Does a General Contractor Need to Send a Preliminary Notice in New York?

No. The Steps That Decide a Contractor's Lien Come at Filing, Not Before

No Preliminary Notice Step

New York does not make a preliminary notice a condition of a contractor's lien on private work. Under Lien Law § 3, a contractor who performs labor or furnishes materials for the improvement of real property with the consent or at the request of the owner has a lien from the time of filing a notice of lien. The sections that govern the contents of the notice of lien, the time to file it, and its service (Lien Law §§ 9, 10, and 11) set no notice step that must come before filing.

Lien Law § 2(9) defines a contractor as a person who enters into a contract with the owner of real property for its improvement. That is the general contractor on an ordinary private project.

What Is Required: Service on the Owner

The notice requirement in New York attaches to the notice of lien itself. Within 5 days before or 30 days after filing, the lienor must serve a copy of the notice of lien on the owner. Lien Law § 11.

For an owner who is a natural person, the statute allows personal delivery, delivery at the owner's last known residence in the city or town where the property lies to a person of suitable age and discretion, or registered or certified mail to the last known place of residence. For a corporate owner, it allows delivery to a listed officer, director, or managing agent within the state, or registered or certified mail to the last known place of business.

Proof of that service must be filed with the county clerk within 35 days after the notice of lien is filed. Failure to file it terminates the notice as a lien. Lien Law § 11.

There is a second reason to serve promptly. Until service is made, an owner without knowledge of the lien is protected in any payment made in good faith to a contractor or other person claiming a lien. Lien Law § 11.

What a General Contractor Should Calendar

File the notice of lien with the clerk of the county where the property is situated during the work or within 8 months after completion of the contract, final performance of the work, or final furnishing of materials, dating from the last item of work performed or materials furnished. Where the property is improved or to be improved with a single family dwelling, the period is 4 months. Lien Law § 10. The statute defines single family dwelling to exclude certain developer-owned dwellings in filed subdivisions, so the 4-month period does not cover every single family house.

The lien then lasts 1 year after the notice of lien is filed unless, within that year, an action to foreclose is commenced and a notice of pendency is filed with the county clerk, or an extension is filed. A lien on a single family dwelling can be extended only by court order. Lien Law § 17.

Public Improvements Work Differently

On a public improvement, Lien Law § 5 gives the lien on public funds to a person performing labor for or furnishing materials to a contractor or its subcontractor. The payment bond under State Finance Law § 137 is furnished by the contractor and guarantees payment to persons furnishing labor or materials to the contractor or any subcontractors. Both remedies are written for those working under the contractor. The contractor holding the public contract has no public improvement lien for its own unpaid contract balance.

Frequently Asked Questions

Does a general contractor need a preliminary notice in New York?

No. Lien Law § 3 gives a contractor a lien from the time of filing a notice of lien, and Lien Law §§ 9, 10, and 11 set no notice that must be sent before filing. The required notice step is service of a copy of the notice of lien on the owner.

When must a New York contractor serve the notice of lien on the owner?

Within 5 days before or 30 days after filing the notice of lien. Lien Law § 11. Proof of service must be filed with the county clerk within 35 days after the notice of lien is filed, or the notice terminates as a lien.

Why does prompt service matter to a New York contractor?

Under Lien Law § 11, until the notice of lien has been served, an owner without knowledge of the lien is protected in any payment made in good faith to a contractor or other person claiming a lien.

How long does a New York general contractor have to file?

During the work or within 8 months, dating from the last item of work performed or materials furnished, or within 4 months where the property is improved or to be improved with a single family dwelling. Lien Law § 10.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.