Washington Lien Waivers

Washington Lien Waiver Forms and Rules

When Washington lien waivers are required, which forms apply, and when a waiver takes effect, for contractors, subcontractors, and suppliers.

Washington has no statutory lien waiver form

Washington prescribes no statutory lien waiver forms; RCW 60.04.071 requires only that a paid claimant release the paid lien rights on demand.

Quick Answer

No. Washington does not require or prescribe a statutory lien waiver form. The statute requires only that a claimant release lien rights for which payment has been made and accepted, once a release is demanded (RCW 60.04.071). All other waivers are contract documents enforced by their terms.

Advance waivers of private lien rights are not void in Washington. A lien waiver in a purchase order was enforced in Reid Sand & Gravel, Inc. v. Bellevue Properties, 7 Wn. App. 701 (1972). Waiver is not presumed, however, and must be clear, certain, and unequivocal (Boise Cascade Corp. v. Distinctive Homes, Inc., 67 Wn.2d 289 (1965)).

No statute makes a Washington waiver conditional on a check clearing. A broad unconditional through-date waiver can release rights even with a balance unpaid, so sign only a conditional waiver that expressly requires receipt of cleared funds until the payment has actually cleared.

Washington lien waivers are contract documents. The statute prescribes no conditional or unconditional, progress or final forms. What a waiver releases depends on its own words, and Washington courts distinguish releasing a recorded lien from surrendering the underlying right to lien unpaid work.

Washington also does not void advance lien waivers on private projects. A clear contractual waiver can be enforced, so the wording of every waiver, purchase order, and subcontract matters.

Washington Lien Waiver Types

Conditional Waiver on Progress Payment

When to use it
Exchanged for a progress payment not yet received.
When it takes effect
Takes effect when its written condition, such as receipt of the identified payment in cleared funds, is satisfied. Washington supplies no statutory condition.

Unconditional Waiver on Progress Payment

When to use it
Signed after a progress payment has been received and cleared.
When it takes effect
Operates according to its language when signed and delivered. A through-date waiver can release all rights through that date, not just the amount paid.

Conditional Waiver on Final Payment

When to use it
Exchanged for the final payment before it is received.
When it takes effect
Takes effect when its stated conditions occur. Check its reservations for retainage, disputed changes, and interest.

Unconditional Waiver on Final Payment

When to use it
Signed after final payment has been received and cleared.
When it takes effect
Operates according to its words. Distinguish an all-rights waiver from a release of one recorded lien.

Releasing a recorded lien is not necessarily waiving the right to lien

In Shelcon Construction Group, LLC v. Haymond, 187 Wn. App. 878 (2015), a claimant released its recorded lien to facilitate financing without being paid in full. Because the release did not state that payment was made or surrender future lien rights, the claimant could record a second timely lien that included the unpaid work.

Broad unconditional waivers can release unpaid amounts

In Exterra, LLC v. Cle Elum Gateway Property, LLC, No. 31751-0-III (Wash. Ct. App. Nov. 20, 2014) (unpublished), the court enforced broad through-date waivers that were not conditioned on payment of every amount owed. The signer's belief that it waived only paid amounts did not overcome the language.

Advance waivers and coercion

Private advance lien waivers can be enforced if they are clear and unequivocal (Reid Sand & Gravel, Inc. v. Bellevue Properties, 7 Wn. App. 701 (1972)).

Coercing a claimant, or attempting to, in order to discourage a Notice to Owner or a lien filing, including by threatening to withhold future contracts, is an unfair or deceptive practice under the Consumer Protection Act (RCW 60.04.035).

Public works bond and retainage rights

RCW 39.04.900 voids contractual waivers of the public works rights created by chapter 223, Laws of 1992, which include retainage protections. It is not a blanket prohibition on every waiver of public bond rights.

Courts enforce express procedural waivers: PowerCom, Inc. v. Valley Electric Co. of Mt. Vernon, Inc., 29 Wn. App. 2d 506 (2024), enforced subcontract language postponing a bond suit until the prime's dispute with the owner was resolved.

No notarization requirement

RCW 60.04.071 does not require a waiver or release to be notarized. A release recorded to clear a recorded lien must satisfy recording requirements.

Exchange Washington lien waivers with your customers and subcontractors, tracked against each payment.

Lien Waiver Exchange

Open Questions Under Washington Law

  • Whether a permanent waiver of all public works payment bond rights under RCW 39.08, signed before performance, is enforceable. No controlling published Washington decision resolves it. This point is not settled under Washington law. National Lien & Bond confirms it with a local Washington attorney before relying on it.

Frequently Asked Questions

Does Washington have a statutory lien waiver form?

No. Washington prescribes no conditional, unconditional, progress, or final waiver forms. RCW 60.04.071 requires only that a paid claimant release the paid lien rights when payment is made, accepted, and a release is demanded.

Are advance lien waivers enforceable in Washington?

On private projects, a clear and unequivocal contractual waiver can be enforced (Reid Sand & Gravel, Inc. v. Bellevue Properties, 7 Wn. App. 701 (1972)). Coercing a claimant not to file a lien or notice is an unfair practice (RCW 60.04.035).

Does a Washington lien waiver need to be notarized?

No statute requires notarization of a lien waiver. A release recorded against title must meet recording requirements.

Is a Washington unconditional waiver effective if I have not been paid?

It can be. Washington courts enforce waivers by their language, and a broad unconditional through-date waiver can release unpaid amounts. A simple release of a recorded lien, without words surrendering future rights, may not bar a new timely lien (Shelcon Construction Group, LLC v. Haymond, 187 Wn. App. 878 (2015)).

Can I waive public works bond or retainage rights in Washington?

Rights created by the 1992 public works act, including retainage protections, cannot be waived by contract (RCW 39.04.900). Other bond-related terms, such as a clause postponing suit, can be enforced if explicit (PowerCom, Inc. v. Valley Electric Co., 29 Wn. App. 2d 506 (2024)).

Must a Washington claimant release its lien after payment?

Yes. Once payment is made and accepted and a release is demanded, the claimant must immediately release the paid rights or face liability for damages and attorney fees (RCW 60.04.071).