Massachusetts Lien Waiver Forms and Rules
When Massachusetts lien waivers are required, which forms apply, and when a waiver takes effect, for contractors, subcontractors, and suppliers.
Massachusetts requires statutory lien waiver forms
G.L. c. 254, § 32 voids advance lien waivers and subordinations, except listed exceptions; a partial waiver and subordination by a Notice of Contract filer is valid only in substantially the statutory form without material deviation.
Quick Answer
Yes, in part. Massachusetts requires the statutory Partial Waiver and Subordination of Lien form for any partial waiver or subordination given by a person who has filed a Notice of Contract, in substantially the statutory form without material deviation (G.L. c. 254, § 32(4)). Other advance lien waivers are void.
The statutory form waives lien rights for work through a stated payment period only upon receipt of the identified payment. It preserves retainage, unpaid changes, and disputed claims, and it subordinates remaining rights only to a named lender's actual advances through the 25th day after the payment period ends.
The form is signed under penalties of perjury and does not require notarization. It does not affect anyone else's lien rights, so a general contractor's waiver does not waive the separate liens of its subcontractors and suppliers.
Public payment bond rights under G.L. c. 149, § 29 cannot be contracted away in advance. The Supreme Judicial Court voided a subcontract clause forfeiting those rights. Costa v. Brait Builders Corp., 463 Mass. 65 (2012).
Massachusetts starts from a prohibition. Under G.L. c. 254, § 32, any agreement that bars a party from filing a Notice of Contract, enforcing a lien, or that subordinates lien rights is void and unenforceable, unless it fits one of four statutory exceptions.
The main exception is a single combined statutory form, the Partial Waiver and Subordination of Lien. Massachusetts has no separate statutory family of conditional and unconditional, progress and final waivers.
Massachusetts Lien Waiver Types
Partial Waiver and Subordination of Lien
- When to use it
- Given with a payment application by a person who has filed a Notice of Contract, to waive lien rights for work through a stated payment period and subordinate remaining rights to a named lender's advances.
- When it takes effect
- The waiver operates upon receipt of the identified payment. The subordination reaches only amounts the lender actually advances through the 25th day after the payment period ends. Retainage, unpaid changes, and disputed claims are excepted.
Notice Dissolving Lien
- When to use it
- Filed by a lienholder to dissolve its own recorded lien, typically after final payment.
- When it takes effect
- Dissolves the recorded lien upon filing in the registry. It does not necessarily bar a later timely Notice of Contract (Tremont Tower, 436 Mass. 677).
Payment Waiver by Principal on a Lien Bond
- When to use it
- Given in connection with an interim or final payment received, by a person named as principal on a § 12 blanket lien bond.
- When it takes effect
- Valid under the § 32 exception for payments actually received.
Statement of Amounts Due or Paid
- When to use it
- A statement by a person entitled to file a lien of the amounts due or paid, used in payment and closing transactions.
- When it takes effect
- Permitted by § 32. It reports amounts; it does not waive future lien rights.
Advance waivers are void
Section 32 voids any contract or collateral provision that bars filing a Notice of Contract, bars lien enforcement steps, or prospectively subordinates lien rights. Placing the provision in a signed construction contract does not cure it.
Only the four statutory exceptions survive: payment waivers by a § 12 bond principal, statements of amounts due or paid, § 10 dissolutions, and the statutory Partial Waiver and Subordination of Lien.
Use the statutory form without material deviation
A partial waiver or subordination by a Notice of Contract filer must be in substantially the statutory form without material deviation. A broader or reworded waiver falls outside the exception and is void.
The form requires account information, including pending changes and disputed claims.
Notarization
The statutory form is signed under penalties of perjury and does not require notarization. A dissolution or other instrument recorded in the registry must meet registry execution and acknowledgment requirements (G.L. c. 254, § 30).
Payment bond rights
Public payment bond rights under G.L. c. 149, § 29 cannot be prospectively waived. In Costa v. Brait Builders Corp., 463 Mass. 65 (2012), the Supreme Judicial Court invalidated a subcontract clause forfeiting a subcontractor's bond rights, even though it was labeled a condition precedent.
A lien waiver is not automatically a bond waiver. Private payment bonds are governed by their terms and G.L. c. 149, § 29A.
Residential projects
Section 32 has no residential exception. Home improvement contracts under G.L. c. 142A carry separate disclosure requirements, and the owner's c. 142A rights cannot be waived. The § 33 lender withholding rule excludes projects of one to four dwelling units.
Exchange Massachusetts lien waivers with your customers and subcontractors, tracked against each payment.
Open Questions Under Massachusetts Law
- Section 32 does not define receipt of payment, and no controlling appellate decision says whether the statutory waiver takes effect when a check is delivered or only when funds clear. Whether a cleared-funds condition added to the form is a material deviation is also undecided. This point is not settled under Massachusetts law. National Lien & Bond confirms it with a local Massachusetts attorney before relying on it.
Frequently Asked Questions
Does Massachusetts have a statutory lien waiver form?
Yes. G.L. c. 254, § 32 prescribes the Partial Waiver and Subordination of Lien. A partial waiver or subordination by a person who has filed a Notice of Contract must be in substantially that form without material deviation.
Are advance lien waivers enforceable in Massachusetts?
No. Section 32 voids agreements that bar filing a Notice of Contract, bar lien enforcement, or prospectively subordinate lien rights, unless the agreement fits a statutory exception.
Does a Massachusetts lien waiver have to be notarized?
No. The statutory Partial Waiver and Subordination of Lien is signed under penalties of perjury. A document recorded in the registry, such as a § 10 dissolution, must meet registry recording requirements.
When does the Massachusetts partial lien waiver take effect?
The waiver operates upon receipt of the payment identified in the form, for work through the stated payment period. It is not effective on signature alone.
How do I release a mechanics lien in Massachusetts after final payment?
The lienholder files a signed notice dissolving the lien in the registry where its Notice of Contract was filed (G.L. c. 254, § 10).
Can a Massachusetts subcontractor waive payment bond rights in advance?
No. The Supreme Judicial Court held that a subcontract clause forfeiting a subcontractor's public payment bond rights is unenforceable. Costa v. Brait Builders Corp., 463 Mass. 65 (2012).
Related Massachusetts Resources
Massachusetts Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Massachusetts Notice Requirements
Who must give notice, when, and how.
Massachusetts Mechanics Lien Forms
Every notice, lien, release, and bond claim form.
Massachusetts Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Massachusetts law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.