Quick Answer

An Illinois subcontractor generally needs a Section 24 notice served on the owner and any known lender within 90 days after completing its work, a verified Claim for Lien recorded within four months to preserve rights against third parties, and a suit within two years (770 ILCS 60/24, 60/7, 60/9).

On an existing owner-occupied single-family residence, a subcontractor must also serve a 60-day notice on the owner from first furnishing (770 ILCS 60/21(c)). Since January 1, 2025, that requirement appears only in Section 21(c). The contractor must give the owner a statutory warning before the first payment (§ 5(b)(i)).

A contractor must give the owner a sworn statement listing every subcontractor and supplier before receiving any payment (§ 5(a)). An owner or interested party can serve a Section 34 notice that forces the claimant to sue within 30 days, and can demand a Section 35 release once the lien is paid.

On public projects, a claimant files a verified notice of claim with the awarding public body within 180 days after last furnishing, sends a copy to the prime contractor within 10 days, and sues within one year (30 ILCS 550/2). A Section 23 lien on public funds must reach the public official before the funds are paid out.

The Illinois Mechanics Lien Act, 770 ILCS 60, uses a series of statements and notices rather than a single preliminary notice. Contractors give owners sworn statements, subcontractors serve a Section 24 notice within 90 days after completing their work, and every claimant must record a verified Claim for Lien within four months to protect against third parties.

Public property in Illinois is not subject to mechanics liens. On public projects, unpaid claimants use the verified notice of claim under the Public Construction Bond Act, 30 ILCS 550, and may also assert a lien on public funds under Section 23 of the Mechanics Lien Act.

This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory form text.

Illinois Preliminary Notices

Contractor's Sworn Statement

Notarized
Required When It Applies
Who uses it
Contractors in direct contract with the owner
When
Before any payment or advance from the owner
Served on or filed with
The owner
Notarization
Required (under oath or verified by affidavit)
  • It lists every party furnishing labor or materials and the amount due or to become due to each.
  • A sworn statement that correctly lists a subcontractor and its amount can substitute for that subcontractor's Section 24 notice to the extent of the amount shown.

770 ILCS 60/5(a)

Notice to Owner of Owner-Occupied Single-Family Residence (Contractor's Warning)

Statutory Form
Required When It Applies
Who uses it
Contractors on owner-occupied single-family residences
When
In the contract or a separate statement, before the first payment
Served on or filed with
The owner or the owner's agent
Notarization
Not required
  • The statutory warning must be in at least 10-point boldface type.

770 ILCS 60/5(b)(i)

60-Day Notice to Owner (Owner-Occupied Residence)

Statutory Form
Required When It Applies
Who uses it
Subcontractors and suppliers on an existing owner-occupied single-family residence
When
Within 60 days after first furnishing labor or materials
Served on or filed with
The occupying owner or the owner's residential agent, personally or by certified mail, return receipt requested
Notarization
Not required
  • A late notice preserves the lien only to the extent the owner has not been prejudiced by payments already made.

770 ILCS 60/21(c)

Illinois Notices Before Filing a Lien

Section 24 Notice (Subcontractor's 90-Day Notice)

Required When It Applies
Who uses it
Subcontractors, sub-subcontractors, and suppliers not in direct contract with the owner
When
Within 90 days after completing the claimant's contract or final qualifying extra work
Served on or filed with
The owner of record or a listed representative, and any known lender, by certified or registered mail, tracked delivery service, or personal service
Notarization
Not required
  • The statute provides a model notice, not an exclusive form.
  • Since January 1, 2025, a nationally recognized tracked delivery service is an authorized method.

770 ILCS 60/24

Illinois Lien Claim and Service

Claim for Lien

Notarized
Required When It Applies
Who uses it
Contractors, subcontractors, and suppliers
When
Within 4 months after completion to preserve the lien against third parties; against the original owner, within 2 years
Served on or filed with
Recorded with the recorder of deeds in the county where the property lies
Notarization
Required (verified by affidavit)
  • The claim must summarize the contract, state the balance after credits, describe the property, and give the completion date.
  • Timely filing suit within four months can substitute for recording.

770 ILCS 60/7, 60/28

Notice of Recorded Lien (Owner-Occupied Residence)

Required When It Applies
Who uses it
Contractors in direct contract with the owner of an owner-occupied single-family residence
When
Within 10 days after recording the Claim for Lien
Served on or filed with
The owner
Notarization
Not required
  • Failure extinguishes the lien to the extent of damages the owner suffers before notice.

770 ILCS 60/7(d)

Illinois Enforcing the Lien

Complaint to Foreclose Mechanics Lien

Required When It Applies
Who uses it
Lien claimants
When
Within 2 years after completion of the contract or final qualifying extra work, or within 30 days after a Section 34 notice
Served on or filed with
Filed in the circuit court of the county where the property lies
Notarization
Not required by the Act

770 ILCS 60/9, 60/11

Section 34 Notice to Commence Suit

Statutory Form
Optional
Who uses it
Owners, lienors, other interested persons, or their agents or attorneys
When
Any time after the lien is recorded; the claimant must sue, or answer in a pending suit, within 30 days
Served on or filed with
The claimant or its agent or attorney, personally or by registered or certified mail, return receipt requested
Notarization
Not required
  • The forfeiture warning must be in at least 10-point boldface type. If the claimant does not act, the lien is forfeited.

770 ILCS 60/34

Illinois Releasing or Bonding Off a Lien

Section 35 Release of Lien

Statutory Form
Required When It Applies
Who uses it
Lien claimants whose recorded lien has been paid with filing costs or forfeited
When
Within 10 days after a written demand for release
Served on or filed with
Delivered to the requesting party and recorded in the original recording office
Notarization
Not expressly required; county recording requirements apply
  • The release must carry the statutory recording warning in bold letters at least one-quarter inch high.

770 ILCS 60/35

Petition to Substitute Bond for Lien

Statutory Form
Notarized
Optional
Who uses it
Owners and other interested persons or payment obligors
When
Any time; if a lien suit is pending, within the statutory window after the claimant's complaint
Served on or filed with
Filed in the circuit court of the county where the property lies; notice served on the claimant and its attorney
Notarization
Required (verified petition)
  • The surety bond must equal 175 percent of the lien. The court's order and executed bond are recorded in each county.

770 ILCS 60/38.1

Illinois Owner Notices and Forms

Subcontractor's Sworn Statement on Demand

Notarized
Required When It Applies
Who uses it
Subcontractors, at the written demand of the owner, contractor, or their agents
When
Within 5 days after written demand
Served on or filed with
The party that made the demand
Notarization
Required if the demand calls for an oath

770 ILCS 60/22

Illinois Public Works and Payment Bond Claims

Verified Notice of Claim (Public Construction Bond Act)

Notarized
Required When It Applies
Who uses it
Unpaid subcontractors, suppliers, and laborers on bonded public projects
When
Within 180 days after the claimant's last furnishing; copy to the prime contractor within 10 days after filing
Served on or filed with
State projects: the awarding officer, board, bureau, or department. Local projects: the clerk or secretary of the political subdivision
Notarization
Required (verified)
  • The statute lists the required content, including the claimant, the prime contractor, the hiring party, the improvement, and the unpaid amount.

30 ILCS 550/2

Action on Public Payment Bond

Required When It Applies
Who uses it
Claimants that filed a timely verified notice of claim
When
Within 1 year after the claimant's last furnishing
Served on or filed with
Filed in the circuit court where the contract was performed, in the name of the public body for the claimant's use, with a certified copy of the bond
Notarization
Not required

30 ILCS 550/2

Notice of Lien on Public Funds

Notarized
Required When It Applies
Who uses it
Subcontractors, suppliers, and laborers furnishing to a public project contractor
When
Before the public body pays the funds or delivers the voucher; within 30 days after a contractor's written demand
Served on or filed with
Local projects: the clerk or secretary. State projects: the Director or official letting the contract. A copy goes to the prime contractor at once
Notarization
Required (sworn statement)
  • Effective on receipt. It attaches only to unpaid contract funds held by the public body.

770 ILCS 60/23(b)-(c)

Complaint for Accounting (Lien on Public Funds)

Required When It Applies
Who uses it
Claimants that served a Notice of Lien on Public Funds
When
Within 90 days after the notice; copy of the complaint to the public official within 10 days after filing
Served on or filed with
Filed in circuit court naming the prime contractor and the hiring contractor; delivered to the public official
Notarization
Not required
  • On State appropriations, suit and delivery must occur at least 15 days before the appropriation lapses.

770 ILCS 60/23(b)(4), (c)(4)

Frequently Asked Questions

Is there a statutory mechanics lien form in Illinois?

No fill-in form. The Mechanics Lien Act prescribes the content of the Claim for Lien: a summary of the contract, the balance due after credits, a sufficient property description, and the completion date, verified by affidavit (770 ILCS 60/7). Section 24 provides a model notice, not an exclusive form.

Does an Illinois mechanics lien have to be notarized?

Yes. The Claim for Lien must be verified by the affidavit of the claimant or its agent or employee (770 ILCS 60/7). The Section 24 notice and the 60-day residential notice do not require notarization.

Where do I file a mechanics lien in Illinois?

Record the Claim for Lien with the recorder of deeds in the county where the property is located. Record within four months after completion to protect the lien against purchasers, lenders, and other third parties (770 ILCS 60/7).

What is a Section 34 notice in Illinois?

A written demand, with a statutory boldface warning, served on the lien claimant by an owner, lienor, or other interested person. The claimant must file suit, or answer in a pending suit, within 30 days or the lien is forfeited (770 ILCS 60/34).

What form releases a mechanics lien in Illinois?

A Section 35 release. Once the lien and filing costs are paid, the claimant must deliver a release within 10 days after written demand, bearing the statutory recording warning (770 ILCS 60/35). An owner may also substitute a 175 percent bond for the lien under Section 38.1.

What form do I use for an Illinois public project bond claim?

A verified notice of claim filed with the awarding public body within 180 days after your last furnishing, with a copy to the prime contractor within 10 days. Suit on the bond is due within one year after last furnishing (30 ILCS 550/2).

Is the 60-day residential notice still required in Illinois?

Yes. For an existing owner-occupied single-family residence, a subcontractor must serve the owner within 60 days after first furnishing. Public Act 103-827, effective January 1, 2025, moved the requirement entirely into 770 ILCS 60/21(c).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.