The Statutes Give a Bond Claim, Not a Lien on Public Property
For public work, the Texas statutes do not provide a lien on the public land or building. Texas Government Code Chapter 2253 requires a payment bond for the protection of those who furnish labor and material, and Subchapter J of Property Code Chapter 53 gives a lien on money due the contractor on smaller contracts.
Which remedy applies depends on the size of the prime contract and the type of governmental entity.
When a Payment Bond Is Required
A governmental entity that makes a public work contract with a prime contractor must require a payment bond if the contract is in excess of $25,000. If the governmental entity is a municipality or a joint board created under Subchapter D, Chapter 22, Transportation Code, the threshold is a contract in excess of $50,000. Gov't Code §2253.021(a)(2).
The bond is in the amount of the contract and is solely for the protection and use of payment bond beneficiaries who have a direct contractual relationship with the prime contractor or a subcontractor to supply public work labor or material. §2253.021(c).
The Monthly Bond Claim Notice
To recover on the bond, a beneficiary must mail written notice of the claim to the prime contractor and the surety on or before the 15th day of the 3rd month after each month in which any of the claimed labor was performed or any of the claimed material was delivered. §2253.041(a), (b).
The notice must be accompanied by a sworn statement of account stating in substance that the amount claimed is just and correct and that all just and lawful offsets, payments, and credits known to the affiant have been allowed. §2253.041(c).
A beneficiary that does not have a direct contractual relationship with the prime contractor must also mail the prime contractor written notice of the claim on or before the 15th day of the 2nd month after each month in which the labor was performed or the material was delivered. A copy of the statement sent to the subcontractor is sufficient for this notice. §2253.047(c).
Notices must be sent by certified or registered mail. §2253.048(a).
Retainage on Public Work
A beneficiary whose contract provides for retainage must mail written notice of the retainage claim to the prime contractor and the surety on or before the 90th day after the date of final completion of the public work contract. §2253.046(a). The notice is not required if the amount claimed is part of a prior claim made under the subchapter. §2253.046(c).
Suit on the Bond
A beneficiary may sue the principal or the surety, jointly or severally, if the claim is not paid before the 61st day after the date the notice for the claim is mailed. §2253.073(a). Suit may not be brought after the first anniversary of the date notice for the claim is mailed. §2253.078(b).
If the Governmental Entity Did Not Obtain a Bond
If a governmental entity fails to obtain a payment bond that §2253.021 requires, the entity is subject to the same liability that a surety would have had, and a payment bond beneficiary is entitled to a lien on money due to the prime contractor in the same manner and to the same extent as if the contract were subject to Subchapter J, Chapter 53, Property Code. §2253.027(a). To recover, the beneficiary gives the governmental entity notice in the same manner as it would give notice to a surety under Subchapter C. §2253.027(b). Subsection (c) contains a specific exception to the entity's surety liability that involves a lessee's failure to submit a required notice of commencement. §2253.027(c).
This means a lien on money due the prime contractor can be available when a required bond is missing, even though the contract is larger than the small-contract limits of Subchapter J described below. The lien reaches the money due the prime contractor, not the public real property.
Small Contracts: A Lien on the Money
Where the prime contract does not exceed $25,000, or $50,000 for a municipality or a joint board created under Subchapter D, Chapter 22, Transportation Code, a person who furnishes material or labor to the contractor and gives the required notice has a lien on the money, bonds, or warrants due the contractor for the improvements. Tex. Prop. Code §53.231. Apart from the case described above, where a governmental entity failed to obtain a bond that Chapter 2253 required, this lien is not available merely because a project has no bond. Under §53.231 it applies only to prime contracts within those limits, it depends on the required notice, and it reaches the money, bonds, or warrants due the contractor, not the public real property.
The claimant must send written notice of the claim by certified mail to the officials whose duty it is to pay the contractor and to the contractor. §53.232. The notice must be given not later than the 15th day of the 2nd month following the month in which the labor was performed or the material furnished. §53.234.
Frequently Asked Questions
Can you file a mechanics lien on a public project in Texas?
Not against the public property. The statutory remedies are a claim on the payment bond under Government Code Chapter 2253 and, on small contracts, a lien on money due the contractor under Property Code §53.231.
When is a payment bond required on Texas public work?
When the prime contract is in excess of $25,000, or in excess of $50,000 if the governmental entity is a municipality or a joint board created under Subchapter D, Chapter 22, Transportation Code. Gov't Code §2253.021(a)(2).
What notice is required for a Texas public works bond claim?
Written notice with a sworn statement of account, mailed by certified or registered mail to the prime contractor and the surety by the 15th day of the 3rd month after each month of labor or deliveries. §§2253.041, 2253.048. A claimant with no direct contract with the prime contractor also notifies the prime by the 15th day of the 2nd month. §2253.047(c).
How long do you have to sue on a Texas payment bond?
Suit may be brought if the claim is not paid before the 61st day after the notice is mailed, and may not be brought after the first anniversary of the date the notice is mailed. Gov't Code §§2253.073, 2253.078.
What if the Texas public contract is too small to require a bond?
A person who furnishes material or labor to the contractor has a lien on the money, bonds, or warrants due the contractor if notice is sent by certified mail to the paying officials and the contractor by the 15th day of the 2nd month after the month of the work. Prop. Code §§53.231 to 53.234.
Related Texas Resources
Explore other critical compliance areas for Texas construction mechanic lien law.
Notice Requirements
Notice of Claim for derivative claimants, retainage notice deadlines, homestead contract requirements, and monthly notice obligations
Mechanic Lien Deadlines
Mechanic Lien affidavit filing deadlines for original contractors and derivative claimants on non-residential, residential, and homestead properties
Mechanic Lien Enforcement Deadlines
Suit filing deadlines, public works payment bond claims under Government Code Chapter 2253, and foreclosure requirements
Texas Mechanics Lien Forms
Every notice, lien, release, and bond claim form used in Texas
Texas Lien Waivers
Statutory waiver forms, waiver types, and enforceability rules in Texas
Texas Overview
Return to the main Texas construction mechanic lien law page