Virginia Lien Waivers

Virginia Lien Waiver Forms and Rules

When Virginia lien waivers are required, which forms apply, and when a waiver takes effect, for contractors, subcontractors, and suppliers.

Virginia has no statutory lien waiver form

Virginia prescribes no statutory lien waiver forms; Va. Code § 43-3(C) voids any contract provision, executed before labor or materials are furnished, that waives or diminishes mechanics lien rights.

Quick Answer

No. Virginia does not require or prescribe a statutory lien waiver form. Conditional, unconditional, progress, and final waivers are contract documents, and Virginia courts enforce them by their terms. Forging or signing a waiver without authority is separately prohibited (Va. Code § 43-13.1).

Advance waivers are void. Under Va. Code § 43-3(C), a contract provision executed before labor or materials are furnished that waives or diminishes the lien rights of a general contractor, subcontractor, lower-tier subcontractor, or supplier is null and void. The rule applies to residential and nonresidential projects.

Once work has been furnished, a waiver is not invalid merely because payment has not arrived. An unconditional waiver cannot be rewritten by an unwritten payment condition (Walker & Laberge Co. v. First National Bank of Boston, 206 Va. 683 (1966)), so sign an unconditional waiver only after funds clear.

Virginia lien waivers are contract documents. The Code prescribes no conditional or unconditional, progress or final forms; the statutory models in §§ 43-5, 43-8, and 43-10 are lien perfection forms, not waivers. Virginia courts enforce waivers according to their exact wording.

The Code does limit when a waiver may be signed. A waiver in a contract signed before work is furnished is void, and a waiver of the right to sue on a public payment bond is void unless signed after the claimant has performed.

Virginia Lien Waiver Types

Conditional Waiver on Progress Payment

When to use it
Exchanged for a progress payment not yet received.
When it takes effect
Takes effect when its written condition, such as receipt of cleared funds, is satisfied. Virginia supplies no condition by statute.

Unconditional Waiver on Progress Payment

When to use it
Signed after a progress payment has been received and cleared.
When it takes effect
Operates on execution and delivery under its terms. A through-date waiver can release all rights through that date, even beyond the amount paid (United Masonry Inc. v. Riggs National Bank, 233 Va. 476 (1987)).

Conditional Waiver on Final Payment

When to use it
Exchanged for the final payment before it is received.
When it takes effect
Takes effect when its stated condition is met. Reservations for retainage and disputed claims must be written in.

Unconditional Waiver on Final Payment

When to use it
Signed after final payment has been received and cleared.
When it takes effect
Operates on execution and delivery. An amount-limited waiver releases only the stated amount (First National Bank of Martinsville v. Roy N. Ford Co., 219 Va. 942 (1979)).

Advance waivers before furnishing are void

A contract provision executed before labor or materials are furnished that waives or diminishes the lien rights of a general contractor, subcontractor, lower-tier subcontractor, or material supplier is null and void (Va. Code § 43-3(C)).

One exception: a general contractor may, by a signed writing before or after furnishing, subordinate its lien rights to a prior or later recorded deed of trust (Va. Code § 43-21). Subordination does not extinguish the lien.

Waivers are enforced by their exact wording

Virginia's Supreme Court has upheld broad through-date partial waivers even where the payment was less than the balance due (United Masonry Inc. v. Riggs National Bank, 233 Va. 476 (1987)) and limited other partial releases to their stated amounts (First National Bank of Martinsville v. Roy N. Ford Co., 219 Va. 942 (1979)).

A waiver must be express or proved by clear and convincing evidence; a payment affidavit is not automatically a lien waiver (McMerit Construction Co. v. Knightsbridge Development Co., 235 Va. 368 (1988)).

Payment bond waivers on public works

A waiver of the right to sue on a Virginia Public Procurement Act payment bond is void unless it is in writing, signed by the claimant, and executed after the claimant has performed the labor or furnished the materials (Va. Code § 2.2-4341(D)).

Va. Code § 11-4.1:1 separately voids pre-furnishing contract provisions waiving a subcontractor's or supplier's payment bond claims or claims for demonstrated additional costs.

No notarization requirement

Neither § 43-3(C) nor § 2.2-4341(D) requires a waiver to be notarized. A recorded certificate of satisfaction is a different instrument with its own affidavit requirement.

Residential projects

Virginia has no separate residential waiver form. The advance-waiver ban applies to residential projects, and residential settlement payment affidavits under §§ 43-13.2 and 43-13.3 do not release any claimant's lien.

Exchange Virginia lien waivers with your customers and subcontractors, tracked against each payment.

Lien Waiver Exchange

Open Questions Under Virginia Law

  • Whether a subcontract requirement to submit progress-payment waivers that release disputed amounts violates Va. Code § 11-4.1:1. A November 2026 unpublished Court of Appeals decision enforced such releases without reaching that question (Kahsai v. FAM Construction, LLC, No. 1710-25-4). This point is not settled under Virginia law. National Lien & Bond confirms it with a local Virginia attorney before relying on it.

Frequently Asked Questions

Does Virginia have a statutory lien waiver form?

No. Virginia does not prescribe conditional, unconditional, progress, or final lien waiver forms. The statutory forms in the Code are for perfecting a lien, not waiving it.

Are advance lien waivers enforceable in Virginia?

No. A contract provision executed before labor or materials are furnished that waives or diminishes lien rights is null and void (Va. Code § 43-3(C)). A general contractor may still subordinate its lien to a deed of trust in a signed writing (Va. Code § 43-21).

Does a Virginia lien waiver need to be notarized?

No. Virginia law imposes no general notarization requirement on a contractual lien waiver or a payment bond waiver.

Can I waive Virginia payment bond rights?

Only after performing. A waiver of the right to sue on a public payment bond is void unless written, signed by the claimant, and executed after the claimant furnished the labor or materials (Va. Code § 2.2-4341(D)).

Is a Virginia unconditional waiver effective before payment clears?

It can be. An unambiguous unconditional waiver cannot be altered by an unwritten condition that payment be made (Walker & Laberge Co. v. First National Bank of Boston, 206 Va. 683 (1966)). Use a conditional waiver until funds clear.

Does a through-date waiver release more than the payment received?

It can. The Supreme Court of Virginia enforced through-date partial waivers covering all work through the stated date, although the payment was less than the balance (United Masonry Inc. v. Riggs National Bank, 233 Va. 476 (1987)).