Washington Mechanics Lien Forms
Every notice, lien, enforcement, release, and bond claim document used on Washington construction projects, with who uses it, when it is due, and where it goes.
Quick Answer
A Washington subcontractor or supplier needs three core documents in order: a Notice to Owner, a Claim of Lien recorded with the county within 90 days after last furnishing, and a foreclosure suit filed within 8 calendar months after recording (RCW 60.04.031, 60.04.091, 60.04.141).
The Notice to Owner has no deadline, but it reaches back only 60 days before it is mailed or served on most projects, and only 10 days on new single-family construction. Claimants who contract with the owner or the prime contractor are generally exempt, except on repair or remodel of an existing owner-occupied home (RCW 60.04.031).
The Claim of Lien must be signed and verified under penalty of perjury. Give the owner a copy within 14 days after recording; missing that step forfeits attorney fees and costs against the owner, not the lien. Serve the owner with the foreclosure summons and complaint within 90 days after filing (RCW 60.04.091, 60.04.141).
On public works, file a notice of claim against the payment bond with the public body within 30 days after completion and acceptance, and a separate claim against retainage within 45 days after completion. Suppliers to subcontractors must also notify the prime contractor within 10 days after first delivery (RCW 39.08.030, 39.08.065, 60.28.011).
Washington's construction lien statute, RCW 60.04, prescribes the wording of its key documents. The Notice to Owner, the Claim of Lien, the Notice to Real Property Lender, and the contractor's Notice to Customer disclosure statement each follow a statutory form that must be substantially followed.
This page describes each Washington document a claimant, owner, or public works claimant uses, who uses it, when it is due, and where it goes. Public works use two separate remedies, a claim against the contractor's payment bond and a lien on the retained percentage, each with its own notices and deadlines.
Washington Preliminary Notices
Notice to Owner (Notice of Right to Claim a Lien)
- Who uses it
- Subcontractors, suppliers, and professionals without a direct contract with the owner
- When
- At any time, but it protects only furnishing within 60 days before it is given (10 days on new single-family construction) and afterward
- Served on or filed with
- The owner or reputed owner by certified or registered mail or personal service; also the prime contractor when the statute requires
- Notarization
- Not required
- Subcontractors in direct contract with the prime, laborers, and direct owner contractors are generally exempt. On repair or remodel of an existing owner-occupied single-family home, even first-tier subcontractors must give it, and the lien is limited to what the owner had not yet paid the prime when the notice arrived.
- Where a required notice was never given, the lien cannot be enforced.
RCW 60.04.031
Notice to Customer (Contractor Disclosure Statement)
- Who uses it
- Contractors in direct contract with the customer on covered residential and small commercial work
- When
- Before beginning work
- Served on or filed with
- The customer, who signs an acknowledgment the contractor keeps for 3 years
- Notarization
- Not required
- Covers residential work on four or fewer units of $1,000 or more and commercial building work of $1,000 or more but less than $60,000.
- Failure to give it bars the contractor's lien.
RCW 18.27.114
Notice to Real Property Lender
- Who uses it
- Unpaid potential lien claimants on projects with construction financing and no qualifying payment bond
- When
- After payment has been unpaid 5 days past its due date, and within 35 days after the due date
- Served on or filed with
- The lender's administering office, with copies to the owner and the prime contractor, by certified or registered mail or personal service
- Notarization
- Not required
- The lender must then withhold undisbursed construction funds or obtain a payment bond covering the noticed amount.
RCW 60.04.221
Washington Lien Claim and Service
Claim of Lien
- Who uses it
- Contractors, subcontractors, suppliers, and professionals
- When
- Within 90 days after the claimant last furnished labor, professional services, materials, or equipment
- Served on or filed with
- Recorded with the county auditor or recording office where the property is located; copy to the owner within 14 days
- Notarization
- Required; signed and verified under penalty of perjury
- A claim substantially following the statutory sworn form is valid without a separate formal acknowledgment (Williams v. Athletic Field, Inc., 172 Wn.2d 683 (2011)).
- Missing the 14-day owner copy forfeits attorney fees and costs against the owner but does not invalidate the lien.
RCW 60.04.091
Washington Enforcing the Lien
Complaint to Foreclose Lien
- Who uses it
- Lien claimants
- When
- File within 8 calendar months after recording the Claim of Lien, and serve the owner within 90 days after filing
- Served on or filed with
- Filed in superior court in the county where the property is located; the owner must be joined
- Notarization
- Not required
- If the claim states credit terms, the 8 months runs from the end of the credit period. The owner's bankruptcy tolls the period.
- A lis pendens is ineffective unless a defendant is served or summons publication begins within 60 days after it is recorded (RCW 4.28.320).
RCW 60.04.141
Washington Releasing or Bonding Off a Lien
Release of Lien Rights
- Who uses it
- A claimant that has been paid
- When
- Immediately after payment is made and accepted and a release is demanded
- Served on or filed with
- Delivered to the person making payment; a release of a recorded lien is recorded to clear title
- Notarization
- Not required by the statute; a recorded release must meet recording requirements
- A claimant that unjustifiably delays a release is liable for damages and attorney fees.
RCW 60.04.071
Bond in Lieu of Claim
- Who uses it
- Owners and other interested parties disputing a lien
- When
- Before or after foreclosure begins
- Served on or filed with
- Recorded where the Claim of Lien was recorded
- Notarization
- Not separately required
- For liens of $10,000 or less, the bond is the greater of $5,000 or twice the lien; above $10,000, at least 1.5 times the lien. Recording releases the property, but the claimant must still timely enforce against the bond.
RCW 60.04.161
Washington Owner Notices and Forms
Motion and Order to Show Cause on Frivolous or Clearly Excessive Lien
- Who uses it
- Owners, contractors, subcontractors, lenders, and lien claimants
- When
- At any time; the hearing is held 6 to 15 days after service
- Served on or filed with
- Filed in superior court where the property is located and served on the claimant
- Notarization
- Required; supported by affidavit
- Attorney fees run both ways: to the owner if the lien is frivolous, and to the claimant if it is not.
RCW 60.04.081
Jobsite Project Notice
- Who uses it
- Prime contractors on projects costing more than $5,000
- When
- Posted in plain view throughout construction
- Served on or filed with
- The jobsite; a qualifying posted permit or inspection card may satisfy it
- Notarization
- Not required
- The notice identifies the property, owner, prime contractor, and construction lender or payment bond.
RCW 60.04.230
Washington Public Works and Payment Bond Claims
Notice to Contractor of Supplies Furnished to a Subcontractor
- Who uses it
- Suppliers furnishing materials, supplies, or provisions to a subcontractor on public works
- When
- No later than 10 days after first delivery to the subcontractor
- Served on or filed with
- Delivered or mailed to the prime contractor
- Notarization
- Not required
- Missing it bars a bond action for those items. Labor claims and suppliers selling directly to the prime need no such notice.
RCW 39.08.065
Supplier Notice of Right to Claim Against Retained Percentage
- Who uses it
- Suppliers of materials, supplies, or equipment not in direct contract with the prime contractor
- When
- At any time; it covers furnishing during the 60 days before it is given and afterward
- Served on or filed with
- The prime contractor, by registered or certified mail or personal service with a signed receipt
- Notarization
- Not required
RCW 60.28.015
Notice of Claim Against Payment Bond
- Who uses it
- Laborers, subcontractors, and suppliers on public works
- When
- Within 30 days after completion of the contract and acceptance of the work by affirmative action of the public body
- Served on or filed with
- Presented to and filed with the contracting public body
- Notarization
- Not required
- Suit on the bond is governed by the 6-year period for actions on a written contract. Waiting 30 days after filing the claim before suing preserves the statutory attorney fee award.
RCW 39.08.030; RCW 4.16.040
Notice of Claim Against Retained Percentage
- Who uses it
- Laborers, subcontractors, and suppliers on public works
- When
- Within 45 days after completion of the contract work
- Served on or filed with
- Filed with the contracting public body
- Notarization
- Not required
- The retainage claim runs from completion, not acceptance. Calendar it separately from the bond claim.
RCW 60.28.011(2)
Suit to Foreclose Lien on Retained Percentage
- Who uses it
- Claimants that filed a timely retainage claim
- When
- Within 4 months after filing the claim against the retained percentage
- Served on or filed with
- Filed in superior court in the county where the claim was filed
- Notarization
- Not required
- Missing this deadline releases the fund to the contractor but does not affect the claim against the contractor or surety.
RCW 60.28.030
Frequently Asked Questions
Is there a statutory mechanics lien form in Washington?
Yes. RCW 60.04.091 sets out the Claim of Lien form, and RCW 60.04.031 sets out the Notice to Owner form, each to be substantially followed. The Notice to Customer and the Notice to Real Property Lender also follow statutory forms (RCW 18.27.114, 60.04.221).
Does a Washington lien have to be notarized?
The Claim of Lien must be signed and verified under penalty of perjury. A claim substantially following the statutory sworn form is valid without a separate notarial acknowledgment (RCW 60.04.091; Williams v. Athletic Field, Inc., 172 Wn.2d 683 (2011)).
Who must send a Notice to Owner in Washington?
Subcontractors, suppliers, and professionals who do not contract with the owner, unless exempt. Subcontractors in direct contract with the prime are exempt except on repair or remodel of an existing owner-occupied single-family home (RCW 60.04.031).
Where do I file a mechanics lien in Washington?
Record the Claim of Lien with the county auditor or recording office of the county where the property is located within 90 days after last furnishing, and give the owner a copy within 14 days (RCW 60.04.091).
How does a contractor's Notice to Customer affect its lien?
On covered contracts, a contractor that fails to give the Notice to Customer disclosure statement before starting work cannot claim a lien. The contractor must also be registered (RCW 18.27.114).
What form releases a mechanics lien in Washington?
Washington has no statutory release form. After payment and a demand, the claimant must immediately release the paid lien rights (RCW 60.04.071). An owner may also record a Bond in Lieu of Claim to release the property (RCW 60.04.161).
What form do I use for a Washington public works bond claim?
File the statutory notice of claim with the contracting public body within 30 days after completion and acceptance (RCW 39.08.030), and a separate retainage claim within 45 days after completion (RCW 60.28.011). Suppliers to subcontractors also notify the prime within 10 days after first delivery (RCW 39.08.065).
Related Washington Resources
Washington Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Washington Notice Requirements
Who must give notice, when, and how.
Washington Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Washington Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Washington law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.