Who Must Give It
The 60-day notice applies to each subcontractor who has furnished, or is furnishing, labor, services, material, fixtures, apparatus or machinery, or forms or form work for an existing owner-occupied single-family residence. The subcontractor gives it in order to preserve its lien. 770 ILCS 60/21(c).
Subcontractor has its statutory meaning here, which includes a person who furnishes material for the contractor. 770 ILCS 60/21(a). Section 21(c) itself refers to the subcontractor or material supplier.
A contractor in direct contract with the owner does not give this notice. Its residential obligations are the boldface notice before the first payment under 770 ILCS 60/5(b)(i) and the written notice within 10 days after recording a lien under 770 ILCS 60/7(d).
When, to Whom, and How
The subcontractor must notify the occupant within 60 days from its first furnishing. This is the reverse of the Section 24 notice, which is measured from completion.
The notice is given to the occupant either personally or by certified mail, return receipt requested, addressed to the occupant or the occupant's agent at the residence. Notice by certified mail is considered served at the time of its mailing. 770 ILCS 60/21(c).
These are the only two methods Section 21(c) lists. The tracked delivery company option that Section 24(a) allows for the 90-day notice does not appear in Section 21(c).
What the Notice Must Say
Section 21(c) prescribes the contents. The notice must also carry the statutory warning headed "NOTICE TO OWNER", in at least 10 point bold face type. The warning tells the owner that the subcontractor has performed work for or delivered material to the owner's home improvement contractor, that this entitles the subcontractor to file a lien against the residence if it is not paid, and that the owner is urged to request a lien waiver from the contractor when paying. Copy the warning from the current text of 770 ILCS 60/21(c) and do not paraphrase it. The notice must contain:
- The name and address of the subcontractor or material supplier
- The date the subcontractor or material supplier started to work or to deliver materials
- The type of work done and to be done, or the type of labor, services, materials, fixtures, apparatus or machinery, or forms or form work delivered and to be delivered
- The name of the contractor requesting the work
- The statutory warning to the owner
If the 60 Days Have Passed
A late notice still has value. Any notice given after 60 days preserves the subcontractor's lien, but only to the extent that the owner has not been prejudiced by payments made prior to receipt of the notice. 770 ILCS 60/21(c).
The measure is receipt. Each payment the owner makes before the late notice is received can reduce what the lien reaches, so a subcontractor that has missed the 60 days should give the notice at once.
The 90-Day Notice Still Applies
Section 21(c) and Section 24 are separate requirements with different recipients, contents, and clocks. The 60-day notice goes to the occupant and describes the work. The Section 24 notice states the claim and the amount due or to become due, goes to the owner of record and any known lender, and is due within 90 days after completion. 770 ILCS 60/24(a). A notice that satisfies only Section 21(c) does not automatically satisfy Section 24, and the reverse is also true. The statutes do not require two separate documents, but a combined notice must independently meet the content, timing, recipient, and service requirements of both sections. Section 24 also excuses a separate notice when its sworn statement exception applies.
Frequently Asked Questions
Who must send the Illinois 60-day notice?
Each subcontractor, including a material supplier, who has furnished or is furnishing labor, services, or material for an existing owner-occupied single-family residence. 770 ILCS 60/21(c). A contractor in direct contract with the owner does not give this notice.
When is the Illinois 60-day notice due?
Within 60 days from the subcontractor's first furnishing of labor, services, or material. Notice by certified mail, return receipt requested, is considered served at the time of mailing. 770 ILCS 60/21(c).
What if the Illinois 60-day notice is late?
A notice given after 60 days still preserves the lien, but only to the extent the owner has not been prejudiced by payments made before receiving the notice. 770 ILCS 60/21(c).
Does the 60-day notice replace the 90-day Section 24 notice?
No. Section 21(c) and Section 24 are distinct requirements, and a notice that satisfies only one does not automatically satisfy the other. Two separate documents are not required, but a combined notice must independently meet the content, timing, recipient, and service requirements of both sections. Section 24 excuses a separate notice when its sworn statement exception applies. 770 ILCS 60/21(c), 60/24(a).
Related Illinois Resources
Explore other critical compliance areas for Illinois construction mechanic lien law.
Notice Requirements
Statutory notice obligations for subcontractors, suppliers, residential projects, and public works bond claims
Mechanic Lien Deadlines
Mechanic Lien recording timelines, strict compliance pitfalls, verified claim requirements, and private vs. public mechanic lien rules
Mechanic Lien Enforcement Deadlines
Foreclosure litigation, Section 34 demand, public fund mechanic liens, payment bond claims, and enforcement timelines
Illinois Mechanics Lien Forms
Every notice, lien, release, and bond claim form used in Illinois
Illinois Lien Waivers
Statutory waiver forms, waiver types, and enforceability rules in Illinois
Illinois Overview
Return to the main Illinois construction mechanic lien law page