North Dakota Mechanics Lien Forms

North Dakota Mechanics Lien Forms

Every notice, lien, enforcement, release, and bond claim document used on North Dakota construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

A North Dakota claimant usually needs four documents in order: a written notice of intent to claim a lien mailed at least 10 days before recording, the construction lien recorded within 90 days after last furnishing, a notice of intent to enforce, and a foreclosure action with a lis pendens (N.D.C.C. §§ 35-27-02, 35-27-13, 35-27-24, 35-27-25).

The notice of intent to claim a lien goes to the owner by certified mail at least 10 days before the lien is recorded. It applies to every claimant, including a prime contractor. North Dakota has no preliminary notice at the start of work (N.D.C.C. § 35-27-02).

Record the lien with the county recorder within 90 days after your contribution is complete to keep priority against good-faith purchasers, encumbrancers, and owner payments. A later lien filed within 3 years after the first item was furnished remains valid against the owner (N.D.C.C. §§ 35-27-13, 35-27-14).

Before suing, give the owner written notice of intent to enforce: personal service at least 10 days before suit, or registered mail at least 20 days before suit. Suit and a recorded lis pendens are due within 3 years after recording, or within 30 days after an owner's demand (N.D.C.C. §§ 35-27-24, 35-27-25).

North Dakota construction liens are governed by Chapter 35-27 of the North Dakota Century Code. Payment bonds on public improvements are governed by Chapter 48-01.2. Release of a lien by undertaking is governed by Chapter 35-21, and the discharge of a paid lien by N.D.C.C. § 35-01-27.

North Dakota statutes describe the content of most lien documents rather than prescribing fill-in forms. The table below lists each document, who uses it, and when it is due. National Lien & Bond does not reproduce statutory text on this page.

North Dakota Notices Before Filing a Lien

Notice of Intention to Claim a Construction Lien

Required When It Applies
Who uses it
Every lien claimant, including prime contractors, subcontractors, and suppliers
When
At least 10 days before recording the construction lien
Served on or filed with
The legal or equitable owner, by certified mail
Notarization
Not required
  • The statute requires written notice that a lien will be claimed; it does not prescribe a form or title.

N.D.C.C. § 35-27-02(4)

North Dakota Lien Claim and Service

Construction Lien

Required When It Applies
Who uses it
Unpaid contractors, subcontractors, and suppliers who improve real property
When
Within 90 days after the claimant's contribution is complete for full priority; no lien may be filed more than 3 years after the first item of material is furnished
Served on or filed with
Recorded with the county recorder of the county where the property lies
Notarization
Not required by the lien statute, but the lien must meet general recording requirements, usually an acknowledgment
  • The lien must state the property description, the amount due, the first and last dates of contribution, and the person with whom the claimant contracted.
  • A good-faith mortgage financing the improvement has priority unless the lien is recorded before the mortgage.

N.D.C.C. §§ 35-27-13, 35-27-14, 47-19-03

Itemized and Verified Account of Claim

Required When It Applies
Who uses it
Lien claimants who receive an owner's written request
When
On request made by the owner within 15 days after completion of the contract; suit may not begin until 10 days after the account is furnished
Served on or filed with
The owner
Notarization
Verification required

N.D.C.C. § 35-27-09

North Dakota Enforcing the Lien

Notice of Intention to Enforce Lien

Required When It Applies
Who uses it
Lienholders preparing to foreclose
When
At least 10 days before suit if personally served, or at least 20 days before suit if sent by registered mail
Served on or filed with
The legal or equitable owner
Notarization
Not required
  • This notice is separate from the notice given before recording the lien.

N.D.C.C. § 35-27-24

Foreclosure Action and Lis Pendens

Required When It Applies
Who uses it
Lienholders
When
Within 3 years after the lien is recorded, or within 30 days after delivery of an owner's demand
Served on or filed with
Suit filed in the district court of the county where the property lies; lis pendens recorded with the county recorder
Notarization
Not required
  • Filing suit alone is not enough. The lis pendens must also be recorded within the deadline or the lien is deemed satisfied.

N.D.C.C. §§ 35-27-24, 35-27-25, 28-05-07

North Dakota Releasing or Bonding Off a Lien

Certificate of Discharge

Required When It Applies
Who uses it
Holders of a lien that has been paid
When
Within 60 days after satisfaction or 30 days after the owner's written demand, whichever is shorter
Served on or filed with
Recorded with the county recorder
Notarization
Acknowledgment required
  • Failure to discharge creates liability for actual damages and $100 in exemplary damages.

N.D.C.C. § 35-01-27

Application, Affidavit, and Undertaking for Release of Lien

Required When It Applies
Who uses it
Owners or holders of a substantial interest who dispute a lien
When
At any time after the lien is filed
Served on or filed with
Filed with the clerk of district court of the county where the lien is filed and served on the lien claimant
Notarization
Supporting affidavit required
  • The undertaking requires two sureties in at least the amount of the lien. The claimant has seven days after service to object to the sureties.

N.D.C.C. §§ 35-21-01 to 35-21-04

North Dakota Owner Notices and Forms

Owner's Request for Itemized Account

Optional
Who uses it
Owners and other qualifying interested persons
When
Within 15 days after completion of the contract
Served on or filed with
The lien claimant
Notarization
Not required

N.D.C.C. § 35-27-09

Owner's Demand to Commence Suit

Optional
Who uses it
Owners or their representatives
When
At any time after the lien is recorded
Served on or filed with
Delivered to the lienholder and filed with the county recorder
Notarization
Not required by the statute; recording requirements apply
  • The demand must warn that the lien is forfeited unless suit is commenced and a lis pendens recorded within 30 days after delivery.

N.D.C.C. § 35-27-25

Owner's Notice Objecting to Unauthorized Improvements

Optional
Who uses it
Owners or interested landholders who did not authorize the work
When
Served within five days after learning of the work, or posted conspicuously on the property
Served on or filed with
The person making the improvement, or posted at the property
Notarization
Not required

N.D.C.C. § 35-27-07

North Dakota Public Works and Payment Bond Claims

Notice of Claim on Public Improvement Bond

Required When It Applies
Who uses it
Claimants with a contract with a subcontractor but no contract with the prime contractor
When
Within 90 days after the claimant completes its contribution
Served on or filed with
The prime contractor, by registered mail
Notarization
Not required
  • The notice must state with substantial accuracy the amount claimed and the party for whom the work was done.

N.D.C.C. § 48-01.2-11

Action on Contractor's Bond

Required When It Applies
Who uses it
Unpaid claimants on bonded public improvements
When
After 90 days without payment following completion of the claimant's contribution, and within 1 year after completion and acceptance of the project
Served on or filed with
Filed in court against the contractor and surety
Notarization
Not required
  • A claimant may obtain a certified copy of the bond and contract from the governing body by affidavit.

N.D.C.C. §§ 48-01.2-10, 48-01.2-11, 48-01.2-12

Frequently Asked Questions

Is there a statutory mechanics lien form in North Dakota?

No. North Dakota prescribes the content of a construction lien, not a fill-in form. The lien must state the property description, the amount due, the first and last dates of contribution, and the person with whom the claimant contracted (N.D.C.C. § 35-27-13).

Does a North Dakota construction lien have to be notarized?

The lien statute does not require verification, but a lien must be recordable. A privately signed instrument generally needs an acknowledgment or other authorized proof of execution, with exceptions such as an instrument signed by a North Dakota attorney with an identification number (N.D.C.C. §§ 35-27-13, 47-19-03).

Where do I file a mechanics lien in North Dakota?

Record the construction lien with the county recorder of the county where the property lies, within 90 days after your contribution is complete for full priority. Mail the owner a written notice by certified mail at least 10 days before recording (N.D.C.C. §§ 35-27-02, 35-27-13).

What notice do I give before suing on a North Dakota lien?

Give the owner written notice of intent to enforce the lien, by personal service at least 10 days before suit or by registered mail at least 20 days before suit (N.D.C.C. § 35-27-24). This is separate from the notice given before recording.

What form releases a mechanics lien in North Dakota?

A paid lienholder records an acknowledged certificate of discharge within 60 days after satisfaction, or 30 days after the owner's written demand if shorter (N.D.C.C. § 35-01-27). A disputed lien can be released by an application, affidavit, and undertaking with two sureties filed with the clerk of district court (N.D.C.C. § 35-21-02).

Can a North Dakota owner shorten the time to foreclose a lien?

Yes. An owner may deliver a written demand to the lienholder and file it with the county recorder. The lienholder must then commence suit and record a lis pendens within 30 days after delivery, or the lien is forfeited (N.D.C.C. § 35-27-25).

What form do I use for a North Dakota public project bond claim?

A claimant with no contract with the prime contractor sends the prime contractor written notice by registered mail within 90 days after completing its contribution, stating the amount and the party supplied. Suit on the bond is due within 1 year after completion and acceptance of the project (N.D.C.C. §§ 48-01.2-11, 48-01.2-12).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.