Massachusetts Mechanics Lien Forms
Every notice, lien, enforcement, release, and bond claim document used on Massachusetts construction projects, with who uses it, when it is due, and where it goes.
Quick Answer
A Massachusetts subcontractor or supplier generally needs four documents in order: a Notice of Identification mailed to the general contractor within 30 days after starting work, a recorded Notice of Contract, a recorded Statement of Account, and a civil action filed within 90 days after the statement (G.L. c. 254, §§ 4, 8, 11).
The Notice of Contract is due by the earliest of 60 days after a Notice of Substantial Completion is recorded, 90 days after a Notice of Termination is recorded, or 90 days after the general contractor's last furnishing. The Statement of Account uses 90, 120, and 120 days from the same events.
Within 30 days after commencing the enforcement action, the claimant records an attested copy of the complaint in the registry of deeds (§ 5). A lienholder may dissolve its own lien by filing a signed notice (§ 10), and any person in interest may dissolve a lien by recording a bond (§ 14).
On public works, a claimant that contracts with a subcontractor, but not with the general contractor, sends written notice to the general contractor by registered or certified mail within 65 days after last furnishing. Suit on the payment bond is due within 1 year after last furnishing (G.L. c. 149, § 29).
Massachusetts mechanics lien law (G.L. c. 254) works through recorded documents. Each lien claimant records its own Notice of Contract in the registry of deeds, then records a Statement of Account, then sues within 90 days after the statement is filed.
Chapter 254 supplies substantially prescribed forms for the Notice of Contract, the Notice of Identification, the Notice of Substantial Completion, the Notice of Termination, the lien bonds, and the Partial Waiver and Subordination of Lien. Owners use completion and termination notices to shorten the filing deadlines.
This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory text or offer downloadable forms.
Massachusetts Preliminary Notices
Notice of Identification
- Who uses it
- Claimants without a direct contract with the general contractor
- When
- Within 30 days after commencing performance
- Served on or filed with
- The general contractor, by certified mail, return receipt requested; it is not recorded
- Notarization
- Not required
- Without it, the lien is capped at the balance due under the subcontract above the claimant.
- The form identifies the claimant, its customer, the project, and the amount or estimated amount.
G.L. c. 254, § 4
Massachusetts Lien Claim and Service
Notice of Contract
- Who uses it
- Every lien claimant: contractors with a direct owner contract under § 2, and subcontractors, suppliers, and equipment lessors under § 4
- When
- By the earliest of 60 days after a Notice of Substantial Completion is recorded, 90 days after a Notice of Termination is recorded, or 90 days after the general contractor's last furnishing
- Served on or filed with
- Recorded in the registry of deeds for the county or district where the land lies; subcontractors and suppliers must also give the owner actual notice of the filing
- Notarization
- No oath required; follow registry acknowledgment requirements
- The last-furnishing deadline runs from the general contractor's last furnishing, or that of anyone claiming through it, not the claimant's own last day.
- Without a timely Notice of Contract, there is no lien.
G.L. c. 254, §§ 2, 4, 30
Statement of Account
- Who uses it
- Every lien claimant
- When
- By the earliest of 90 days after a Notice of Substantial Completion is recorded, 120 days after a Notice of Termination is recorded, or 120 days after the general contractor's last furnishing
- Served on or filed with
- Recorded in the registry of deeds where the land lies
- Notarization
- No oath or verification required by statute
- The statement must give a just and true account of the amount due or to become due, with all credits, a brief property description, and the owners named in the Notice of Contract.
- Design professionals under §§ 2C and 2D file within 30 days after the last day their Notice of Contract could be filed.
G.L. c. 254, § 8
Massachusetts Enforcing the Lien
Civil Action to Enforce Lien and Recorded Attested Complaint
- Who uses it
- Lien claimants
- When
- Suit within 90 days after filing the Statement of Account; attested copy of the complaint recorded within 30 days after commencing the action
- Served on or filed with
- Filed in the Superior Court for the county or the District Court for the judicial district where the land lies; attested complaint recorded in the registry of deeds
- Notarization
- The recorded copy must be attested; the complaint need not be verified
- Missing the 90-day suit deadline dissolves the lien.
G.L. c. 254, §§ 5, 11
Massachusetts Releasing or Bonding Off a Lien
Notice Dissolving Lien
- Who uses it
- The lienholder, as to its own lien
- When
- At any time; effective on filing
- Served on or filed with
- Filed in the registry where the Notice of Contract was filed
- Notarization
- Not required by statute; follow registry recording requirements
- Dissolving a recorded lien does not necessarily surrender the right to record a later timely Notice of Contract. Tremont Tower Condominium, LLC v. George B.H. Macomber Co., 436 Mass. 677 (2002).
G.L. c. 254, § 10
Bond to Dissolve a Particular Lien
- Who uses it
- Any person in interest, including the owner
- When
- At any time; the lien dissolves when the bond is recorded
- Served on or filed with
- Recorded in the registry where the land lies; notice of recording and a copy of the bond served on or delivered to the claimant
- Notarization
- Executed under seal by a Massachusetts authorized surety
- The penal sum equals the lien amount. The claimant must sue on the bond within 90 days after the later of filing its Statement of Account or receiving notice of the bond's recording.
G.L. c. 254, § 14
Blanket Lien Bond
- Who uses it
- Any person in interest, including the owner
- When
- At any time; later liens of covered beneficiaries do not attach after recording
- Served on or filed with
- Recorded in the registry where the land lies, with the contract price certificate
- Notarization
- Signed and sealed by an authorized surety
- Beneficiaries sue on the bond within 90 days after filing the Statement of Account and record an attested complaint.
G.L. c. 254, § 12
Massachusetts Owner Notices and Forms
Verified Complaint for Ruling or Summary Discharge of Lien
- Who uses it
- Any person in interest, including the owner, contractor, or mortgagee
- When
- No fixed period; the show cause order is served at least 7 days before the hearing
- Served on or filed with
- Filed in the local Superior or District Court; necessary parties and recorded mortgage holders receive notice
- Notarization
- Required. The complaint must be verified and supported by other written proof
G.L. c. 254, § 15A
Notice of Substantial Completion
- Who uses it
- The owner and the general contractor, executed jointly
- When
- Upon or after substantial completion
- Served on or filed with
- Recorded in the registry; the owner sends a recorded copy by certified mail to prior § 4 filers, and the contractor sends copies to its direct subcontractors and to identification notice claimants
- Notarization
- Not required by statute
- Recording shortens the Notice of Contract deadline to 60 days and the Statement of Account deadline to 90 days.
G.L. c. 254, § 2A
Notice of Termination
- Who uses it
- The owner, when the general contract is terminated before a Notice of Substantial Completion
- When
- After termination
- Served on or filed with
- Recorded in the registry; the owner mails a copy by certified mail to the contractor and prior § 4 filers, and the contractor delivers copies down the chain
- Notarization
- Not required by statute
- Recording sets the Notice of Contract deadline at 90 days and the Statement of Account deadline at 120 days after recording.
G.L. c. 254, § 2B
Home Improvement Contract Disclosures
- Who uses it
- Contractors performing covered residential work over $1,000 on existing owner-occupied buildings of one to four units
- When
- Signed before work begins, with a signed copy to the owner
- Served on or filed with
- The homeowner
- Notarization
- Not required
- The contract must include conspicuous notice of any resulting lien or security interest, among other required terms.
G.L. c. 142A, §§ 1, 2
Massachusetts Public Works and Payment Bond Claims
Written Notice of Claim on Public Payment Bond
- Who uses it
- Claimants that contract with a subcontractor of the general contractor but not with the general contractor
- When
- Within 65 days after the claimant last furnished labor or materials
- Served on or filed with
- The general contractor, by registered or certified mail to its office, place of business, or residence, or in any manner permitted for civil process
- Notarization
- Not required; the notice need not be sworn
- The notice must state with substantial accuracy the amount claimed and the party for whom the work was done.
- For specially fabricated materials, a separate written notice of the order is due within 20 days after final written approval.
G.L. c. 149, § 29
Action on Public Payment Bond
- Who uses it
- Claimants protected by the payment bond
- When
- Within 1 year after the claimant's last furnishing included in the claim
- Served on or filed with
- Filed in the Superior Court against the principal and surety
- Notarization
- Not required
- Claimants in direct contract with the general contractor do not need the 65-day notice.
G.L. c. 149, § 29
Demand for Direct Payment
- Who uses it
- Statutorily defined subcontractors on public building contracts
- When
- After substantial completion, for a balance unpaid within 70 days after substantial completion
- Served on or filed with
- Delivered or sent by certified mail to the awarding authority, with a copy delivered or mailed to the general contractor at the same time
- Notarization
- Required. The demand is a sworn statement with a detailed breakdown of the balance
- The general contractor may reply within 10 days with a sworn, itemized reply; disputed amounts are deposited in a joint account.
G.L. c. 30, § 39F
Frequently Asked Questions
Is there a statutory mechanics lien form in Massachusetts?
Yes, for several documents. G.L. c. 254, §§ 2 and 4 supply substantially prescribed forms for the Notice of Contract, and § 4 supplies the Notice of Identification. The Statement of Account has prescribed content under § 8 but no fill-in form.
Does a Massachusetts mechanics lien have to be notarized?
Chapter 254 does not require an oath on the Notice of Contract or the Statement of Account. Documents recorded in the registry of deeds must still meet registry execution and acknowledgment requirements, and § 30 addresses acknowledged instruments of entities.
Where do I file a mechanics lien in Massachusetts?
Record the Notice of Contract and the Statement of Account in the registry of deeds for the county or district where the land lies, or with the Land Court registry for registered land (G.L. c. 254, §§ 2, 4, 8). The Notice of Identification is mailed to the general contractor and is not recorded.
What are the Massachusetts Notice of Contract deadlines?
Record the Notice of Contract by the earliest of 60 days after a Notice of Substantial Completion is recorded, 90 days after a Notice of Termination is recorded, or 90 days after the general contractor's last furnishing (G.L. c. 254, §§ 2, 4).
What form releases a mechanics lien in Massachusetts?
A lienholder may dissolve its own lien by filing a signed notice in the registry (G.L. c. 254, § 10). Any person in interest may dissolve a lien by recording a bond under § 14 or a blanket bond under § 12, or may seek summary discharge in court under § 15A.
How long do I have to sue on a Massachusetts mechanics lien?
Suit must be commenced within 90 days after the Statement of Account is filed, and an attested copy of the complaint must be recorded within 30 days after the action is commenced (G.L. c. 254, §§ 5, 11).
What form do I use for a Massachusetts public project bond claim?
There is no statutory form. A claimant that contracts with a subcontractor sends written notice to the general contractor within 65 days after last furnishing, then sues within 1 year after last furnishing (G.L. c. 149, § 29). Subcontractors on public buildings may also demand direct payment under G.L. c. 30, § 39F.
Related Massachusetts Resources
Massachusetts Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Massachusetts Notice Requirements
Who must give notice, when, and how.
Massachusetts Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Massachusetts Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Massachusetts law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.