4 Months to Protect the Lien Against Third Parties, 2 Years as to the Owner

Two Deadlines in One Section

Section 7 sets two periods, and which one matters depends on who the lien must be enforced against.

Against third parties: a contractor may not enforce its lien against or to the prejudice of any other creditor, incumbrancer, or purchaser unless, within 4 months after completion, it either brings an action to enforce the lien or files a verified claim for lien with the recorder of the county where the improvement is located. 770 ILCS 60/7(a).

Against the owner: the claim for lien may be filed at any time after the contract is made and within 2 years after completion of the contract, or the completion of any extra work or the furnishing of any extra labor, services, or material. 770 ILCS 60/7(a).

Recording is not a prerequisite to a timely suit against the original owner. Section 9 independently requires a suit or counterclaim within two years after completion, and a Section 34 demand can shorten that period. 770 ILCS 60/9, 60/34.

On most projects there is a lender or a potential buyer, so the 4-month period is the one to calendar. The 2-year period helps only where the owner is the sole party whose interest is at stake.

When the Clock Starts

The 4 months run from completion. If extra or additional work is done, or extra or additional labor, services, or material is delivered, the 4 months run from the completion of that extra or additional work or the final delivery of that extra or additional material. 770 ILCS 60/7(a). Completion means the end of the claimant's lienable contract work or deliveries, including qualifying extra or additional work or materials, and not simply the latest site visit; warranty service, maintenance, correction of an already completed job, or trivial work done to revive a deadline ordinarily does not restart the period.

For a contractor there is no waiting period at the front end. The claim for lien may be filed at any time after the claimant's contract is made. A subcontractor is subject to the 10-day period in Section 28, described below.

What the Claim for Lien Must Contain

The claim is verified by the affidavit of the claimant, or the claimant's agent or employee. As to the owner, it may be amended at any time before final judgment. An error or overcharge does not defeat the lien to its proper amount unless it is shown to have been made with intent to defraud. 770 ILCS 60/7(a). The claim must consist of:

  • A brief statement of the claimant's contract
  • The balance due after allowing all credits
  • A sufficiently correct description of the lot, lots, or tracts of land to identify the property

Subcontractors and Suppliers

A subcontractor files its claim for lien within the same limits as to time that Section 7 provides for the contractor. 770 ILCS 60/28. The same 4-month and 2-year periods therefore apply.

The difference is the step that comes first. The subcontractor must serve the Section 24 notice within 90 days after completion, and Section 28 gives the right to file the claim for lien or a complaint when the money due is not paid within 10 days after that notice is served. The 10 days apply to recording the claim as well as to filing suit. Because the notice deadline arrives before the 4-month deadline, it controls the schedule.

After Recording on an Owner-Occupied Home

A contractor for improvements to an owner-occupied single-family residence must give the owner written notice within 10 days after recording the lien. Late notice extinguishes the lien to the extent of damages the owner suffered as a result before notice was given. This requirement does not apply to subcontractors. 770 ILCS 60/7(d).

Frequently Asked Questions

How long do you have to file a mechanics lien in Illinois?

To enforce the lien against other creditors, incumbrancers, or purchasers, record the verified claim for lien or bring suit within 4 months after completion. As to the owner, the claim may be filed within 2 years after completion. 770 ILCS 60/7(a). Recording is not a prerequisite to a timely suit against the original owner, which Section 9 requires within two years after completion. 770 ILCS 60/9.

Does the Illinois 4-month period run from completion or from the last invoice?

From completion, or from the completion of extra or additional work or the final delivery of extra or additional material if any was furnished. 770 ILCS 60/7(a). The invoice date is not the statutory trigger.

Where is an Illinois claim for lien recorded?

In the office of the recorder of the county in which the building or improvement to be charged with the lien is situated. 770 ILCS 60/7(a).

Is the filing deadline different for Illinois subcontractors?

No. Section 28 gives subcontractors the same time limits that Section 7 provides for the contractor. A subcontractor must also have served the Section 24 notice within 90 days after completion. 770 ILCS 60/24(a), 60/28.

Can an Illinois claim for lien be filed before the work is finished?

Yes, for a contractor. Section 7(a) states that the claim for lien may be filed at any time after the claimant's contract is made. A subcontractor may file its claim or its complaint if the money due is not paid within 10 days after the Section 24 notice is served. 770 ILCS 60/28.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us