IL Lien Enforcement Deadline

How Long Do You Have to Enforce a Mechanics Lien in Illinois?

Two Years After Completion, Unless a Section 34 Demand Cuts It to 30 Days

Two Years, Measured From Completion

A suit to enforce the lien must be commenced, or a counterclaim filed, within two years after the completion of the contract, or completion of the extra or additional work, or furnishing of extra or additional material under it. 770 ILCS 60/9. Completion means the end of the claimant's lienable contract work or deliveries, including qualifying extra or additional work or materials, and not simply the latest site visit; warranty service, maintenance, correction of an already completed job, or trivial work done to revive a deadline ordinarily does not restart the period.

The period is measured from completion, not from the date the claim for lien was recorded. Recording late in the 4-month window does not move the two-year date.

The suit is brought in the circuit court in the county where the improvement is located. A lien claimant who was not made a party to another claimant's suit may petition to intervene and enforce its lien by counterclaim. 770 ILCS 60/9.

A Section 34 Demand Shortens the Period to 30 Days

The two years can be cut short by a written demand. The demand may come from the owner, a lienor, a county recorder acting under Section 3-5010.8 of the Counties Code, or any person interested in the real estate, or their agent or attorney. Once it is served on the lien claimant, suit must be commenced, or an answer filed in a pending suit, within 30 days, or the lien is forfeited. 770 ILCS 60/34(a).

The demand may be served by registered or certified mail, return receipt requested, or by personal service. It must contain, in at least 10 point bold face type, the statutory warning that failure to respond within 30 days after receipt shall result in forfeiture of the lien. 770 ILCS 60/34(b).

Subsection (a) counts the 30 days from service of the demand, and the required warning speaks of 30 days after receipt. The trigger is effective service of the demand on the claimant, its agent, or its attorney, not mailing alone. A claimant should count from the earliest effective service on or receipt by any of those recipients, not from its own later personal receipt or from a later duplicate of the demand.

Subcontractors and Suppliers

A subcontractor enforces its lien within the same limits as to time provided for the contractor in Section 7 and Sections 9 to 20. 770 ILCS 60/28. The two-year period and the Section 34 demand both apply.

The right to file a complaint arises when the money due is not paid within 10 days after the Section 24 notice is served. All suits by subcontractors must be brought against the contractor and the owner jointly, and the owner is liable for no more than the subcontractor's pro rata share of the funds due to the contractor. 770 ILCS 60/28.

The 4-Month Rule Reaches Suits Too

Section 7(a) gives a claimant two ways to preserve the lien against other creditors, incumbrancers, and purchasers: record a claim for lien within 4 months after completion, or bring an action to enforce the lien within that same 4 months. A suit filed inside 4 months does the work of a recorded claim. As against those third parties, a suit filed later depends on a claim having been recorded within the 4 months. As against the original owner, recording is not a prerequisite to a timely suit under Section 9.

Public Projects Run on Different Clocks

None of these periods applies to a lien on public funds or a payment bond claim. A lien on public funds must be enforced by a complaint for an accounting within 90 days after serving the notice of lien. On State work paid from a legislative appropriation, the suit must be commenced and the complaint delivered at least 15 days before the appropriation lapses. 770 ILCS 60/23. An action on a public payment bond may not be brought later than one year after the claimant furnished its last item of work or materials. 30 ILCS 550/2.

Frequently Asked Questions

How long do you have to enforce a mechanics lien in Illinois?

Suit must be commenced, or a counterclaim filed, within two years after completion of the contract, or completion of extra or additional work, or furnishing of extra or additional material. 770 ILCS 60/9.

Does the Illinois two-year period run from the recording date?

No. Section 9 measures it from completion of the contract or of extra or additional work, not from the date the claim for lien was recorded.

What is a Section 34 demand in Illinois?

A written demand, served on the lien claimant by the owner, a lienor, a county recorder under Section 3-5010.8 of the Counties Code, or any person interested in the real estate, requiring suit to be commenced or an answer filed in a pending suit. If the claimant does not act within 30 days, the lien is forfeited. 770 ILCS 60/34.

How is a Section 34 demand served?

By registered or certified mail, return receipt requested, or by personal service. It must include the statutory forfeiture warning in at least 10 point bold face type. 770 ILCS 60/34.

Who must be named when an Illinois subcontractor sues to enforce a lien?

Section 28 requires all suits and actions by subcontractors to be against both the contractor and the owner jointly, and no judgment is rendered until both are before the court by process or publication. 770 ILCS 60/28.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.