One Year, Measured From the Filing Deadline
Suit to foreclose a Texas mechanics lien must be brought not later than the first anniversary of the last day a claimant may file the lien affidavit under §53.052. Tex. Prop. Code §53.158(a).
The starting point is the deadline to file, not the date the claimant actually filed. A subcontractor on a commercial project that last furnished labor in January has until May 15 to file its affidavit. Its suit deadline is the first anniversary of May 15, whether the affidavit was filed in February or on the last day.
The same one-year period applies to original contractors and to other claimants, on residential and non-residential projects. Section 53.158 as amended by House Bill 2237 applies to original contracts entered into on or after January 1, 2022. Earlier contracts remain subject to the former law.
Work Out the Filing Deadline First
Because the suit period depends on §53.052, the first step is to identify which filing deadline applied to the claim:
- Original contractor, non-residential: the 15th day of the 4th month after the month the work was completed, terminated, or abandoned
- Original contractor, residential construction project: the 15th day of the 3rd month after that month
- Other claimant, non-residential: the 15th day of the 4th month after the month the claimant last provided labor or materials
- Other claimant, residential construction project: the 15th day of the 3rd month after that month
- Other claimant, retainage: the 15th day of the 3rd month after the month the original contract was completed, terminated, or abandoned
Extension by Recorded Agreement
The period may be extended to not later than the second anniversary of the date the claimant filed the lien affidavit. To do so, the claimant must enter into a written agreement with the then-current record owner of the property before the original period expires. §53.158(a-2).
The agreement must be recorded with the clerk of the same county where the lien was recorded, and it is considered notice of the extension to any subsequent purchaser.
Note that the two measurements differ. The basic period runs from the last day the affidavit could have been filed. The outer limit of an extension runs from the day the affidavit was in fact filed.
An Expired Period Is Not Revived by the Owner's Suit
If suit is pursued solely to discharge a lien because limitations have expired on bringing a foreclosure suit, the lien claimant's right to pursue a suit to foreclose is not revived. §53.158(a-1).
Public Projects Run on a Different Clock
On a bonded public work the claim is against the payment bond. A beneficiary may sue the principal or surety if the claim is not paid before the 61st day after the date the notice for the claim is mailed, and may not bring suit after the first anniversary of the date the notice is mailed. Tex. Gov't Code §§2253.073(a), 2253.078(b).
Frequently Asked Questions
How long do you have to enforce a mechanics lien in Texas?
Suit to foreclose must be brought not later than the first anniversary of the last day the claimant could have filed the lien affidavit under §53.052. Property Code §53.158(a).
Does the Texas one-year period run from the day the lien was filed?
No. It runs from the last day the affidavit could have been filed, which depends on the claimant and the project type under §53.052. Filing the affidavit early does not move the suit deadline.
Can the Texas lien enforcement deadline be extended?
Yes, by written agreement with the then-current record owner, made before the one-year period expires and recorded in the county where the lien was recorded. The extended period cannot run past the second anniversary of the date the affidavit was filed. §53.158(a-2).
What is the deadline to sue on a Texas public works payment bond?
Suit may be brought if the claim is not paid before the 61st day after the claim notice is mailed, and may not be brought after the first anniversary of the date the notice is mailed. Gov't Code §§2253.073, 2253.078.
Related Texas Resources
Explore other critical compliance areas for Texas construction mechanic lien law.
Notice Requirements
Notice of Claim for derivative claimants, retainage notice deadlines, homestead contract requirements, and monthly notice obligations
Mechanic Lien Deadlines
Mechanic Lien affidavit filing deadlines for original contractors and derivative claimants on non-residential, residential, and homestead properties
Mechanic Lien Enforcement Deadlines
Suit filing deadlines, public works payment bond claims under Government Code Chapter 2253, and foreclosure requirements
Texas Mechanics Lien Forms
Every notice, lien, release, and bond claim form used in Texas
Texas Lien Waivers
Statutory waiver forms, waiver types, and enforceability rules in Texas
Texas Overview
Return to the main Texas construction mechanic lien law page