No Preliminary Notice Step
A subcontractor in New York does not send a preliminary notice to preserve lien rights on private work. Lien Law § 3 gives a subcontractor who performs labor or furnishes materials with the consent or at the request of the owner, or of the owner's agent, contractor, or subcontractor, a lien from the time of filing a notice of lien. The sections on contents, filing, and service (Lien Law §§ 9, 10, 11, and 11-b) set no notice that must precede filing.
The definition is broad. Under Lien Law § 2(10), a subcontractor is a person who enters into a contract with a contractor or with a subcontractor for the improvement. A subcontractor hired by another subcontractor is within the definition.
Two Service Requirements at Filing
First, serve the owner. Within 5 days before or 30 days after filing, the lienor must serve a copy of the notice of lien on the owner by one of the methods in Lien Law § 11.
Second, serve the parties above you. Within 5 days before or within 30 days after filing, the lienor must serve a copy by certified mail on the contractor or subcontractor for whom it was employed or to whom it furnished materials, or, if the lienor is itself a contractor or subcontractor, on the party with whom its contract was made. A lienor with a direct contract with a subcontractor or sub-subcontractor, but not with the contractor, must also serve a copy by certified mail on the contractor. Lien Law § 11-b.
Both sections state the same consequence. Failure to file proof of service with the county clerk within 35 days after the notice of lien is filed terminates the notice as a lien. Lien Law §§ 11, 11-b. Section 11-b adds that a lienor who fails to serve the copy it requires is liable for reasonable attorney's fees, costs, and expenses incurred in obtaining the copy.
The Limit That Does the Work a Preliminary Notice Does Elsewhere
New York protects the owner by limiting the amount of the lien. Where labor is performed for, or materials furnished to, a contractor or subcontractor, the lien cannot be for a sum greater than the sum earned and unpaid on the contract at the time of filing the notice of lien, and any sum subsequently earned on it. Lien Law § 4(1).
The same subdivision provides that the owner is not liable, by reason of all liens under the article, for more than the value or agreed price of the labor and materials remaining unpaid at the time the notices of lien are filed.
Timing therefore matters even without a preliminary notice. Until the notice of lien is served, an owner without knowledge of the lien is also protected in payments made in good faith to a contractor. Lien Law § 11. Each payment made up the chain before filing and service reduces what the lien can reach.
Filing Deadline
File during the work or within 8 months after completion of the contract, final performance of the work, or final furnishing of materials, dating from the last item of work performed or materials furnished. On real property improved or to be improved with a single family dwelling, the period is 4 months. Lien Law § 10. The statute defines single family dwelling to exclude certain developer-owned dwellings in filed subdivisions, so the 4-month period does not cover every single family house.
Frequently Asked Questions
Does a subcontractor need a preliminary notice in New York?
No. Under Lien Law § 3 the lien arises from the filing of a notice of lien, and Lien Law §§ 9, 10, 11, and 11-b set no notice that must come before filing. The required steps are service of the notice of lien and filing proof of that service.
Who must a New York subcontractor serve with the notice of lien?
The owner under Lien Law § 11, and by certified mail the contractor or subcontractor that hired it under Lien Law § 11-b. A lienor whose contract is with a subcontractor or sub-subcontractor and not with the contractor must also send a copy to the contractor by certified mail.
What happens if a New York subcontractor does not file proof of service?
Failure to file proof of service with the county clerk within 35 days after the notice of lien is filed terminates the notice as a lien. Lien Law §§ 11, 11-b.
Is a New York subcontractor's lien limited by payments the owner already made?
Yes. Under Lien Law § 4(1) the lien cannot exceed the sum earned and unpaid on the contract at the time the notice of lien is filed, plus any sum subsequently earned on it.
Related New York Resources
Explore other critical compliance areas for New York construction mechanic lien law.
Notice Requirements
Itemized statement demands, trustee examination rights, and service requirements for private and public works under New York law
Mechanic Lien Deadlines
Notice of Mechanic Lien filing deadlines (8 months private, 4 months single family dwelling), retainage rules, proof of service requirements, and public works mechanic lien filing
Mechanic Lien Enforcement Deadlines
1-year mechanic lien enforcement period, mechanic lien extension procedures, Notice of Pendency rules, private bond suit deadlines, and public works enforcement
New York Mechanics Lien Forms
Every notice, lien, release, and bond claim form used in New York
New York Lien Waivers
Statutory waiver forms, waiver types, and enforceability rules in New York
New York Overview
Return to the main New York construction mechanic lien law page