Quick Answer
A Virginia subcontractor needs three core documents in order: a sworn Memorandum for Mechanic's Lien recorded in the circuit court clerk's office, a written notice to the owner of the amount and character of the claim, and a suit to enforce with a verified itemized account (Va. Code §§ 43-4, 43-7, 43-17, 43-22).
Record the memorandum within 90 days after the last day of the month of last furnishing, and in no event later than 90 days after the structure is completed or work is terminated. The lien may include only work furnished within 150 days before the last furnishing, plus retainage of up to 10% (Va. Code § 43-4).
On one- or two-family residential projects where the building permit names a mechanics' lien agent, notify the agent within 30 days after first furnishing or permit issuance. A late notice preserves the lien only for work furnished on or after its date (Va. Code § 43-4.01).
On public works, a claimant that contracted with a subcontractor gives the prime contractor written notice within 90 days after its last furnishing by registered or certified mail. Every bond suit must be filed within 1 year after the claimant's last furnishing (Va. Code § 2.2-4341).
Virginia mechanics lien law, Va. Code § 43-1 and following, centers on one recorded document: the sworn Memorandum for Mechanic's Lien. The Code supplies substantial-form models for general contractors, subcontractors, and lower-tier claimants, and subcontractors also give the owner a written notice of the amount and character of the claim.
This page describes each Virginia document a claimant, owner, or public works claimant uses, who uses it, when it is due, and where it is recorded or served. One- and two-family residential projects may require notice to a mechanics' lien agent named on the building permit, and public works use the payment bond provisions of the Virginia Public Procurement Act.
Virginia Preliminary Notices
Notice to Mechanics' Lien Agent
- Who uses it
- Lien claimants on one- or two-family residential projects whose building permit designates a mechanics' lien agent
- When
- Within 30 days after first furnishing, or within 30 days after the permit is issued if work began earlier
- Served on or filed with
- The mechanics' lien agent named on the permit, by registered or certified mail or physical delivery
- Notarization
- Not required
- The statute prescribes the contents: claimant contact information, license details if applicable, permit number, property description, and a statement seeking payment.
- A late notice preserves the lien only for work furnished on or after the notice date. If no agent is named, no notice is required.
Va. Code § 43-4.01
Notices to Make Owner or General Contractor Personally Liable
- Who uses it
- Subcontractors, laborers, and suppliers seeking personal liability of the owner or general contractor
- When
- A first notice of the nature of the contract and probable claim; then a second notice with a verified account, after the work and within 30 days after completion or termination of the project
- Served on or filed with
- The owner or its agent and the general contractor, or the general contractor alone
- Notarization
- The second notice's account must be verified by affidavit
- This is a separate remedy from the mechanics lien, capped by the amounts the owner or contractor owes.
Va. Code § 43-11
Virginia Lien Claim and Service
Memorandum for Mechanic's Lien
- Who uses it
- General contractors, subcontractors, and lower-tier subcontractors and suppliers
- When
- Within 90 days after the last day of the month of last furnishing, and no later than 90 days after completion or termination of the work
- Served on or filed with
- Recorded in the circuit court clerk's office of the county or city where the property is located
- Notarization
- Required; verified by oath and affidavit
- Separate statutory models apply to general contractors, subcontractors, and lower-tier claimants. Each includes license information or a certification that no license is required.
- A general contractor must also mail a copy to the owner and file a certification of mailing with the memorandum.
Va. Code §§ 43-4, 43-5, 43-8, 43-10
Notice to Owner of Amount and Character of Claim
- Who uses it
- Subcontractors, and lower-tier subcontractors and suppliers
- When
- No separate statutory deadline, but delay risks the owner paying out the funds the lien can reach
- Served on or filed with
- The owner or its agent; lower-tier claimants also serve the general contractor or its agent
- Notarization
- Not required; signed
- The subcontractor's lien is limited to what the owner owes the general contractor when the notice is given and afterward (Mills v. Moore's Super Stores, 217 Va. 276 (1976)).
Va. Code §§ 43-7, 43-8, 43-9, 43-10
Virginia Enforcing the Lien
Suit to Enforce Mechanic's Lien
- Who uses it
- Lien claimants
- When
- Within the later of 6 months after recording the memorandum or 60 days after completion or termination of the work
- Served on or filed with
- Filed in the circuit court of the county or city where the property is located
- Notarization
- The itemized account filed with the suit must be verified by affidavit
- A memorandum of lis pendens gives record notice to purchasers but is not a condition of timely suit (Va. Code § 8.01-268).
Va. Code §§ 43-17, 43-22
Virginia Releasing or Bonding Off a Lien
Certificate of Satisfaction of Mechanic's Lien
- Who uses it
- A lien creditor that has been paid
- When
- After payment or satisfaction of the lien
- Served on or filed with
- Recorded in the circuit court clerk's office where the memorandum is recorded
- Notarization
- A supporting affidavit is required under the incorporated satisfaction statutes
- A partial release must identify the released property. An owner may also apply to the court for a release order on 20 days' notice if the lien is paid or no timely suit was filed (Va. Code § 43-68).
Va. Code § 43-67; Va. Code § 55.1-339
Application to Release Lien by Bond or Cash Deposit
- Who uses it
- Owners, general contractors, and other interested parties
- When
- Before suit or after suit, on 5 days' notice to the lienor
- Served on or filed with
- Filed with the court having jurisdiction to enforce the lien
- Notarization
- Not separately required
- A bond must be double the lien amount plus costs with an approved surety; a cash deposit must cover the lien and costs.
Va. Code §§ 43-70, 43-71
Virginia Owner Notices and Forms
Petition for Hearing on Validity of Lien
- Who uses it
- Owners and any holder of an interest in the property
- When
- At any time, on good cause and reasonable notice
- Served on or filed with
- Filed in the circuit court where the property is located, with notice to the lienor
- Notarization
- Not required
- If the court finds the lien invalid, it orders the lien released of record.
Va. Code § 43-17.1
Owner's Payment Affidavit or Signed Statement at Settlement
- Who uses it
- Residential owners, developers, and builders selling or refinancing
- When
- At the sale, permanent loan, or refinance settlement
- Served on or filed with
- The purchaser or lender
- Notarization
- Not necessarily; an affidavit or a signed statement attested by a witness
- The statement confirms that direct-contract claimants are paid or lists those unpaid. It does not release any claimant's lien.
Va. Code §§ 43-13.2, 43-13.3
Virginia Public Works and Payment Bond Claims
Written Notice of Claim on Payment Bond
- Who uses it
- Claimants that contracted with a subcontractor rather than the prime contractor on public works
- When
- Within 90 days after the claimant last performed labor or furnished materials
- Served on or filed with
- The prime contractor at its regular business office, by registered or certified mail
- Notarization
- Not required
- The notice must state with substantial accuracy the amount claimed and the party for whom the work was performed. Claimants in direct contract with the prime need no notice.
Va. Code § 2.2-4341(B)
Action on the Payment Bond
- Who uses it
- Unpaid public works claimants
- When
- Direct-contract claimants after 90 days unpaid; all claimants within 1 year after their last labor or materials
- Served on or filed with
- Filed in a court of competent jurisdiction; the public body need not be joined
- Notarization
- Not required
- Payment bonds are required on nontransportation public construction contracts over $500,000 and on qualifying state-funded transportation projects over $350,000.
Va. Code §§ 2.2-4337, 2.2-4341
Frequently Asked Questions
Is there a statutory mechanics lien form in Virginia?
Yes. The Code supplies substantial-form models for the Memorandum for Mechanic's Lien and the accompanying affidavit for general contractors, subcontractors, and lower-tier claimants, and for the subcontractor's notice to the owner (Va. Code §§ 43-5, 43-8, 43-10).
Does a Virginia mechanics lien have to be notarized?
Yes. The memorandum must be verified by the oath and affidavit of the claimant or its agent, ordinarily before a notary (Va. Code § 43-4). The itemized account filed with the enforcement suit must also be verified (Va. Code § 43-22).
Where do I file a mechanics lien in Virginia?
Record the memorandum in the circuit court clerk's office of the county or city where the property is located, within 90 days after the last day of the month of last furnishing and no later than 90 days after completion or termination (Va. Code § 43-4).
When must I notify a mechanics' lien agent in Virginia?
On one- or two-family residential projects whose building permit names an agent, within 30 days after first furnishing or permit issuance. A late notice protects only work furnished afterward (Va. Code § 43-4.01).
What form releases a mechanics lien in Virginia?
A certificate of satisfaction recorded in the circuit court clerk's office after payment (Va. Code § 43-67). An owner can also bond off the lien by court order (Va. Code §§ 43-70, 43-71) or seek a court release if no timely suit was filed (Va. Code § 43-68).
Does Virginia have a notice of completion?
No. Virginia has no owner-recorded notice of completion that shortens lien deadlines. Actual completion or termination of the work controls (Va. Code §§ 43-4, 43-17).
What form do I use for a Virginia public project bond claim?
A claimant that contracted with a subcontractor sends the prime a written notice by registered or certified mail within 90 days after last furnishing, then sues within 1 year after last furnishing (Va. Code § 2.2-4341).
Related Virginia Resources
Virginia Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Virginia Notice Requirements
Who must give notice, when, and how.
Virginia Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Virginia Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Virginia law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.