Does a Material Supplier Need to Send a Preliminary Notice in Texas?

Yes, Unless the Supplier Contracted Directly With the Owner

Suppliers Follow the Same Rule as Subcontractors

Texas Property Code §53.056 does not separate suppliers from subcontractors. It applies to any claimant other than an original contractor, and the statutory definition of a subcontractor includes a person who has furnished materials to fulfill an obligation to an original contractor or to a subcontractor of any tier. §53.001(13).

A supplier selling to the general contractor, or to a subcontractor, must therefore send the Notice of Claim for Unpaid Labor or Materials to the owner or reputed owner and the original contractor for the lien to be valid. §53.056(a), (a-1).

The one supplier that sends no notice is a supplier that contracts with the owner directly or through the owner's agent. That supplier is an original contractor. §53.001(7).

The Deadline, Month by Month

The notice must be sent not later than the 15th day of the 3rd month after the month during which the materials were provided, or the 15th day of the 2nd month on a residential construction project. §53.056(a-1). Unpaid contractual retainage has its own notice deadline under §53.057.

Suppliers on open accounts should read that rule carefully. The deadline runs separately for each month of deliveries. Materials delivered in March to a commercial project must be noticed by June 15. Materials delivered in April must be noticed by July 15. A supplier that waits until the account is six months past due has already passed the deadline for the earliest months.

Construction equipment rental is treated as material. The definition of material includes rent at a reasonable rate for construction equipment used or reasonably required and delivered for use in the direct performance of the work at the site. §53.001(4)(B).

Specially Fabricated Materials

A person who specially fabricates material has a lien even if the material is not delivered. §53.021(2). Specially fabricated material is material fabricated for use as a component of the construction or repair so as to be reasonably unsuitable for use elsewhere. §53.001(12).

For undelivered specially fabricated materials, the notice deadline runs from the month during which the materials would normally have been delivered. §53.056(a-1).

Form, Delivery, and Homesteads

The notice must be in substantially the form printed in §53.056(a-2) and may include an invoice or billing statement. It is delivered in person, by certified mail, or by another traceable private delivery or mailing service that can confirm proof of receipt. §53.003(b).

On a homestead, the notice to the owner must include or have attached the statement set out in §53.254(g) for the lien to be valid.

Public Projects Are a Different Rule

On a public work covered by a payment bond, the supplier's notice goes to the prime contractor and the surety, not the public owner. It must be mailed on or before the 15th day of the 3rd month after each month in which any of the claimed material was delivered, with a sworn statement of account. Tex. Gov't Code §2253.041.

A supplier that does not have a direct contractual relationship with the prime contractor must also mail the prime contractor written notice of the claim on or before the 15th day of the 2nd month after each month in which the material was delivered. Gov't Code §2253.047(c). These notices must be sent by certified or registered mail. Gov't Code §2253.048(a).

Frequently Asked Questions

Does a material supplier need a preliminary notice in Texas?

Yes, unless the supplier contracted directly with the owner. Property Code §53.056 requires the Notice of Claim for Unpaid Labor or Materials from every claimant other than an original contractor, and it must be sent to the owner or reputed owner and the original contractor.

When is a Texas supplier's notice due?

By the 15th day of the 3rd month after the month in which the materials were provided, or the 15th day of the 2nd month on a residential construction project. §53.056(a-1). Each month of deliveries has its own deadline.

Does a Texas supplier have lien rights for materials that were never delivered?

For specially fabricated material, yes. Section 53.021(2) gives a lien to a person who specially fabricates material even if it is not delivered. The notice deadline is measured from the month the material would normally have been delivered.

What does a Texas supplier send on a public project?

Written notice of the claim with a sworn statement of account, mailed by certified or registered mail to the prime contractor and the surety by the 15th day of the 3rd month after each month of delivery. Gov't Code §§2253.041, 2253.048. A supplier with no direct contract with the prime contractor also notifies the prime by the 15th day of the 2nd month. §2253.047(c).

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.