Quick Answer
A Georgia subcontractor or supplier not in privity with the contractor generally needs a Notice to Contractor within 30 days, a Claim of Lien recorded within 90 days after last furnishing, a lien action within 365 days after recording, and a Notice of Commencement of Lien Action within 30 days after suit (O.C.G.A. §§ 44-14-361.5, 44-14-361.1).
The Notice to Contractor is required only when a compliant Notice of Commencement has been filed. It goes to the owner or the owner's agent and to the contractor, within 30 days after the Notice of Commencement is filed or first furnishing, whichever is later (§ 44-14-361.5).
Within 2 business days after recording the Claim of Lien, the claimant sends a copy to the owner, and also to the contractor when a Notice of Commencement was filed. An owner or contractor can shorten the suit period to 60 days with a Notice of Contest of Lien (§ 44-14-368).
On public projects, a remote claimant gives the contractor a 30-day Notice to Contractor where the contractor filed a Notice of Commencement, or a 90-day notice of unpaid claim where it did not (§§ 13-10-63, 36-91-93). Suit on the bond is due within one year after completion and acceptance.
Georgia's mechanics and materialmen's lien statute, O.C.G.A. § 44-14-360 et seq., prescribes the content of the Notice of Commencement, the Notice to Contractor, the Claim of Lien, the Notice of Contest of Lien, and the statutory lien waivers. Several of these documents must appear in at least 12-point type.
Public property in Georgia is not subject to mechanics liens. On state and local public projects, unpaid subcontractors and suppliers proceed against the contractor's payment bond under O.C.G.A. §§ 13-10-60 et seq. and 36-91-90 et seq.
This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory form text.
Georgia Preliminary Notices
Preliminary Notice of Lien Rights
- Who uses it
- Potential lien claimants that elect to file it, commonly first-tier subcontractors and suppliers
- When
- Within 30 days after first delivering labor, services, or materials
- Served on or filed with
- Recorded with the clerk of superior court in the county where the property lies; a copy is sent to the contractor or owner within 7 days
- Notarization
- Not required
- A valid, unexpired notice protects against dissolution of the lien by a contractor's or owner's sworn payment statement.
- It is not a substitute for the Claim of Lien.
O.C.G.A. § 44-14-361.3
Notice to Contractor
- Who uses it
- Lien claimants not in privity with the contractor, where a compliant Notice of Commencement has been filed
- When
- Within 30 days after the Notice of Commencement is filed or first furnishing, whichever is later
- Served on or filed with
- The owner or the owner's agent, and the contractor, at the addresses in the Notice of Commencement, by registered or certified mail or statutory overnight delivery
- Notarization
- Not required
- If no compliant Notice of Commencement is filed, this notice is not required.
O.C.G.A. § 44-14-361.5
Georgia Lien Claim and Service
Claim of Lien
- Who uses it
- Contractors, subcontractors, suppliers, laborers, and other eligible lien claimants
- When
- Within 90 days after the claimant's last furnishing; a copy is sent within 2 business days after recording
- Served on or filed with
- Recorded with the clerk of superior court in the county where the property lies; a copy goes to the owner, and to the contractor when a Notice of Commencement was filed
- Notarization
- Not expressly required by the lien statute
- The lien must contain the owner's notice of the right to contest and the statement that it expires 395 days after filing, in at least 12-point bold type.
- An amended Claim of Lien may reduce the amount at any time.
O.C.G.A. §§ 44-14-361.1, 44-14-367
Georgia Enforcing the Lien
Lien Action
- Who uses it
- Lien claimants holding a recorded Claim of Lien
- When
- Within 365 days after the Claim of Lien is recorded, unless shortened by a Notice of Contest
- Served on or filed with
- Filed in the appropriate court; a bankruptcy proof of claim or binding arbitration can also qualify
- Notarization
- Not required
O.C.G.A. § 44-14-361.1(a)(3)
Notice of Commencement of Lien Action
- Who uses it
- Lien claimants or their attorneys
- When
- Within 30 days after commencing the lien action
- Served on or filed with
- Recorded with the clerk of superior court in the county where the lien was recorded
- Notarization
- Required (executed under oath)
- The notice must identify the owner, the court, the parties, the case number, and the lien's book and page.
O.C.G.A. § 44-14-361.1(a)(3)
Notice of Contest of Lien
- Who uses it
- Owners or contractors, or their agents or attorneys
- When
- Any time after the Claim of Lien is recorded; the claimant must then sue within 60 days after receipt
- Served on or filed with
- Recorded with the clerk of superior court; a copy is sent to the claimant within 7 days after filing by registered or certified mail or statutory overnight delivery
- Notarization
- Not required
- If no Notice of Commencement of Lien Action is recorded, the lien is extinguished 90 days after the contest is filed.
O.C.G.A. § 44-14-368
Georgia Releasing or Bonding Off a Lien
Bond to Discharge Lien
- Who uses it
- Owners or contractors
- When
- Any time after the lien is filed; notice of the bond filing is sent within 7 days
- Served on or filed with
- Filed with the clerk of superior court for approval; notice and a copy of the bond go to the claimant
- Notarization
- Not required for the bond; a property bond requires a sworn affidavit
- The bond is generally double the lien amount, but only the lien amount where the property is the owner's domicile.
O.C.G.A. § 44-14-364
Cancellation of Preliminary Notice Upon Final Payment
- Who uses it
- Claimants that filed a Preliminary Notice of Lien Rights
- When
- Delivered at final payment, or the notice is cancelled of record within 10 days after final payment
- Served on or filed with
- Delivered to the paying party or recorded with the clerk of superior court
- Notarization
- Not required
- A claimant that fails to cancel faces actual damages, costs, and reasonable attorney fees.
O.C.G.A. § 44-14-362
Cancellation or Release of Claim of Lien
- Who uses it
- Lien claimants whose recorded lien has been paid, settled, or released
- When
- Upon payment, settlement, or voluntary release
- Served on or filed with
- Recorded against the original lien in the county where it was filed
- Notarization
- Not required by the lien statute; county recording requirements apply
O.C.G.A. § 44-14-366(f)(3)
Affidavit of Nonpayment
- Who uses it
- Claimants that signed a statutory waiver but were not paid
- When
- Before 90 days after the waiver was executed; copies are sent within 7 days after filing
- Served on or filed with
- Recorded in the county where the property lies; a copy goes to the owner, and to the contractor where the claimant lacks privity with the owner and a Notice of Commencement was filed
- Notarization
- Required (sworn before a witness and a notary)
O.C.G.A. § 44-14-366(g)
Georgia Owner Notices and Forms
Notice of Commencement
- Who uses it
- Owners, owners' agents, or contractors
- When
- Within 15 days after the contractor physically commences work
- Served on or filed with
- Filed with the clerk of superior court in the project county and posted at the job site
- Notarization
- Not required
- A contractor must supply a copy within 10 days after a written request, or the Notice to Contractor requirement does not apply to the requester.
O.C.G.A. § 44-14-361.5(b)
Demand for Filing of Claim of Lien
- Who uses it
- Owners or closing participants seeking to clear a Preliminary Notice of Lien Rights
- When
- On nonresidential property, not before substantial completion, termination, or abandonment; the claimant then has 10 days to file a lien
- Served on or filed with
- The claimant, at the address in the preliminary notice, by registered or certified mail or statutory overnight delivery
- Notarization
- Not required; the later affidavit seeking cancellation is sworn
O.C.G.A. § 44-14-361.4
Georgia Public Works and Payment Bond Claims
Notice of Commencement (Public Projects)
- Who uses it
- Contractors furnishing the payment bond
- When
- Within 15 days after physical commencement of work
- Served on or filed with
- Filed with the clerk of superior court in the project county and posted at the site
- Notarization
- Not required
O.C.G.A. §§ 13-10-62, 36-91-92
Notice to Contractor (Public Projects)
- Who uses it
- Claimants contracting with a subcontractor but not with the prime contractor, where the contractor filed a compliant Notice of Commencement
- When
- Within 30 days after the Notice of Commencement is filed or first furnishing, whichever is later
- Served on or filed with
- The prime contractor
- Notarization
- Not required
O.C.G.A. §§ 13-10-63(a)(2), 36-91-93(a)(2)
90-Day Notice of Claim (Public Projects)
- Who uses it
- The same remote claimants, where the contractor did not comply with the Notice of Commencement requirements
- When
- Within 90 days after the claimant's last furnishing
- Served on or filed with
- The prime contractor, by registered or certified mail, statutory overnight delivery, or service of process
- Notarization
- Not required
- The 30-day and 90-day notices are alternative routes, not cumulative requirements.
O.C.G.A. §§ 13-10-63(a)(1), 36-91-93(a)(1)
Action on Payment Bond (Public Projects)
- Who uses it
- Unpaid claimants protected by the payment bond
- When
- After 90 days from last furnishing, and within 1 year after completion and acceptance of the contract by the public authority
- Served on or filed with
- Filed in court in the claimant's name against the contractor and surety
- Notarization
- Not required
O.C.G.A. §§ 13-10-65, 36-91-95
Frequently Asked Questions
Is there a statutory mechanics lien form in Georgia?
Georgia prescribes the content of the Claim of Lien rather than a fill-in form. It must state the amount, identify the property, give the last furnishing date, and include the owner's notice of the right to contest and the 395-day expiration statement in at least 12-point bold type (O.C.G.A. §§ 44-14-361.1, 44-14-367).
Does a Georgia Claim of Lien have to be notarized?
The lien statute does not expressly require verification or notarization of the Claim of Lien. The Notice of Commencement of Lien Action must be executed under oath, and the Affidavit of Nonpayment must be sworn before a witness and a notary (§§ 44-14-361.1(a)(3), 44-14-366(g)).
Where do I file a mechanics lien in Georgia?
Record the Claim of Lien with the clerk of superior court in the county where the property is located within 90 days after last furnishing. Within 2 business days, send a copy to the owner, and to the contractor when a Notice of Commencement was filed (§ 44-14-361.1(a)(2)).
Is the Notice to Contractor always required in Georgia?
No. It is required only where a compliant Notice of Commencement has been filed, and only for claimants not in privity with the contractor. It goes to both the owner and the contractor (§ 44-14-361.5).
What form releases a mechanics lien in Georgia?
A recorded Claim of Lien is released by a cancellation recorded against the original lien. An owner or contractor may also discharge the lien by filing a bond with the clerk of superior court (§ 44-14-364). A lien that expires under § 44-14-367 needs no release.
What form do I use for a Georgia public project bond claim?
A claimant without a contract with the prime contractor gives a 30-day Notice to Contractor if the contractor filed a Notice of Commencement, or a 90-day notice of claim if it did not. Suit on the bond is due within one year after completion and acceptance (§§ 13-10-63, 13-10-65, 36-91-93, 36-91-95).
What does a Notice of Contest of Lien do in Georgia?
It requires the claimant to commence its lien action within 60 days after receipt of the notice and record a Notice of Commencement of Lien Action. If no action notice is recorded, the lien is extinguished 90 days after the contest is filed (§ 44-14-368).
Related Georgia Resources
Georgia Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Georgia Notice Requirements
Who must give notice, when, and how.
Georgia Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Georgia Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Georgia law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.