Every notice, lien, enforcement, release, and bond claim document used on Indiana construction projects, with who uses it, when it is due, and where it goes.

Quick Answer

An Indiana lien claimant needs a sworn statement and notice of intention to hold a lien, recorded in duplicate with the county recorder within 90 days after last furnishing, or 60 days on a Class 2 residential structure, and a foreclosure suit within one year after recording (Ind. Code §§ 32-28-3-3, 32-28-3-6).

On alteration or repair of an owner-occupied single or double family dwelling, a claimant furnishing to someone other than the owner must give the occupying owner written notice within 30 days after first furnishing. On original construction of a dwelling for owner occupancy, the notice is furnished to the owner and recorded within 60 days (§ 32-28-3-1(h)-(i)).

An owner or other interested person can serve a written notice to file suit, which requires foreclosure within 30 days after receipt (§ 32-28-3-10). After a paid lien, the lienholder must release it within 15 days after a demand (§ 32-28-6-1).

On state public works, a claimant files a verified claim with the division within 60 days after last furnishing and delivers a copy to the contractor (§ 4-13.6-7-10). On local public works, it files with the board within 60 days and sues within 60 days after final completion and acceptance (§ 36-1-12-13.1).

Indiana's mechanics lien statute, Indiana Code § 32-28-3, centers on one document: the sworn statement and notice of intention to hold a lien, recorded with the county recorder within 90 days after last furnishing, or 60 days on Class 2 residential structures. Residential projects add pre-lien notices for claimants that do not deal directly with the owner.

Public property in Indiana is not subject to mechanics liens. Claimants on public projects file claims against retained funds and payment bonds, and the procedure differs for state projects, local projects, other public bodies, and INDOT highway work.

This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory text.

Indiana Preliminary Notices

Pre-Lien Notice (Residential Alteration or Repair)

Required When It Applies
Who uses it
Subcontractors and suppliers furnishing on credit to someone other than the occupying owner, on an owner-occupied single or double family dwelling
When
Within 30 days after first delivery of materials or labor
Served on or filed with
The occupying owner; not recorded
Notarization
Not required
  • The notice must describe the delivery or work and state that lien rights exist. Missing it defeats the lien.

Ind. Code § 32-28-3-1(h)

Pre-Lien Notice (Original Residential Construction)

Required When It Applies
Who uses it
Claimants furnishing through someone other than the owner on original construction of a single or double family dwelling for owner occupancy
When
Within 60 days after first delivery or labor, for both furnishing and recording
Served on or filed with
Furnished to the record owner and a copy filed with the county recorder
Notarization
Not required

Ind. Code § 32-28-3-1(i)

Indiana Notices Before Filing a Lien

Personal Liability Notice to Owner

Optional
Who uses it
Subcontractors, equipment lessors, journeymen, and laborers
When
No fixed deadline; recovery is limited to sums due or to become due from the owner, so serve it early
Served on or filed with
The owner, or the owner's agent if the owner is absent; not recorded
Notarization
Not required
  • It must state the claim amount, the services, the employer's debt, and that the owner is held responsible. It is a remedy separate from the lien.

Ind. Code § 32-28-3-9

Indiana Lien Claim and Service

Sworn Statement and Notice of Intention to Hold a Lien

Notarized
Required When It Applies
Who uses it
Contractors, subcontractors, suppliers, and laborers
When
Within 90 days after last furnishing; within 60 days on Class 2 structures and auxiliary improvements on the same real estate
Served on or filed with
Recorded in duplicate with the county recorder where the property lies; the recorder mails the duplicate to the owner within 3 business days
Notarization
Required (sworn and verified)
  • The notice states the amount, the claimant, the owner and its latest tax record address, and the legal description.
  • On original construction, record before a good-faith purchaser's deed is recorded.

Ind. Code § 32-28-3-3

Indiana Enforcing the Lien

Complaint to Foreclose Mechanic's Lien

Required When It Applies
Who uses it
Lienholders
When
Within 1 year after recording, or within 30 days after receipt of a notice to file suit
Served on or filed with
Filed in the circuit or superior court of the county where the property lies
Notarization
Not required
  • A written credit agreement signed by the lienholder and all record owners, recorded within the year, can extend the deadline.

Ind. Code § 32-28-3-6

Notice to File Foreclosure Action

Optional
Who uses it
Owners and other interested persons, including mortgagees and lienholders
When
Any time after the lien is recorded; the lienholder must sue within 30 days after receipt
Served on or filed with
The lienholder, by registered or certified mail to its recorded address
Notarization
Not required; the follow-up affidavit to clear the record is sworn
  • If no suit is filed, the notice giver may record an affidavit with the county recorder to release the lien of record.

Ind. Code § 32-28-3-10

Indiana Releasing or Bonding Off a Lien

Release of Mechanic's Lien

Required When It Applies
Who uses it
Lienholders whose secured debt has been paid or satisfied
When
Within 15 days after a demand for release
Served on or filed with
Recorded with the county recorder where the lien was filed
Notarization
Not prescribed by the statute; county recording requirements apply
  • A lienholder that fails to release after demand faces statutory damages.

Ind. Code § 32-28-6-1

Written Undertaking with Surety to Release Property

Optional
Who uses it
Foreclosure defendants, owners, or other interested persons
When
During a pending foreclosure action
Served on or filed with
Filed in the foreclosure action for court approval
Notarization
Not required
  • The undertaking secures payment of any judgment, costs, and allowed attorney fees; on approval, the court releases the property.

Ind. Code § 32-28-3-11

Indiana Owner Notices and Forms

Affidavit for Release by Lapse of Time

Notarized
Optional
Who uses it
Owners and other interested persons
When
13 months after the lien notice was filed, if no foreclosure is pending
Served on or filed with
Filed with the county recorder
Notarization
Required (sworn affidavit)

Ind. Code §§ 32-28-6-1(c), 32-28-6-2

Recorded No-Lien Contract

Notarized
Optional
Who uses it
Owners and principal contractors, only for Class 2 residential work and other categories the statute authorizes
When
Recorded within 5 days after execution
Served on or filed with
Recorded with the county recorder where the property lies
Notarization
Required (acknowledged as a deed)
  • It cannot defeat liens for work furnished before recording, and is not available for ordinary commercial projects.

Ind. Code § 32-28-3-1(e)-(g)

Indiana Public Works and Payment Bond Claims

Verified Claim (State Public Works)

Notarized
Required When It Applies
Who uses it
Subcontractors and suppliers on state projects
When
Within 60 days after last furnishing; to proceed on the bond, also send a copy to the surety
Served on or filed with
Filed with the division, with a copy delivered to the contractor
Notarization
Required (verified)
  • Wait 30 days after filing and delivery before suing; sue on the bond within 1 year after final settlement.

Ind. Code §§ 4-13.6-7-10, 4-13.6-7-11

Claim and Duplicate Statements (Local Public Works)

Required When It Applies
Who uses it
Subcontractors, suppliers, laborers, and service providers on local projects
When
Within 60 days after last furnishing
Served on or filed with
Filed with the board, with a copy delivered to the contractor; the board forwards a duplicate to the surety
Notarization
Not required (signed statements)
  • Wait 30 days after filing and delivery; sue the surety within 60 days after final completion and acceptance.

Ind. Code §§ 36-1-12-12, 36-1-12-13.1

Duplicate Verified Statements (Other Public Bodies)

Notarized
Required When It Applies
Who uses it
Unpaid claimants on public work under Indiana Code § 5-16-5
When
Within 60 days after last furnishing
Served on or filed with
Filed with the public body, with a copy delivered to the contractor
Notarization
Required (verified)
  • Wait 30 days; sue the surety within 60 days after final completion and acceptance.

Ind. Code § 5-16-5-2

Verified Itemized Statement (INDOT Highway Projects)

Notarized
Required When It Applies
Who uses it
Unpaid claimants on state highway work
When
Within 60 days after last furnishing and within 30 days after final acceptance
Served on or filed with
Filed in triplicate with INDOT, which mails copies to the contractor and surety
Notarization
Required (verified)
  • If the claim is rejected, sue within 90 days after receiving the rejection notice and forward the clerk's certificate to INDOT.

Ind. Code §§ 8-23-9-26, 8-23-9-30

Frequently Asked Questions

Is there a statutory mechanics lien form in Indiana?

No fill-in form. Indiana Code § 32-28-3-3 prescribes the content of the sworn statement and notice of intention to hold a lien: the amount claimed, the claimant's name and address, the owner's name and latest tax record address, and the legal description of the property.

Does an Indiana mechanics lien have to be notarized?

Yes. The notice of intention to hold a lien must be sworn and verified (Ind. Code § 32-28-3-3). The residential pre-lien notices do not require notarization.

Where do I file a mechanics lien in Indiana?

Record the sworn statement and notice in duplicate with the county recorder in the county where the property lies. The recorder mails the duplicate to the owner within three business days (Ind. Code § 32-28-3-3).

What is the Indiana residential pre-lien notice?

A written notice from a claimant that does not deal directly with the owner. For alteration or repair of an owner-occupied single or double family dwelling, give it to the occupying owner within 30 days after first furnishing. For original construction, furnish and record it within 60 days (Ind. Code § 32-28-3-1(h)-(i)).

What form releases a mechanics lien in Indiana?

A release recorded with the county recorder. Once the debt is paid, the lienholder must release the lien within 15 days after a demand (Ind. Code § 32-28-6-1). An owner may also clear a lien by affidavit after a notice to sue goes unanswered, or 13 months after filing if no suit is pending.

What form do I use for an Indiana public project bond claim?

It depends on the project. State projects use a verified claim filed with the division within 60 days; local projects use a claim filed with the board within 60 days; INDOT highway work uses a verified itemized statement filed in triplicate. Each has its own suit deadline.

Deadlines Are Unforgiving

Every Day You Wait Is a Day Closer to Missing Your Deadline

Construction lien deadlines are strict and unforgiving. Once they pass, your right to payment may be gone forever.

Contact Us