New Jersey Mechanics Lien Forms
Every notice, lien, enforcement, release, and bond claim document used on New Jersey construction projects, with who uses it, when it is due, and where it goes.
Quick Answer
On commercial work, a New Jersey claimant usually needs three documents in order: a Construction Lien Claim lodged with the county clerk within 90 days after last furnishing, service of the claim within 10 days after lodging, and a suit to enforce within 1 year after last furnishing (N.J.S.A. 2A:44A-6, 2A:44A-7, 2A:44A-14).
Residential construction adds two steps. Lodge a Notice of Unpaid Balance and Right to File Lien within 60 days after last furnishing and serve a demand for arbitration within 10 days after lodging it. Lodge the lien claim within 10 days after the arbitrator's determination and no later than 120 days after last furnishing (N.J.S.A. 2A:44A-21).
New Jersey has no general preliminary notice for private projects. The lien claim must substantially follow the statutory form and be signed, acknowledged, and verified by oath (N.J.S.A. 2A:44A-8). An owner or affected contractor may serve a demand that shortens the suit deadline to 30 days after receipt.
On public works, a claimant without a direct contract with the bonded contractor gives it written notice before commencing work. Every claimant provides a statement of amount due to the sureties and contractor, and sues no sooner than 90 days after that statement and within 1 year after last furnishing (N.J.S.A. 2A:44-145, 2A:44-146).
New Jersey construction liens are governed by the Construction Lien Law, N.J.S.A. 2A:44A-1 et seq. Payment bonds on public works are governed by N.J.S.A. 2A:44-143 to 2A:44-148, and the Municipal Mechanics' Lien Law, N.J.S.A. 2A:44-125 et seq., creates a lien on public contract funds. Liens cannot attach to public real property.
The Construction Lien Law prescribes forms for the Notice of Unpaid Balance and Right to File Lien, the Construction Lien Claim, the bond discharging a lien, and the owner's affidavit of payment. The lien claim must be signed, acknowledged, and verified by oath. The table below describes each document. National Lien & Bond does not reproduce statutory text on this page.
New Jersey Preliminary Notices
Notice of Unpaid Balance and Right to File Lien
- Who uses it
- Claimants on residential construction (required); claimants on nonresidential work (optional, for priority)
- When
- Residential: within 60 days after last furnishing. Nonresidential: within the 90-day lien period, before a competing conveyance or mortgage is recorded
- Served on or filed with
- Lodged with the county clerk where the property lies; residential notices are served within 10 days after lodging
- Notarization
- Signed, acknowledged, and verified
- Residential construction covers qualifying one-, two-, and three-family dwellings and residential units in developments for sale, not rental units.
- On nonresidential work the notice does not create a lien or extend the lien deadline.
N.J.S.A. 2A:44A-20, 2A:44A-21
New Jersey Notices Before Filing a Lien
Demand for Arbitration (Residential)
- Who uses it
- Claimants on residential construction, unless the parties agreed in writing to another dispute resolution method
- When
- Within 10 days after lodging the Notice of Unpaid Balance
- Served on or filed with
- Served on the owner and affected parties, with an expedited proceeding instituted through the American Arbitration Association
- Notarization
- Affidavit of lodging required
- The arbitrator ordinarily decides within 30 days whether the lien may be filed and in what amount. If setoffs are found, the claimant may have to post security within 10 days.
N.J.S.A. 2A:44A-21(b)
New Jersey Lien Claim and Service
Construction Lien Claim
- Who uses it
- Contractors, subcontractors, and suppliers with lien rights
- When
- Nonresidential: within 90 days after last furnishing. Residential: within 10 days after the arbitrator's determination and no later than 120 days after last furnishing
- Served on or filed with
- Lodged for record with the county clerk of the county where the property lies
- Notarization
- Signed, acknowledged, and verified by oath
- Warranty calls and work after completion or termination do not restart the 90-day clock.
- An amended lien claim must meet the original claim's conditions and deadlines.
N.J.S.A. 2A:44A-6, 2A:44A-8, 2A:44A-11
Service of Construction Lien Claim
- Who uses it
- Every lien claimant
- When
- Within 10 calendar days after lodging the claim
- Served on or filed with
- The owner or community association and, if applicable, the contractor or subcontractor against whom the claim is asserted, by personal service or simultaneous certified or registered mail and ordinary mail
- Notarization
- Not required
- Serve the copy stamped received for filing. A party served late must show material prejudice to defeat the lien.
N.J.S.A. 2A:44A-7
New Jersey Enforcing the Lien
Complaint to Enforce and Notice of Lis Pendens
- Who uses it
- Lien claimants
- When
- Within 1 year after last furnishing, or within 30 days after receiving a written demand to commence suit, whichever is earlier
- Served on or filed with
- Filed in the Superior Court of the county where the property lies; the lis pendens is filed with the county clerk
- Notarization
- Not required
- A contractual arbitration clause may stay the suit but does not excuse a timely protective filing.
N.J.S.A. 2A:44A-14, 2A:44A-24.1
New Jersey Releasing or Bonding Off a Lien
Certificate Discharging Lien Claim
- Who uses it
- Lien claimants, their successors, or attorneys
- When
- Within 30 days after payment, satisfaction, or settlement, or within 7 days after an interested party's demand
- Served on or filed with
- Filed with the county clerk
- Notarization
- Required (acknowledged or proved)
- If the claimant does not discharge a paid lien, the owner may file the statutory Owner Affidavit of Payment to Discharge Lien Claim at least 13 months after the lien, after 90 days' certified-mail notice to the claimant.
N.J.S.A. 2A:44A-30, 2A:44A-33
Bond Discharging Construction Lien
- Who uses it
- Owners, community associations, contractors, or subcontractors
- When
- At any time after the lien claim is filed
- Served on or filed with
- Filed with the county clerk; a cash deposit alternative is made with the Superior Court clerk
- Notarization
- Executed by principal and authorized surety; no claimant oath
- The bond or deposit is generally 110 percent of the claim, with a residential cap. It releases the land but does not establish that the claimant has been paid.
N.J.S.A. 2A:44A-31, 2A:44A-32
New Jersey Owner Notices and Forms
Demand to Commence Action
- Who uses it
- Owners, community associations, or the contractor or subcontractor against whose account the lien was filed
- When
- At any time after the lien claim is filed; suit is then due within 30 days after receipt
- Served on or filed with
- The lien claimant, personally or by certified mail, return receipt requested
- Notarization
- Not required
N.J.S.A. 2A:44A-14(a)(2)
Verified List of Subcontractors and Suppliers
- Who uses it
- Contractors and subcontractors, on written request of the owner, community association, or contractor
- When
- Within 10 days after the request
- Served on or filed with
- The requesting party
- Notarization
- Verified under oath
N.J.S.A. 2A:44A-37
New Jersey Public Works and Payment Bond Claims
Notice of Furnishing (Public Payment Bond)
- Who uses it
- Claimants on bonded public works without a direct contract with the bonded contractor
- When
- Before commencing work
- Served on or filed with
- The bonded contractor, by certified mail or another method that provides proof of delivery
- Notarization
- Not required
- A late notice protects only what is furnished from the date of the notice forward.
N.J.S.A. 2A:44-145
Statement of Amount Due
- Who uses it
- Every unpaid claimant on a bonded public work
- When
- Within 1 year after last work or delivery, and early enough to allow the 90-day wait before the 1-year suit bar
- Served on or filed with
- The sureties and the bonded contractor
- Notarization
- Not required
N.J.S.A. 2A:44-145
Suit on Public Payment Bond
- Who uses it
- Unpaid claimants who provided a statement of amount due
- When
- No sooner than 90 days after providing the statement, and within 1 year after last furnishing
- Served on or filed with
- Filed in court in the claimant's own name
- Notarization
- Not required
- The bond may be waived on specified State contracts up to $200,000 and local contracts up to $100,000.
N.J.S.A. 2A:44-143, 2A:44-145, 2A:44-146
Notice of the Delivery of Labor or Materials (Municipal Lien)
- Who uses it
- Claimants furnishing to a subcontractor on a covered local public agency contract
- When
- Within 20 days after first furnishing to the subcontractor
- Served on or filed with
- Filed with the municipal clerk, county chief financial officer, or the chairman of the commission, board, or authority, as appropriate
- Notarization
- Not required; signed
- A late notice preserves the lien for furnishing on or after the notice, subject to the statute's exceptions.
N.J.S.A. 2A:44-128
Notice of Lien Claim (Municipal Lien)
- Who uses it
- Unpaid claimants on covered local public agency contracts
- When
- Before the whole work is completed and accepted, or within 60 days afterward
- Served on or filed with
- Filed with the head officer or the secretary or clerk of the public agency
- Notarization
- Verified by oath of the claimant or agent
- The lien attaches to contract funds, not public land. An enforcement action must be brought in the Superior Court within 60 days after completion and acceptance of the whole work.
N.J.S.A. 2A:44-132, 2A:44-133, 2A:44-138
Frequently Asked Questions
Is there a statutory construction lien form in New Jersey?
Yes. The Construction Lien Claim must be substantially in the form set out in N.J.S.A. 2A:44A-8, and the Notice of Unpaid Balance and Right to File Lien in the form in 2A:44A-20. The statute also prescribes the bond discharging a lien (2A:44A-31).
Does a New Jersey construction lien have to be notarized?
Yes. The Construction Lien Claim must be signed, acknowledged, and verified by oath (N.J.S.A. 2A:44A-6, 2A:44A-8). A certificate discharging the lien must also be acknowledged or proved (2A:44A-30).
Where do I file a construction lien in New Jersey?
Lodge the Construction Lien Claim with the county clerk of the county where the property lies, within 90 days after last furnishing on nonresidential work. Serve a stamped copy on the owner and applicable contractor or subcontractor within 10 days after lodging (N.J.S.A. 2A:44A-6, 2A:44A-7).
What extra steps apply to a New Jersey residential lien?
Lodge a Notice of Unpaid Balance within 60 days after last furnishing, serve it, and demand arbitration within 10 days after lodging. Lodge the lien claim within 10 days after the arbitrator's determination and no later than 120 days after last furnishing (N.J.S.A. 2A:44A-21).
What form releases a construction lien in New Jersey?
The claimant files an acknowledged certificate discharging the lien within 30 days after payment or 7 days after demand (N.J.S.A. 2A:44A-30). An owner or contractor may also file a statutory Bond Discharging Construction Lien or make a cash deposit, generally 110 percent of the claim (2A:44A-31).
Can a New Jersey owner force me to sue sooner?
Yes. The owner, community association, or the contractor or subcontractor against whose account the lien was filed may serve a written demand. Suit is then due within 30 days after receipt, or within 1 year after last furnishing if earlier (N.J.S.A. 2A:44A-14).
What form do I use for a New Jersey public project bond claim?
New Jersey has no prescribed bond claim form. Give the bonded contractor written notice before commencing work if you lack a direct contract, provide a statement of amount due to the sureties and contractor, and sue after 90 days and within 1 year after last furnishing (N.J.S.A. 2A:44-145, 2A:44-146).
Related New Jersey Resources
New Jersey Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
New Jersey Notice Requirements
Who must give notice, when, and how.
New Jersey Lien Waivers
Statutory forms, waiver types, and enforceability rules.
New Jersey Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about New Jersey law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.