Quick Answer
A North Dakota claimant usually needs four documents in order: a written notice of intent to claim a lien mailed at least 10 days before recording, the construction lien recorded within 90 days after last furnishing, a notice of intent to enforce, and a foreclosure action with a lis pendens (N.D.C.C. §§ 35-27-02, 35-27-13, 35-27-24, 35-27-25).
The notice of intent to claim a lien goes to the owner by certified mail at least 10 days before the lien is recorded. It applies to every claimant, including a prime contractor. North Dakota has no preliminary notice at the start of work (N.D.C.C. § 35-27-02).
Record the lien with the county recorder within 90 days after your contribution is complete to keep priority against good-faith purchasers, encumbrancers, and owner payments. A later lien filed within 3 years after the first item was furnished remains valid against the owner (N.D.C.C. §§ 35-27-13, 35-27-14).
Before suing, give the owner written notice of intent to enforce: personal service at least 10 days before suit, or registered mail at least 20 days before suit. Suit and a recorded lis pendens are due within 3 years after recording, or within 30 days after an owner's demand (N.D.C.C. §§ 35-27-24, 35-27-25).
North Dakota construction liens are governed by Chapter 35-27 of the North Dakota Century Code. Payment bonds on public improvements are governed by Chapter 48-01.2. Release of a lien by undertaking is governed by Chapter 35-21, and the discharge of a paid lien by N.D.C.C. § 35-01-27.
North Dakota statutes describe the content of most lien documents rather than prescribing fill-in forms. The table below lists each document, who uses it, and when it is due. National Lien & Bond does not reproduce statutory text on this page.
North Dakota Notices Before Filing a Lien
Notice of Intention to Claim a Construction Lien
- Who uses it
- Every lien claimant, including prime contractors, subcontractors, and suppliers
- When
- At least 10 days before recording the construction lien
- Served on or filed with
- The legal or equitable owner, by certified mail
- Notarization
- Not required
- The statute requires written notice that a lien will be claimed; it does not prescribe a form or title.
N.D.C.C. § 35-27-02(4)
North Dakota Lien Claim and Service
Construction Lien
- Who uses it
- Unpaid contractors, subcontractors, and suppliers who improve real property
- When
- Within 90 days after the claimant's contribution is complete for full priority; no lien may be filed more than 3 years after the first item of material is furnished
- Served on or filed with
- Recorded with the county recorder of the county where the property lies
- Notarization
- Not required by the lien statute, but the lien must meet general recording requirements, usually an acknowledgment
- The lien must state the property description, the amount due, the first and last dates of contribution, and the person with whom the claimant contracted.
- A good-faith mortgage financing the improvement has priority unless the lien is recorded before the mortgage.
N.D.C.C. §§ 35-27-13, 35-27-14, 47-19-03
Itemized and Verified Account of Claim
- Who uses it
- Lien claimants who receive an owner's written request
- When
- On request made by the owner within 15 days after completion of the contract; suit may not begin until 10 days after the account is furnished
- Served on or filed with
- The owner
- Notarization
- Verification required
N.D.C.C. § 35-27-09
North Dakota Enforcing the Lien
Notice of Intention to Enforce Lien
- Who uses it
- Lienholders preparing to foreclose
- When
- At least 10 days before suit if personally served, or at least 20 days before suit if sent by registered mail
- Served on or filed with
- The legal or equitable owner
- Notarization
- Not required
- This notice is separate from the notice given before recording the lien.
N.D.C.C. § 35-27-24
Foreclosure Action and Lis Pendens
- Who uses it
- Lienholders
- When
- Within 3 years after the lien is recorded, or within 30 days after delivery of an owner's demand
- Served on or filed with
- Suit filed in the district court of the county where the property lies; lis pendens recorded with the county recorder
- Notarization
- Not required
- Filing suit alone is not enough. The lis pendens must also be recorded within the deadline or the lien is deemed satisfied.
N.D.C.C. §§ 35-27-24, 35-27-25, 28-05-07
North Dakota Releasing or Bonding Off a Lien
Certificate of Discharge
- Who uses it
- Holders of a lien that has been paid
- When
- Within 60 days after satisfaction or 30 days after the owner's written demand, whichever is shorter
- Served on or filed with
- Recorded with the county recorder
- Notarization
- Acknowledgment required
- Failure to discharge creates liability for actual damages and $100 in exemplary damages.
N.D.C.C. § 35-01-27
Application, Affidavit, and Undertaking for Release of Lien
- Who uses it
- Owners or holders of a substantial interest who dispute a lien
- When
- At any time after the lien is filed
- Served on or filed with
- Filed with the clerk of district court of the county where the lien is filed and served on the lien claimant
- Notarization
- Supporting affidavit required
- The undertaking requires two sureties in at least the amount of the lien. The claimant has seven days after service to object to the sureties.
N.D.C.C. §§ 35-21-01 to 35-21-04
North Dakota Owner Notices and Forms
Owner's Request for Itemized Account
- Who uses it
- Owners and other qualifying interested persons
- When
- Within 15 days after completion of the contract
- Served on or filed with
- The lien claimant
- Notarization
- Not required
N.D.C.C. § 35-27-09
Owner's Demand to Commence Suit
- Who uses it
- Owners or their representatives
- When
- At any time after the lien is recorded
- Served on or filed with
- Delivered to the lienholder and filed with the county recorder
- Notarization
- Not required by the statute; recording requirements apply
- The demand must warn that the lien is forfeited unless suit is commenced and a lis pendens recorded within 30 days after delivery.
N.D.C.C. § 35-27-25
Owner's Notice Objecting to Unauthorized Improvements
- Who uses it
- Owners or interested landholders who did not authorize the work
- When
- Served within five days after learning of the work, or posted conspicuously on the property
- Served on or filed with
- The person making the improvement, or posted at the property
- Notarization
- Not required
N.D.C.C. § 35-27-07
North Dakota Public Works and Payment Bond Claims
Notice of Claim on Public Improvement Bond
- Who uses it
- Claimants with a contract with a subcontractor but no contract with the prime contractor
- When
- Within 90 days after the claimant completes its contribution
- Served on or filed with
- The prime contractor, by registered mail
- Notarization
- Not required
- The notice must state with substantial accuracy the amount claimed and the party for whom the work was done.
N.D.C.C. § 48-01.2-11
Action on Contractor's Bond
- Who uses it
- Unpaid claimants on bonded public improvements
- When
- After 90 days without payment following completion of the claimant's contribution, and within 1 year after completion and acceptance of the project
- Served on or filed with
- Filed in court against the contractor and surety
- Notarization
- Not required
- A claimant may obtain a certified copy of the bond and contract from the governing body by affidavit.
N.D.C.C. §§ 48-01.2-10, 48-01.2-11, 48-01.2-12
Frequently Asked Questions
Is there a statutory mechanics lien form in North Dakota?
No. North Dakota prescribes the content of a construction lien, not a fill-in form. The lien must state the property description, the amount due, the first and last dates of contribution, and the person with whom the claimant contracted (N.D.C.C. § 35-27-13).
Does a North Dakota construction lien have to be notarized?
The lien statute does not require verification, but a lien must be recordable. A privately signed instrument generally needs an acknowledgment or other authorized proof of execution, with exceptions such as an instrument signed by a North Dakota attorney with an identification number (N.D.C.C. §§ 35-27-13, 47-19-03).
Where do I file a mechanics lien in North Dakota?
Record the construction lien with the county recorder of the county where the property lies, within 90 days after your contribution is complete for full priority. Mail the owner a written notice by certified mail at least 10 days before recording (N.D.C.C. §§ 35-27-02, 35-27-13).
What notice do I give before suing on a North Dakota lien?
Give the owner written notice of intent to enforce the lien, by personal service at least 10 days before suit or by registered mail at least 20 days before suit (N.D.C.C. § 35-27-24). This is separate from the notice given before recording.
What form releases a mechanics lien in North Dakota?
A paid lienholder records an acknowledged certificate of discharge within 60 days after satisfaction, or 30 days after the owner's written demand if shorter (N.D.C.C. § 35-01-27). A disputed lien can be released by an application, affidavit, and undertaking with two sureties filed with the clerk of district court (N.D.C.C. § 35-21-02).
Can a North Dakota owner shorten the time to foreclose a lien?
Yes. An owner may deliver a written demand to the lienholder and file it with the county recorder. The lienholder must then commence suit and record a lis pendens within 30 days after delivery, or the lien is forfeited (N.D.C.C. § 35-27-25).
What form do I use for a North Dakota public project bond claim?
A claimant with no contract with the prime contractor sends the prime contractor written notice by registered mail within 90 days after completing its contribution, stating the amount and the party supplied. Suit on the bond is due within 1 year after completion and acceptance of the project (N.D.C.C. §§ 48-01.2-11, 48-01.2-12).
Related North Dakota Resources
North Dakota Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
North Dakota Notice Requirements
Who must give notice, when, and how.
North Dakota Lien Waivers
Statutory forms, waiver types, and enforceability rules.
North Dakota Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about North Dakota law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.