The Step That Replaces a Preliminary Notice
New York does not require a notice before the lien. It requires that the notice of lien itself be served, and that proof of that service be filed. A notice of lien that is filed on time and never properly served does not survive.
Service on the Owner
Within 5 days before or 30 days after filing the notice of lien, the lienor must serve a copy on the owner. Lien Law § 11.
For an owner who is a natural person, the statute lists these methods:
For a corporate owner, service is made by delivering the copy personally within the state to the president, vice-president, secretary or clerk to the corporation, the cashier, treasurer, or a director or managing agent, or, if such an officer cannot be found within the state, by affixing a copy conspicuously on the property between 9 in the forenoon and 4 in the afternoon, or by registered or certified mail addressed to the corporation's last known place of business.
- Delivering it to the owner personally, or if the owner cannot be found, to the owner's agent or attorney
- Leaving it at the owner's last known place of residence in the city or town where the property is situated, with a person of suitable age and discretion
- Registered or certified mail addressed to the owner's last known place of residence
- If the owner has no such residence in that city or town, or cannot be found, and has no agent or attorney, affixing a copy conspicuously on the property between 9 in the forenoon and 4 in the afternoon
Service on the Contractor or Subcontractor
Within 5 days before or within 30 days after filing, the lienor must also serve a copy by certified mail on the contractor or subcontractor for whom it was employed or to whom it furnished materials, or, if the lienor is a contractor or subcontractor, on the person with whom its contract was made. Lien Law § 11-b.
A lienor having a direct contractual relationship with a subcontractor or a sub-subcontractor, but not with the contractor, must also serve a copy by certified mail on the contractor.
The same rule applies to an amendment of a notice of lien filed under Lien Law § 12-a.
Proof of Service Within 35 Days
Failure to file proof of service with the county clerk within 35 days after the notice of lien is filed terminates the notice as a lien. Both Lien Law § 11 and Lien Law § 11-b say so in the same words.
The 35 days run from the filing of the notice of lien, not from the date of service. A lienor that serves on day 30 has 5 days left to file proof.
Section 11-b carries one more consequence. A lienor, or a person acting for a lienor, who fails to serve the copy that section requires is liable for reasonable attorney's fees, costs, and expenses, as determined by the court, incurred in obtaining the copy.
Until You Serve, the Owner Can Keep Paying
Until service of the notice has been made as Lien Law § 11 provides, an owner without knowledge of the lien is protected in any payment made in good faith to any contractor or other person claiming a lien. Serving at the front of the permitted period, instead of the end, closes that gap.
Public Improvement Liens
The period is shorter on public work. Within 5 days before or simultaneously with filing a notice of lien on a public improvement, the lienor must serve a copy by certified mail on the contractor or subcontractor above it, and the notice of lien must contain or be filed with proof of that service. Failure to file proof of service renders the notice of lien a nullity. Lien Law § 11-c.
Frequently Asked Questions
Do you have to serve a mechanics lien after filing it in New York?
Yes. A copy of the notice of lien must be served on the owner within 5 days before or 30 days after filing (Lien Law § 11), and by certified mail on the contractor or subcontractor above the lienor within the same period (Lien Law § 11-b). A lienor whose contract is with a subcontractor or sub-subcontractor, and not with the prime contractor, must also serve the prime contractor by certified mail.
What is the 35-day rule for a New York mechanics lien?
Proof of service must be filed with the county clerk within 35 days after the notice of lien is filed. Failure to file it terminates the notice as a lien. Lien Law §§ 11, 11-b.
Can a New York notice of lien be served on the owner by mail?
Yes. Lien Law § 11 permits registered or certified mail addressed to a natural person's last known place of residence, or to a corporation's last known place of business.
How is a New York public improvement lien served?
By certified mail on the contractor or subcontractor above the lienor, within 5 days before or simultaneously with filing. Proof of service must be on or filed with the notice of lien, and failure to file it renders the notice a nullity. Lien Law § 11-c.
Related New York Resources
Explore other critical compliance areas for New York construction mechanic lien law.
Notice Requirements
Itemized statement demands, trustee examination rights, and service requirements for private and public works under New York law
Mechanic Lien Deadlines
Notice of Mechanic Lien filing deadlines (8 months private, 4 months single family dwelling), retainage rules, proof of service requirements, and public works mechanic lien filing
Mechanic Lien Enforcement Deadlines
1-year mechanic lien enforcement period, mechanic lien extension procedures, Notice of Pendency rules, private bond suit deadlines, and public works enforcement
New York Mechanics Lien Forms
Every notice, lien, release, and bond claim form used in New York
New York Lien Waivers
Statutory waiver forms, waiver types, and enforceability rules in New York
New York Overview
Return to the main New York construction mechanic lien law page