What Happens If You Send a Preliminary Notice Late in Illinois?

The Answer Depends on Which Notice: the 90-Day Section 24 Notice or the 60-Day Residential Notice

Two Notices, Two Different Rules

Illinois subcontractors and suppliers deal with two pre-lien notices. The Section 24 notice applies on private projects generally and is due within 90 days after completion. The Section 21(c) notice applies only on an existing owner-occupied single-family residence and is due within 60 days from first furnishing.

The statute treats lateness differently for each. One has an express savings clause. The other does not.

A Late 90-Day Section 24 Notice

Section 24(a) says the subcontractor shall serve the notice within 90 days after completion of its contract, or within 90 days after completion of extra or additional work or final delivery of extra or additional material. 770 ILCS 60/24(a). Section 24 contains no provision that preserves part of the lien when the notice is served after that period. Completion means the end of the subcontractor's lienable contract work or deliveries, including qualifying extra or additional work or materials, and not simply the latest site visit; warranty service, maintenance, correction of an already completed job, or trivial work done to revive a deadline ordinarily does not restart the period.

The notice is also the gateway to everything that follows. Section 28 gives the subcontractor the right to file a claim for lien or a complaint when money due is not paid within 10 days after the notice is served as provided in Sections 5, 24, and 25. 770 ILCS 60/28.

If the notice is served outside the applicable 90-day period, including any qualifying extension for extra or additional work or material, and no sworn statement exception applies, the subcontractor's mechanics lien is unenforceable. The prejudice rule that preserves part of the lien after a late 60-day residential notice does not excuse a late Section 24 notice.

A subcontractor that believes it has missed the 90 days should have the facts reviewed promptly, because the questions below determine whether the period was in fact missed.

Three Things to Check Before Treating the 90 Days as Missed

Each of these comes from the text of the Act. None of them extends the 90 days.

  • The start date: the 90 days run from completion of the subcontractor's contract, or, if extra or additional work or material was delivered afterward, from completion of that work or final delivery of that material (770 ILCS 60/24(a))
  • The service date: the notice is considered served when it is placed with the delivery service or in the mail, not when it is received (770 ILCS 60/24(a))
  • The sworn statement: the notice is not necessary when the sworn statement of the contractor or subcontractor gave the owner notice of the amount due and to whom, and if that statement understates the amount, the subcontractor is protected only to the extent of the amount named (770 ILCS 60/24(a))

When the Owner or Lender Cannot Be Found in the County

Section 25 gives an alternative way to give notice, not more time. Where the owner of record, the owner's agent, architect, or superintendent, or the known lending agency cannot be found in the county of the improvement upon reasonable diligence, or does not reside there, the subcontractor may give notice to those persons by filing a verified claim for lien with the recorder within the same 90 days. 770 ILCS 60/25(a).

That recorded notice satisfies Section 24 only as to the persons who could not be found or do not reside in the county. 770 ILCS 60/25(b).

A Late 60-Day Residential Notice

Here the statute is explicit. Any notice given after 60 days by the subcontractor preserves the lien, but only to the extent that the owner has not been prejudiced by payments made prior to receipt of the notice. 770 ILCS 60/21(c).

A late 60-day notice therefore reduces the lien by reference to what the owner paid before receiving it. It does not, by its terms, eliminate the lien. The practical instruction is to give the notice immediately, because the reduction grows with each payment the owner makes before receipt.

The Contractor's Late Post-Recording Notice

A contractor on an owner-occupied single-family residence must give the owner written notice within 10 days after recording a lien. If that notice is late and the owner has suffered damages as a result before notice is given, the lien is extinguished to the extent of the damages. The mere recording of the lien claim is not considered damages. 770 ILCS 60/7(d).

Frequently Asked Questions

Is there a grace period for the Illinois 90-day Section 24 notice?

No. Section 24 requires service within 90 days after completion of the contract, or after completion of extra or additional work or final delivery of extra or additional material. The notice is considered served when it is placed with the delivery service or in the mail. If the notice is served after that period and no sworn statement exception applies, the subcontractor's lien is unenforceable. 770 ILCS 60/24(a).

Can a contractor's sworn statement make up for a missing Section 24 notice?

Section 24(a) says the notice is not necessary when the sworn statement of the contractor or subcontractor gives the owner notice of the amount due and to whom it is due. If the statement is incorrect as to the amount, the subcontractor is protected to the extent of the amount named in it.

What happens if the Illinois 60-day residential notice is late?

The lien is preserved only to the extent that the owner has not been prejudiced by payments made before receiving the notice. 770 ILCS 60/21(c). The lien is reduced, not automatically lost.

Does extra work restart the 90-day period in Illinois?

Section 24(a) measures the 90 days from completion of the contract or, if extra or additional work or material is delivered afterward, from completion of that extra or additional work or final delivery of that extra or additional material. Warranty service, maintenance, correction of an already completed job, or trivial work done to revive a deadline ordinarily does not restart the period, although substantial remedial work genuinely necessary to complete the contract can qualify depending on the facts.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.