Indiana Lien Waivers

Indiana Lien Waiver Forms and Rules

When Indiana lien waivers are required, which forms apply, and when a waiver takes effect, for contractors, subcontractors, and suppliers.

Indiana has no statutory lien waiver form

Indiana prescribes no statutory lien waiver forms; waivers are contracts, and on covered projects a provision requiring a waiver before payment is void (Ind. Code § 32-28-3-16).

Quick Answer

No. Indiana does not require or provide a statutory lien waiver form. Conditional and unconditional waivers on partial and final payments are contracts, effective according to their lawful terms and supported by consideration (Ramsey v. Peoples Trust & Savings Bank, 264 N.E.2d 111 (Ind. Ct. App. 1970)).

A contract provision requiring a waiver of lien or payment bond rights before payment for furnished labor or materials is void, as is an agreement not to file a lien notice (Ind. Code § 32-28-3-16). The rule does not apply to Class 2 residential structures or specified utility work.

Indiana imposes no general notarization requirement on a lien waiver. The sworn notice of intention to hold a lien, the release affidavits, and recorded no-lien contracts acknowledged as deeds are different documents, each with its own execution requirements under Indiana Code § 32-28-3 and § 32-28-6.

Indiana supplies no automatic check-clearing rule. In McCartin McAuliffe Mechanical Contractor, Inc. v. Midwest Gas Storage, Inc., 685 N.E.2d 165 (Ind. Ct. App. 1997), a waiver expressly conditioned on a specified payment raised a failure of consideration question when payment came months later.

Indiana does not prescribe lien waiver forms. Conditional and unconditional partial and final waivers are contractual categories, and each takes effect according to its lawful terms and the consideration given.

Indiana does restrict advance waivers. On covered projects, a contract provision requiring a waiver of lien or payment bond rights before payment for the work is void, and so is an agreement not to file a notice of intention to hold a lien. Class 2 residential structures and certain utility work are excluded from that protection.

Indiana Lien Waiver Types

Conditional Partial Waiver

When to use it
Delivered in exchange for a progress payment not yet received.
When it takes effect
Effective when its stated payment condition occurs, and only for the amount, period, and work it describes.

Unconditional Partial Waiver

When to use it
Delivered after a progress payment has been received.
When it takes effect
Effective according to its operative language, subject to the advance-waiver prohibition and consideration defenses.

Conditional Final Waiver

When to use it
Delivered in exchange for final payment not yet received.
When it takes effect
Effective when the stated final payment condition occurs; exceptions and reservations remain important.

Unconditional Final Waiver

When to use it
Delivered after final payment has been received.
When it takes effect
Effective according to its lawful terms. It may reach beyond lien rights if it also releases contract, bond, or change order claims.

Advance waivers are void on covered projects

A provision requiring a waiver of lien or payment bond rights before payment for furnished labor or materials is void, and so is an agreement not to file a notice of intention to hold a lien (Ind. Code § 32-28-3-16(b)-(c)). The statute voids the provision, not the entire contract.

Section 32-28-3-16 excludes Class 2 structures, auxiliary improvements on the same real estate, and specified regulated utility work, so not every advance waiver in Indiana is void.

Residential no-lien contracts

For Class 2 residential work and the other categories the statute authorizes, an owner and principal contractor may make a no-lien contract. To bind lower tiers it must be written, contain a legal description, be acknowledged as a deed, and be recorded within five days after execution (Ind. Code § 32-28-3-1(e)-(f)).

Work furnished before recording remains protected. An untimely recorded agreement may still bind the contracting parties themselves. Mayberry Cafe, Inc. v. Glenmark Construction Co., 879 N.E.2d 1162 (Ind. Ct. App. 2008).

Notarization

Indiana's lien statute imposes no general notarization requirement on a lien waiver.

Verification and acknowledgment differ: the lien notice must be sworn, the release affidavits are sworn, and a recorded no-lien contract must be acknowledged as a deed.

Payment conditions and pay-if-paid

Apply an express receipt or collected-funds condition as written. If a waiver is unconditional or acknowledges receipt, do not assume Indiana supplies an unstated condition.

On covered projects, an upstream party's receipt of payment cannot condition, limit, or defeat a provider's right to record or foreclose its lien (Ind. Code § 32-28-3-18).

Bond rights and scope

A waiver of lien rights is not automatically a release of the debt or of payment bond rights; the instrument's scope controls. Section 32-28-3-16 also voids advance waivers of payment bond claims on covered projects.

Exchange Indiana lien waivers with your customers and subcontractors, tracked against each payment.

Lien Waiver Exchange

Frequently Asked Questions

Does Indiana have a statutory lien waiver form?

No. Indiana does not prescribe conditional, unconditional, partial, or final waiver forms. Waivers are contracts governed by their lawful terms and consideration.

Does an Indiana lien waiver have to be notarized?

No statute requires it. Notarization or verification applies to other documents, such as the sworn notice of intention to hold a lien (Ind. Code § 32-28-3-3) and release affidavits.

Are advance lien waivers void in Indiana?

On most projects, yes. A provision requiring a waiver of lien or payment bond rights before payment, or an agreement not to file a lien notice, is void (Ind. Code § 32-28-3-16). Class 2 residential structures and certain utility work are excluded.

Can an Indiana homeowner use a no-lien contract?

Yes, for Class 2 residential work. The contract must be written, describe the property, be acknowledged as a deed, and be recorded within five days after execution to bind subcontractors and suppliers (Ind. Code § 32-28-3-1(e)-(f)).

Is a conditional waiver effective if payment arrives late in Indiana?

It depends on the facts. In McCartin McAuliffe Mechanical Contractor, Inc. v. Midwest Gas Storage, Inc., 685 N.E.2d 165 (Ind. Ct. App. 1997), payment tendered many months after a waiver conditioned on that payment raised a question of failure of consideration.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.