1 Year From Filing, and the Action Alone Is Not Enough

1 Year From the Filing of the Notice of Lien

No lien under Article 2 is a lien for longer than 1 year after the notice of lien has been filed, unless within that time an action is commenced to foreclose the lien and a notice of the pendency of the action is filed with the county clerk of the county in which the notice of lien is filed. Lien Law § 17.

The period runs from the filing date of the notice of lien, not from the last day of work. The filing deadline and the enforcement deadline are measured from different events.

Two Filings, Not One

The statute requires both the action and the notice of pendency within the year. The notice of pendency must contain the names of the parties to the action, the object of the action, a brief description of the real property affected, and the time of filing the notice of lien.

The two failures have different results. The failure to file a notice of pendency does not abate the action as to any person liable for the payment of the debt specified in the notice of lien, and the action may be prosecuted to judgment against that person. Lien Law § 17. The claim for the money can continue. The lien on the property is what depends on the notice of pendency.

A lien continued by a notice of pendency also depends on that notice remaining in effect. It terminates as a lien after the notice of pendency has been cancelled as provided in CPLR 6514 or has ceased to be effective as constructive notice as provided in CPLR 6513. Lien Law § 17.

Alternatives to Suing Within the Year

An extension filed with the county clerk within 1 year from the filing of the original notice of lien continues the lien for up to 1 year from the filing of the extension. That route is not available for a lien on real property improved or to be improved with a single family dwelling, which may be extended only by court order. Lien Law § 17.

A lienor made a party defendant in an action to enforce another lien is also protected. If the plaintiff or that defendant has filed a notice of pendency within the time the section prescribes, the defendant's lien is continued, and the action is deemed an action to enforce it.

The Period Can Be Shortened

A lienor may be required to act sooner. Under Lien Law § 59, a notice may be served on the lienor requiring it to commence an action to enforce the lien within a time specified in the notice, not less than 30 days from the time of service, or to show cause why the notice of lien should not be vacated and cancelled. If the lienor does not commence the action as directed, a court of record may vacate and cancel the lien by order. Cancellation is by court order. Serving the notice does not cancel the lien, and neither does the lienor's failure to respond.

The notice is served on the lienor personally or by leaving it at the lienor's last known place of residence with a person of suitable age, with directions to deliver it to the lienor.

Bonded Liens and Public Improvement Liens

The provisions of Lien Law § 17 on continuing liens apply to liens discharged by deposit or by order on the filing of an undertaking. Where a lien is discharged by deposit or by order, a notice of pendency is not filed.

A public improvement lien runs on the same 1-year period from the filing of the notice of lien, but the notice of pendency or the extension is filed with the comptroller of the state or the financial officer of the public corporation with whom the notice of lien was filed. Lien Law § 18. The 3-year expiration rule of CPLR 6513 does not govern that notice of pendency, so it does not need periodic 3-year renewal.

Frequently Asked Questions

How long do you have to enforce a mechanics lien in New York?

1 year after the notice of lien is filed. Within that year an action to foreclose must be commenced and a notice of pendency filed with the county clerk, or an extension must be filed. A lien on a single family dwelling can be extended only by court order, and no notice of pendency is filed where the lien has been discharged by deposit or undertaking. Lien Law § 17.

Is filing the foreclosure action enough to keep a New York lien?

No. Lien Law § 17 requires a notice of pendency as well. Without it, the action may proceed to judgment against the person liable for the debt, but the lien is not continued.

Can an owner force a New York lienor to sue sooner?

Under Lien Law § 59, a notice may be served on the lienor requiring it to commence an action within a time specified, not less than 30 days from service, or show cause why the lien should not be vacated. If the lienor does not act, a court of record may vacate and cancel the lien.

Does the New York enforcement year run from last furnishing?

No. It runs from the filing of the notice of lien. Lien Law § 17.