HomeIllinoisLien Waivers
Illinois Lien Waivers

Illinois Lien Waiver Forms and Rules

When Illinois lien waivers are required, which forms apply, and when a waiver takes effect, for contractors, subcontractors, and suppliers.

Illinois has no statutory lien waiver form

Illinois prescribes no statutory conditional, unconditional, partial, or final lien waiver forms; waivers are contractual instruments governed by their wording (770 ILCS 60).

Quick Answer

No. Illinois does not require or provide a statutory lien waiver form. Conditional and unconditional partial and final waivers are contracts, effective according to their language, delivery, payment conditions, and any reliance by the owner or lender (770 ILCS 60).

A waiver or subordination of lien rights given in anticipation of and in consideration for the award of a contract or subcontract is against public policy and unenforceable (770 ILCS 60/1(d)). R.W. Dunteman Co. v. C/G Enterprises, Inc., 181 Ill. 2d 153 (1998), applied the rule to a public funds lien.

An ordinary Illinois lien waiver does not have to be notarized. Title company packages often pair the waiver with a sworn contractor's affidavit, and the notarization requirement comes from that affidavit, the contract, or the title insurer.

A waiver-to-date can release all lien rights through the stated date, not just the amount paid. A lien waiver under the Mechanics Lien Act does not waive rights under the Public Construction Bond Act unless it specifically says so (30 ILCS 550/2).

Illinois does not prescribe lien waiver forms. Partial and final waivers, often supplied in title company draw packages alongside contractor sworn statements, are contracts whose wording and delivery control their effect.

Illinois does protect claimants in two important ways. A waiver given in anticipation of and in consideration for the award of a contract or subcontract is void, and a waiver under the Mechanics Lien Act does not waive public payment bond rights unless it says so specifically.

Illinois Lien Waiver Types

Conditional Partial Waiver

When to use it
Delivered in exchange for a progress payment that has not yet been received.
When it takes effect
Effective when its stated payment condition is satisfied, within its stated amount, date, and scope. The statute supplies no default condition.

Unconditional Partial Waiver (Waiver to Date)

When to use it
Delivered after a progress payment has been received.
When it takes effect
Effective on delivery according to its terms. It may waive all lien rights through the stated date, not only the amount shown.

Conditional Final Waiver

When to use it
Delivered in exchange for final payment that has not yet been received.
When it takes effect
Effective when its stated condition is satisfied. Review reservations for retainage, extras, and disputed claims.

Unconditional Final Waiver

When to use it
Delivered after final payment has been received.
When it takes effect
Can extinguish the rights described without any payment condition, subject to defenses and the owner's reliance. Nonpayment does not automatically restore the lien.

Waivers given to win the contract are void

A waiver or subordination of lien rights given in anticipation of and in consideration for the award of a construction contract or subcontract is against public policy and unenforceable, including a no-lien clause passed down through the prime contract (770 ILCS 60/1(d)).

The former provision, Section 1.1, was repealed effective January 1, 2006; Section 1(d) is the current authority. Releases given after performance in exchange for payment remain valid.

Notarization

The Mechanics Lien Act does not require an ordinary lien waiver to be notarized. The contractor's sworn statement under Section 5, a Section 22 statement when an oath is demanded, and the verified Claim for Lien do require an oath.

A Section 35 release of a recorded lien must meet county recording requirements.

Reliance and the waiver to date

A broad waiver to date can release more than the payment it accompanies. In Merchants Environmental Industries, Inc. v. SLT Realty Ltd. Partnership, 314 Ill. App. 3d 848 (2000), good-faith reliance, course of dealing, and knowledge of unpaid extras created factual issues about a facially broad waiver.

In Luczak Bros., Inc. v. Generes, 116 Ill. App. 3d 286 (1983), an owner that made no payment in reliance on a final waiver could not use the waiver as an absolute bar.

Payment bond and public funds rights

A waiver under the Mechanics Lien Act does not waive rights under the Public Construction Bond Act unless the waiver specifically says so (30 ILCS 550/2). Read language releasing bond, surety, and public funds rights separately.

Funds paid for a waiver are held in trust

A person who requests a lien waiver in exchange for payment or a promise of payment must hold the sums received in trust for the party entitled to them, and knowing diversion creates liability (770 ILCS 60/21.02).

That trust does not revive a lien released by an unconditional waiver. Give an unconditional waiver only after funds have actually cleared.

Exchange Illinois lien waivers with your customers and subcontractors, tracked against each payment.

Lien Waiver Exchange

Frequently Asked Questions

Does Illinois have a statutory lien waiver form?

No. The Mechanics Lien Act prescribes notice language for several documents, but no conditional, unconditional, partial, or final waiver forms. The waiver forms used in Illinois, including title company forms, are contracts.

Does an Illinois lien waiver have to be notarized?

No statute requires it. The notarization in many title company draw packages comes from the contractor's sworn statement or affidavit, which must be under oath (770 ILCS 60/5), or from the contract or title insurer.

Are no-lien clauses enforceable in Illinois?

Not when given to obtain the work. A waiver of lien rights given in anticipation of and in consideration for the award of a contract or subcontract is against public policy and unenforceable (770 ILCS 60/1(d)). R.W. Dunteman Co. v. C/G Enterprises, Inc., 181 Ill. 2d 153 (1998).

Does a partial lien waiver release only the amount paid in Illinois?

Not necessarily. A waiver to date can release all lien rights through the stated date. Whether unpaid extras survive can depend on the owner's reliance and knowledge (Merchants Environmental Industries, Inc. v. SLT Realty Ltd. Partnership, 314 Ill. App. 3d 848 (2000)).

Does an Illinois lien waiver release payment bond rights?

Not unless it specifically says so. A waiver under the Mechanics Lien Act does not waive rights under the Public Construction Bond Act unless the waiver expressly includes them (30 ILCS 550/2).

What happens if I sign an unconditional waiver and the check bounces?

Illinois does not automatically restore the lien. The party that obtained the waiver must hold the funds received in trust (770 ILCS 60/21.02), but a waiver relied on by an innocent owner or lender may still be enforced. Use a conditional waiver until funds clear.