Can You File a Mechanics Lien on a Public Project in Illinois?

Not on the Property. Illinois Gives a Lien on the Contract Funds and a Claim on the Payment Bond

The Lien Is on the Money, Not the Land

Section 23 of the Mechanics Lien Act does not give a lien on a public body's land or buildings. It gives any person who furnishes labor, services, material, fixtures, apparatus or machinery, or forms or form work to a contractor having a contract for public improvement a lien on the money, bonds, or warrants due or to become due to that contractor under the contract. 770 ILCS 60/23(b), (c).

Subsection (b) covers counties, townships, school districts, cities, municipalities, municipal corporations, and other units of local government. Subsection (c) covers contracts with the State. For this section, contractor includes any subcontractor. 770 ILCS 60/23(a).

The Public Construction Bond Act provides a second remedy, a right to sue on the contractor's bond, and states that it is in addition to and independent of any other rights and remedies. 30 ILCS 550/2. The two remedies have different notices and different deadlines.

Lien on Public Funds: The Notice

There is no lien unless the claimant gives written notice before payment or delivery of the funds is made to the contractor. On local projects the notice goes to the clerk or secretary of the public body. On State projects it goes to the Director or other official whose duty it is to let the contract. A copy must be furnished at once to the contractor. 770 ILCS 60/23(b)(1), (c)(1).

The notice of the claim for lien must contain a sworn statement identifying the claimant's contract, describing the work done by the claimant, and stating the total amount due and unpaid as of the date of the notice.

It may be sent by registered or certified mail, return receipt requested, with delivery limited to addressee only, or delivered. It is effective when received or refused. The lien attaches only to the portion of the money, bonds, or warrants against which no voucher has been issued and delivered to the contractor.

The statute sets no fixed number of days for this notice, but it must precede payment, and the contractor can force the issue. On written demand of the contractor, served by certified mail, return receipt requested, with a copy filed with the public official, a claimant who has not yet given notice must do so within 30 days or the lien is forfeited. 770 ILCS 60/23(b)(2), (c)(2).

Lien on Public Funds: The 90-Day Suit

Within 90 days after serving the notice, the claimant must commence proceedings by complaint for an accounting. The parties defendant are the contractor having the contract with the public body and the contractor to whom the labor or material was furnished. Within 10 days after filing, the claimant must deliver a copy of the complaint to the clerk or secretary, or on a State contract to the Director. 770 ILCS 60/23(b)(4), (c)(4).

Failure to commence the proceeding within 90 days terminates the lien, and no later notice of lien may be given for the same claim. A later notice may still be given for amounts that become due after the earlier notice. 770 ILCS 60/23(b)(5), (c)(5).

On State contracts paid from money appropriated by the General Assembly, the suit must be commenced and a copy of the complaint delivered to the Director not less than 15 days before the date the appropriation will lapse. 770 ILCS 60/23(c)(4).

Payment Bond: 180 Days, 10 Days, One Year

Until January 1, 2029, the State and its political subdivisions must require a bond on contracts for public work costing over $150,000. The Department of Transportation and the Illinois State Toll Highway Authority must require one only if the contract will cost more than $500,000, and a local governmental unit may require a bond on smaller contracts by ordinance or resolution. Other statutory exceptions and authorized substitutes for a bond also apply. 30 ILCS 550/1.

A person who furnished material, apparatus, fixtures, or machinery, or performed labor, for the contractor has no right of action on the bond unless it files a verified notice of the claim within 180 days after the date of its last item of work or the furnishing of its last item of materials. On State contracts the notice is filed with the officer, board, bureau, or department awarding the contract. On contracts with a political subdivision it is filed with the Clerk or Secretary. A copy must go to the contractor within 10 days of the filing. 30 ILCS 550/2.

The notice may be filed by personal service or by United States Mail, postage prepaid, certified or restricted delivery, return receipt requested, limited to addressee only. It is deemed filed on the date of personal service or the date of mailing.

No action on the bond may be brought later than one year after the date the claimant furnished its last item of work, materials, apparatus, fixtures, or machinery. The action is brought in the circuit court in the judicial circuit in which the contract is to be performed. 30 ILCS 550/2.

The Deadlines Side by Side

The two remedies do not share a clock, so each belongs on the calendar:

  • Lien on public funds, notice: before the funds are paid to the contractor, or within 30 days after a contractor's written demand
  • Lien on public funds, suit: complaint for an accounting within 90 days after serving the notice, with a copy delivered to the public official within 10 days after filing, and on State appropriations both steps at least 15 days before the appropriation lapses
  • Payment bond, notice: verified notice filed within 180 days after the claimant's last item of work or materials, with a copy to the contractor within 10 days of filing
  • Payment bond, suit: no later than one year after the claimant's last item of work or materials

Frequently Asked Questions

Can you file a mechanics lien on a public project in Illinois?

Not against the property. Section 23 of the Mechanics Lien Act gives a lien on the money, bonds, or warrants due or to become due to the contractor under the public contract. 770 ILCS 60/23. The Public Construction Bond Act separately gives a right to sue on the contractor's bond. 30 ILCS 550/2.

Is there a deadline to serve an Illinois lien on public funds?

Section 23 sets no fixed number of days, but the notice must be given before payment is made to the contractor, and the lien attaches only to funds against which no voucher has been issued and delivered. If the contractor serves a written demand, the claimant must give notice within 30 days or the lien is forfeited.

How long do you have to sue on an Illinois lien on public funds?

90 days after serving the notice of lien. The claimant commences a complaint for an accounting and delivers a copy to the public official within 10 days after filing. Missing the 90 days terminates the lien for that claim. On State work paid from a legislative appropriation, the suit must be commenced and the complaint delivered at least 15 days before the appropriation lapses. 770 ILCS 60/23.

What is the Illinois public payment bond claim deadline?

A verified notice of claim must be filed within 180 days after the claimant's last item of work or materials, with a copy furnished to the contractor within 10 days of filing. No action may be brought later than one year after the claimant's last item of work or materials. 30 ILCS 550/2.

Which Illinois public projects require a payment bond?

Until January 1, 2029, contracts for public work costing over $150,000, and Department of Transportation and Illinois State Toll Highway Authority contracts costing more than $500,000. Local governmental units may require a bond on smaller contracts. On and after January 1, 2029, the general threshold is public work costing over $50,000, subject to statutory exceptions and permitted substitutes, and the higher Department of Transportation and Toll Highway Authority threshold expires. 30 ILCS 550/1.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.