New Hampshire Mechanics Lien Forms
Every notice, lien, enforcement, release, and bond claim document used on New Hampshire construction projects, with who uses it, when it is due, and where it goes.
Quick Answer
A New Hampshire subcontractor or supplier usually needs four documents in order: a written notice to the owner of its intention to claim a lien, written accounts at least every 30 days, a sworn motion to attach, and a writ of attachment recorded with the registry of deeds within 120 days after last furnishing (RSA 447:5, 447:8, 447:9, 447:10).
Give the notice before furnishing to protect the full amount. A later notice is valid but limits the lien to amounts then due, or later becoming due, to the owner's contractor (RSA 447:6). A claimant contracting directly with the owner needs no notice (RSA 447:2).
Filing a petition within 120 days is not enough; the attachment itself must be made and recorded, and the writ and return must state that it secures the lien (RSA 447:10). A writ in lis pendens form limited to the described real estate may issue without prior application or notice (RSA 511-A:8, III).
Liens cannot attach to public land. On bonded public works, a claimant files a statement of claim within 90 days after the project is completed and accepted, then files a petition to enforce within 1 year after filing the claim, with copies to the principal and surety (RSA 447:17, 447:18).
New Hampshire mechanics liens are governed by RSA Chapter 447, and they are secured through the attachment procedure of RSA Chapter 511-A and Superior Court Rule 47. Payment bonds on public works are governed by RSA 447:16 to 447:18. Mechanics liens cannot attach to public land.
New Hampshire does not use a recorded lien claim. The lien arises from furnishing labor or materials and lasts 120 days, and it is preserved only by an attachment made and recorded within that time. No RSA 447 document has a prescribed statutory form. The table below describes each document. National Lien & Bond does not reproduce statutory text on this page.
New Hampshire Preliminary Notices
Notice of Intention to Claim a Lien
- Who uses it
- Subcontractors, suppliers, and other claimants not in direct contract with the owner
- When
- Before performing labor or furnishing materials, to protect the full amount; a later notice is valid but limited
- Served on or filed with
- The owner or the person having charge of the property, in writing
- Notarization
- Not required
- A late notice limits the lien to amounts due, or later becoming due, to the owner's contractor after the owner receives it.
RSA 447:5, 447:6
Written Account of Labor and Materials
- Who uses it
- Claimants who gave a notice of intention to claim a lien
- When
- As often as once every 30 days after the notice
- Served on or filed with
- The owner or the person having charge of the property
- Notarization
- Not required
- The account is not an alternative to the notice. It lets the owner retain sufficient funds from its contractor.
RSA 447:8
Notice to Construction Lender
- Who uses it
- Persons entitled to a lien on projects financed by a construction mortgage
- When
- Within 15 business days after the jobsite financing posting or after first furnishing, whichever is later
- Served on or filed with
- The institution providing the construction funds, identifying the jobsite name and address
- Notarization
- Not required
- Failure to give this notice does not by itself invalidate the lien.
RSA 447:12-b
New Hampshire Lien Claim and Service
Motion to Attach
- Who uses it
- Lien claimants seeking a court-authorized attachment
- When
- Early enough for the attachment to be made and recorded within 120 days after last furnishing
- Served on or filed with
- Filed with the court with the complaint, a Notice of Intent to Attach, and a proposed order, and served on the defendant; an ex parte motion is available on statutory grounds
- Notarization
- Required (motion under oath)
- In the noticed procedure the defendant may object by the return date, and the court sets a hearing within 14 days after receiving an objection.
RSA 511-A:2, 511-A:8; Super. Ct. R. 47
Writ of Attachment and Return
- Who uses it
- Lien claimants
- When
- Made and recorded within 120 days after the claimant last performed labor or furnished materials
- Served on or filed with
- Recorded by lodging the attested writ and return with the registry of deeds of each county where the land lies
- Notarization
- Not required
- The writ and return must state distinctly that the attachment secures the mechanics lien. A writ in lis pendens form limited to the described real estate may issue without prior application or notice.
RSA 447:9, 447:10, 511-A:5, 511-A:8
New Hampshire Enforcing the Lien
Action on the Underlying Claim
- Who uses it
- Unpaid claimants
- When
- Within the general 3-year limitation for personal actions; there is no separate foreclosure deadline under RSA 447
- Served on or filed with
- Filed in the court with jurisdiction and served on the defendant
- Notarization
- Not required
- Timely attachment secures the lien; the merits are decided separately. An agreement to arbitrate does not waive the right to perfect the lien (Pine Gravel, Inc. v. Cianchette, 128 N.H. 460 (1986)).
RSA 508:4
New Hampshire Releasing or Bonding Off a Lien
Discharge of Attachment
- Who uses it
- Lien claimants or their attorneys
- When
- On request after the attachment is dissolved or released by judgment or otherwise
- Served on or filed with
- Given to the defendant or owner, who may record it wherever the attachment was recorded
- Notarization
- Not specified by statute
RSA 511-A:11
Petition to Release Attachment on Bond
- Who uses it
- Owners or other defendants whose real estate is attached
- When
- At any time while the attachment is in place
- Served on or filed with
- Filed with the court where the action is pending, with reasonable notice to interested parties; the substituted bond runs to the plaintiff
- Notarization
- Not required
- The bond, with sufficient sureties, is conditioned to pay any judgment and costs within 60 days after judgment, or the value of the attached interest if lower.
RSA 511:48, 511:49, 511:50
New Hampshire Owner Notices and Forms
Construction Financing Jobsite Posting
- Who uses it
- Mortgagors that grant a construction mortgage, including a refinancing
- When
- Within 10 business days after executing the construction mortgage
- Served on or filed with
- Posted in a conspicuous place on the jobsite, naming the lender and its address and telephone number
- Notarization
- Not required
RSA 447:12-b
Mortgage Disbursement Affidavit
- Who uses it
- Mortgagors or their agents, relied on by the construction lender
- When
- Before the disbursement for which the lender claims priority
- Served on or filed with
- The mortgagee
- Notarization
- Required (sworn affidavit)
- The affidavit states that completed work and subcontractor and supplier claims have been paid or will be paid from the disbursement. A lender may not knowingly accept a false affidavit.
RSA 447:12-a
New Hampshire Public Works and Payment Bond Claims
Statement of Claim on Public Payment Bond
- Who uses it
- Unpaid subcontractors, suppliers, and laborers on bonded public works
- When
- Within 90 days after the project is completed and accepted by the contracting party
- Served on or filed with
- State projects: the Secretary of State, or the Department of Transportation or Department of Administrative Services when the contract runs through it. Political subdivision projects: the clerk of the superior court where the work was principally performed
- Notarization
- Not required
- The filing office mails copies to the principal and surety. Strict compliance is required; notice sent directly to the contractor is not a substitute (Fastrack Crushing Services, Inc. v. Abatement International/Advatex Associates, Inc., 149 N.H. 661 (2003)).
RSA 447:16, 447:17
Petition to Enforce Bond Claim
- Who uses it
- Claimants who filed a timely statement of claim
- When
- Within 1 year after filing the statement of claim; copies to the principal and surety within the same year
- Served on or filed with
- Filed in the superior court of the county where the contract was principally performed
- Notarization
- Not required
- There is no waiting period. A claimant may instead intervene in a pending petition (General Insulation Co. v. Eckman Construction, 159 N.H. 601 (2010)).
RSA 447:18
Open Questions Under New Hampshire Law
- RSA 447:15 creates a lien on public funds due the contractor, to be filed within 90 days after completion and acceptance, but the statute does not specify the filing office or procedure. This point is not settled under New Hampshire law. National Lien & Bond confirms it with a local New Hampshire attorney before relying on it.
Frequently Asked Questions
Is there a statutory mechanics lien form in New Hampshire?
No. New Hampshire does not use a recorded lien claim. The lien arises from furnishing labor or materials and is secured by an attachment recorded within 120 days (RSA 447:9, 447:10). The attachment papers follow RSA 511-A and Superior Court Rule 47.
Does a New Hampshire mechanics lien have to be notarized?
The notice of intention to claim a lien does not. The motion to attach must be made under oath (Super. Ct. R. 47), which in practice means a sworn or notarized motion. The writ and return need no separate notarization.
Where do I file a mechanics lien in New Hampshire?
File a motion to attach in court, then record the attested writ and return with the registry of deeds of each county where the land lies. The attachment must be made and recorded within 120 days after you last furnished labor or materials (RSA 447:9, 447:10).
Do New Hampshire subcontractors need to give a notice?
Yes. A claimant not in direct contract with the owner must give the owner written notice of its intention to claim a lien, ideally before furnishing. A late notice limits the lien to amounts then due or later becoming due to the owner's contractor (RSA 447:5, 447:6).
What form releases a mechanics lien in New Hampshire?
Once the attachment is dissolved or released, the claimant gives a discharge of attachment on request, which may be recorded (RSA 511-A:11). An owner may petition the court to release the attachment by substituting a bond with sufficient sureties (RSA 511:48).
What form do I use for a New Hampshire public project bond claim?
File a statement of claim within 90 days after the project is completed and accepted, with the Secretary of State or designated department for state work, or the superior court clerk for political subdivision work (RSA 447:17). Petition to enforce within 1 year after filing (RSA 447:18).
Related New Hampshire Resources
New Hampshire Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
New Hampshire Notice Requirements
Who must give notice, when, and how.
New Hampshire Lien Waivers
Statutory forms, waiver types, and enforceability rules.
New Hampshire Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about New Hampshire law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.