NY Supplier Preliminary Notice

Does a Material Supplier Need to Send a Preliminary Notice in New York?

Not on Private Work. On Public Work, a Bond Claim Can Carry a 120-Day Notice

Who Counts as a Materialman

Lien Law § 3 gives a lien to a materialman who furnishes materials for the improvement of real property with the consent or at the request of the owner or of the owner's agent, contractor, or subcontractor.

Lien Law § 2(12) defines a materialman as a person who furnishes material, or the use of machinery, tools, or equipment, or compressed gases for welding or cutting, or fuel or lubricants for machinery or motor vehicles, to an owner, contractor, or subcontractor. Equipment rental is covered at its reasonable rental value for the period of actual use.

Note to whom the material must be furnished: an owner, a contractor, or a subcontractor. A supplier whose only customer is another supplier is not described by that definition.

Materials actually manufactured for the property but not delivered are deemed materials furnished. Lien Law § 3.

No Preliminary Notice on Private Work

A supplier's lien arises from the time of filing a notice of lien. Lien Law § 3. The sections on contents, filing, and service (Lien Law §§ 9, 10, 11, and 11-b) set no notice that must be sent before filing.

The required notices come at filing. Serve a copy of the notice of lien on the owner within 5 days before or 30 days after filing (Lien Law § 11). Within the same period, serve a copy by certified mail on the contractor or subcontractor to whom the materials were furnished, and, if that customer was a subcontractor or sub-subcontractor, on the contractor as well (Lien Law § 11-b). File proof of service with the county clerk within 35 days after the notice of lien is filed, or the notice terminates as a lien.

Why Suppliers Should Still File Early

A supplier to a contractor or subcontractor cannot lien for more than the sum earned and unpaid on the contract at the time of filing the notice of lien, plus any sum subsequently earned. Lien Law § 4(1). A supplier on an open account that waits until the end of the 8-month period may find that little remains unpaid above it.

The notice of lien may be filed at any time during the progress of the work and the furnishing of the materials. Lien Law § 10. The statute does not require a supplier to wait for the job to end.

Public Work: The 120-Day Bond Notice

The one early notice a New York supplier may owe is on a public improvement payment bond. A person with a direct contractual relationship with a subcontractor, but no contractual relationship express or implied with the contractor that furnished the bond, has no right of action on the bond unless it gave written notice to that contractor within 120 days from the date on which the last of the labor was performed or the last of the material was furnished. State Finance Law § 137(3).

The notice must state with substantial accuracy the amount claimed and the name of the party to whom the material was furnished. It is served by personal delivery to the contractor or by registered mail, postage prepaid, addressed to the contractor at any place where it maintains an office or conducts business, or at its residence. Notice actually received by the contractor by other means is deemed sufficient.

A supplier that sold directly to the contractor does not owe this notice. It measures from last furnishing, so it is a claim notice and not a notice due at the start of the job.

Frequently Asked Questions

Does a material supplier need a preliminary notice in New York?

Not on private work. The lien arises from filing a notice of lien under Lien Law § 3, and Lien Law §§ 9, 10, 11, and 11-b set no notice that must come before filing. The supplier serves the notice of lien on the owner and on the contractor or subcontractor it supplied.

Does a supplier to another supplier have a New York mechanics lien?

Lien Law § 2(12) defines a materialman as a person who furnishes material to an owner, contractor, or subcontractor. A supplier whose only customer is another supplier is not described by that definition.

Can an equipment rental company file a lien in New York?

The definition of materialman in Lien Law § 2(12) includes a person who furnishes the use of machinery, tools, or equipment to an owner, contractor, or subcontractor, and furnishing material includes the reasonable rental value for the period of actual use.

What notice does a supplier owe on a New York public payment bond?

A supplier that dealt with a subcontractor and has no contractual relationship with the contractor must give the contractor written notice within 120 days from the date the last material was furnished, stating with substantial accuracy the amount claimed and the party supplied. State Finance Law § 137(3).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.