notice to Contractor where the contractor filed a Notice of Commencement, or a 90-day notice of unpaid claim where it did not (§§ 13-10-63, 36-91-93). Suit on the bond is due within one year after completion and acceptance.

Georgia's mechanics and materialmen's lien statute, O.C.G.A. § 44-14-360 et seq., prescribes the content of the Notice of Commencement, the Notice to Contractor, the Claim of Lien, the Notice of Contest of Lien, and the statutory lien waivers. Several of these documents must appear in at least 12-point type.

Public property in Georgia is not subject to mechanics liens. On state and local public projects, unpaid subcontractors and suppliers proceed against the contractor's payment bond under O.C.G.A. §§ 13-10-60 et seq. and 36-91-90 et seq.

This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory form text.

Georgia Preliminary Notices

Preliminary Notice of Lien Rights

Statutory Form
Optional
Who uses it
Potential lien claimants that elect to file it, commonly first-tier subcontractors and suppliers
When
Within 30 days after first delivering labor, services, or materials
Served on or filed with
Recorded with the clerk of superior court in the county where the property lies; a copy is sent to the contractor or owner within 7 days
Notarization
Not required
  • A valid, unexpired notice protects against dissolution of the lien by a contractor's or owner's sworn payment statement.
  • It is not a substitute for the Claim of Lien.

O.C.G.A. § 44-14-361.3

Notice to Contractor

Required When It Applies
Who uses it
Lien claimants not in privity with the contractor, where a compliant Notice of Commencement has been filed
When
Within 30 days after the Notice of Commencement is filed or first furnishing, whichever is later
Served on or filed with
The owner or the owner's agent, and the contractor, at the addresses in the Notice of Commencement, by registered or certified mail or statutory overnight delivery
Notarization
Not required
  • If no compliant Notice of Commencement is filed, this notice is not required.

O.C.G.A. § 44-14-361.5

Georgia Lien Claim and Service

Claim of Lien

Statutory Form
Required When It Applies
Who uses it
Contractors, subcontractors, suppliers, laborers, and other eligible lien claimants
When
Within 90 days after the claimant's last furnishing; a copy is sent within 2 business days after recording
Served on or filed with
Recorded with the clerk of superior court in the county where the property lies; a copy goes to the owner, and to the contractor when a Notice of Commencement was filed
Notarization
Not expressly required by the lien statute
  • The lien must contain the owner's notice of the right to contest and the statement that it expires 395 days after filing, in at least 12-point bold type.
  • An amended Claim of Lien may reduce the amount at any time.

O.C.G.A. §§ 44-14-361.1, 44-14-367

Georgia Enforcing the Lien

Lien Action

Required When It Applies
Who uses it
Lien claimants holding a recorded Claim of Lien
When
Within 365 days after the Claim of Lien is recorded, unless shortened by a Notice of Contest
Served on or filed with
Filed in the appropriate court; a bankruptcy proof of claim or binding arbitration can also qualify
Notarization
Not required

O.C.G.A. § 44-14-361.1(a)(3)

Notice of Commencement of Lien Action

Notarized
Required When It Applies
Who uses it
Lien claimants or their attorneys
When
Within 30 days after commencing the lien action
Served on or filed with
Recorded with the clerk of superior court in the county where the lien was recorded
Notarization
Required (executed under oath)
  • The notice must identify the owner, the court, the parties, the case number, and the lien's book and page.

O.C.G.A. § 44-14-361.1(a)(3)

Notice of Contest of Lien

Statutory Form
Optional
Who uses it
Owners or contractors, or their agents or attorneys
When
Any time after the Claim of Lien is recorded; the claimant must then sue within 60 days after receipt
Served on or filed with
Recorded with the clerk of superior court; a copy is sent to the claimant within 7 days after filing by registered or certified mail or statutory overnight delivery
Notarization
Not required
  • If no Notice of Commencement of Lien Action is recorded, the lien is extinguished 90 days after the contest is filed.

O.C.G.A. § 44-14-368

Georgia Releasing or Bonding Off a Lien

Bond to Discharge Lien

Optional
Who uses it
Owners or contractors
When
Any time after the lien is filed; notice of the bond filing is sent within 7 days
Served on or filed with
Filed with the clerk of superior court for approval; notice and a copy of the bond go to the claimant
Notarization
Not required for the bond; a property bond requires a sworn affidavit
  • The bond is generally double the lien amount, but only the lien amount where the property is the owner's domicile.

O.C.G.A. § 44-14-364

Cancellation of Preliminary Notice Upon Final Payment

Statutory Form
Required When It Applies
Who uses it
Claimants that filed a Preliminary Notice of Lien Rights
When
Delivered at final payment, or the notice is cancelled of record within 10 days after final payment
Served on or filed with
Delivered to the paying party or recorded with the clerk of superior court
Notarization
Not required
  • A claimant that fails to cancel faces actual damages, costs, and reasonable attorney fees.

O.C.G.A. § 44-14-362

Cancellation or Release of Claim of Lien

Required When It Applies
Who uses it
Lien claimants whose recorded lien has been paid, settled, or released
When
Upon payment, settlement, or voluntary release
Served on or filed with
Recorded against the original lien in the county where it was filed
Notarization
Not required by the lien statute; county recording requirements apply

O.C.G.A. § 44-14-366(f)(3)

Affidavit of Nonpayment

Statutory Form
Notarized
Required When It Applies
Who uses it
Claimants that signed a statutory waiver but were not paid
When
Before 90 days after the waiver was executed; copies are sent within 7 days after filing
Served on or filed with
Recorded in the county where the property lies; a copy goes to the owner, and to the contractor where the claimant lacks privity with the owner and a Notice of Commencement was filed
Notarization
Required (sworn before a witness and a notary)

O.C.G.A. § 44-14-366(g)

Georgia Owner Notices and Forms

Notice of Commencement

Required When It Applies
Who uses it
Owners, owners' agents, or contractors
When
Within 15 days after the contractor physically commences work
Served on or filed with
Filed with the clerk of superior court in the project county and posted at the job site
Notarization
Not required
  • A contractor must supply a copy within 10 days after a written request, or the Notice to Contractor requirement does not apply to the requester.

O.C.G.A. § 44-14-361.5(b)

Demand for Filing of Claim of Lien

Optional
Who uses it
Owners or closing participants seeking to clear a Preliminary Notice of Lien Rights
When
On nonresidential property, not before substantial completion, termination, or abandonment; the claimant then has 10 days to file a lien
Served on or filed with
The claimant, at the address in the preliminary notice, by registered or certified mail or statutory overnight delivery
Notarization
Not required; the later affidavit seeking cancellation is sworn

O.C.G.A. § 44-14-361.4

Georgia Public Works and Payment Bond Claims

Notice of Commencement (Public Projects)

Required When It Applies
Who uses it
Contractors furnishing the payment bond
When
Within 15 days after physical commencement of work
Served on or filed with
Filed with the clerk of superior court in the project county and posted at the site
Notarization
Not required

O.C.G.A. §§ 13-10-62, 36-91-92

Notice to Contractor (Public Projects)

Required When It Applies
Who uses it
Claimants contracting with a subcontractor but not with the prime contractor, where the contractor filed a compliant Notice of Commencement
When
Within 30 days after the Notice of Commencement is filed or first furnishing, whichever is later
Served on or filed with
The prime contractor
Notarization
Not required

O.C.G.A. §§ 13-10-63(a)(2), 36-91-93(a)(2)

90-Day Notice of Claim (Public Projects)

Required When It Applies
Who uses it
The same remote claimants, where the contractor did not comply with the Notice of Commencement requirements
When
Within 90 days after the claimant's last furnishing
Served on or filed with
The prime contractor, by registered or certified mail, statutory overnight delivery, or service of process
Notarization
Not required
  • The 30-day and 90-day notices are alternative routes, not cumulative requirements.

O.C.G.A. §§ 13-10-63(a)(1), 36-91-93(a)(1)

Action on Payment Bond (Public Projects)

Required When It Applies
Who uses it
Unpaid claimants protected by the payment bond
When
After 90 days from last furnishing, and within 1 year after completion and acceptance of the contract by the public authority
Served on or filed with
Filed in court in the claimant's name against the contractor and surety
Notarization
Not required

O.C.G.A. §§ 13-10-65, 36-91-95

Frequently Asked Questions

Is there a statutory mechanics lien form in Georgia?

Georgia prescribes the content of the Claim of Lien rather than a fill-in form. It must state the amount, identify the property, give the last furnishing date, and include the owner's notice of the right to contest and the 395-day expiration statement in at least 12-point bold type (O.C.G.A. §§ 44-14-361.1, 44-14-367).

Does a Georgia Claim of Lien have to be notarized?

The lien statute does not expressly require verification or notarization of the Claim of Lien. The Notice of Commencement of Lien Action must be executed under oath, and the Affidavit of Nonpayment must be sworn before a witness and a notary (§§ 44-14-361.1(a)(3), 44-14-366(g)).

Where do I file a mechanics lien in Georgia?

Record the Claim of Lien with the clerk of superior court in the county where the property is located within 90 days after last furnishing. Within 2 business days, send a copy to the owner, and to the contractor when a Notice of Commencement was filed (§ 44-14-361.1(a)(2)).

Is the Notice to Contractor always required in Georgia?

No. It is required only where a compliant Notice of Commencement has been filed, and only for claimants not in privity with the contractor. It goes to both the owner and the contractor (§ 44-14-361.5).

What form releases a mechanics lien in Georgia?

A recorded Claim of Lien is released by a cancellation recorded against the original lien. An owner or contractor may also discharge the lien by filing a bond with the clerk of superior court (§ 44-14-364). A lien that expires under § 44-14-367 needs no release.

What form do I use for a Georgia public project bond claim?

A claimant without a contract with the prime contractor gives a 30-day Notice to Contractor if the contractor filed a Notice of Commencement, or a 90-day notice of claim if it did not. Suit on the bond is due within one year after completion and acceptance (§§ 13-10-63, 13-10-65, 36-91-93, 36-91-95).

What does a Notice of Contest of Lien do in Georgia?

It requires the claimant to commence its lien action within 60 days after receipt of the notice and record a Notice of Commencement of Lien Action. If no action notice is recorded, the lien is extinguished 90 days after the contest is filed (§ 44-14-368).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.