Does a General Contractor Need to Send a Preliminary Notice in Texas?

No. The Notice Requirement Applies Only to Claimants Other Than an Original Contractor

No Notice of Claim for an Original Contractor

Texas Property Code §53.056(a) requires the Notice of Claim for Unpaid Labor or Materials from "a claimant other than an original contractor." An original contractor is a person contracting with an owner either directly or through the owner's agent. §53.001(7).

A general contractor that holds its contract with the owner is therefore outside §53.056. It gives no monthly notice and no retainage notice under §53.057, which is also limited to claimants other than an original contractor.

The test is the contract, not the trade or the job title. A specialty contractor or a supplier hired directly by the owner is an original contractor. A company called the general contractor that was in fact hired by a tenant's builder or by another contractor is not.

Homestead Projects Have Contract Requirements Instead

On a homestead, the paperwork that matters for a general contractor is the contract itself. To fix a lien on a homestead, the contractor and the owner must execute a written contract setting forth the terms of the agreement, and it must be executed before the material is furnished or the labor is performed. §53.254(a), (b).

If the owner is married, both spouses must sign. The contract must be filed with the county clerk of the county in which the homestead is located. §53.254(c), (e).

A lien affidavit that relates to a homestead must also carry this notice at the top of the page, in at least 10-point boldface: "NOTICE: THIS IS NOT A LIEN. THIS IS ONLY AN AFFIDAVIT CLAIMING A LIEN." §53.254(f).

A Contractor Hired by a Purported Original Contractor

Section 53.026 addresses the case where the owner and the nominal contractor are effectively the same party. A person who labors or furnishes labor or materials under a direct contract with a purported original contractor is considered to be an original contractor for purposes of perfecting a mechanic's lien.

A purported original contractor is one that can effectively control the owner or is effectively controlled by the owner, through common ownership, interlocking directorships, common management, or otherwise, or one engaged without a good faith intention that it would perform the contract. §53.001(7-a). Whether that definition is met is a question of fact, so a contractor in this position commonly sends the §53.056 notice as well.

What an Original Contractor Should Still Calendar

File the lien affidavit with the county clerk by the 15th day of the 4th month after the month in which the original contractor's work was completed, terminated, or abandoned. On a residential construction project the deadline is the 15th day of the 3rd month. §53.052(a).

Send a copy of the affidavit to the owner or reputed owner at the owner's last known business or residence address by the 5th day after the affidavit is filed. §53.055(a).

Bring suit to foreclose by the first anniversary of the last day the affidavit could have been filed under §53.052. §53.158(a).

Frequently Asked Questions

Does a general contractor need a preliminary notice in Texas?

No. Property Code §53.056(a) requires the Notice of Claim only from a claimant other than an original contractor. A contractor that contracts with the owner directly, or through the owner's agent, is an original contractor under §53.001(7).

What does a Texas general contractor have to do on a homestead?

Sign a written contract with the owner before any labor or material is furnished, have both spouses sign if the owner is married, and file the contract with the county clerk of the county where the homestead is located. §53.254. The lien affidavit must carry the statutory notice in 10-point boldface at the top of the page.

Does a Texas general contractor send anything to the owner after filing?

Yes. A copy of the filed lien affidavit must be sent to the owner or reputed owner by the 5th day after the affidavit is filed with the county clerk. §53.055(a).

Who counts as an original contractor in Texas?

A person contracting with an owner either directly or through the owner's agent. §53.001(7). A person contracting directly with a purported original contractor, as defined in §53.001(7-a), is also treated as an original contractor for purposes of perfecting the lien under §53.026.