Quick Answer
An Indiana lien claimant needs a sworn statement and notice of intention to hold a lien, recorded in duplicate with the county recorder within 90 days after last furnishing, or 60 days on a Class 2 residential structure, and a foreclosure suit within one year after recording (Ind. Code §§ 32-28-3-3, 32-28-3-6).
On alteration or repair of an owner-occupied single or double family dwelling, a claimant furnishing to someone other than the owner must give the occupying owner written notice within 30 days after first furnishing. On original construction of a dwelling for owner occupancy, the notice is furnished to the owner and recorded within 60 days (§ 32-28-3-1(h)-(i)).
An owner or other interested person can serve a written notice to file suit, which requires foreclosure within 30 days after receipt (§ 32-28-3-10). After a paid lien, the lienholder must release it within 15 days after a demand (§ 32-28-6-1).
On state public works, a claimant files a verified claim with the division within 60 days after last furnishing and delivers a copy to the contractor (§ 4-13.6-7-10). On local public works, it files with the board within 60 days and sues within 60 days after final completion and acceptance (§ 36-1-12-13.1).
Indiana's mechanics lien statute, Indiana Code § 32-28-3, centers on one document: the sworn statement and notice of intention to hold a lien, recorded with the county recorder within 90 days after last furnishing, or 60 days on Class 2 residential structures. Residential projects add pre-lien notices for claimants that do not deal directly with the owner.
Public property in Indiana is not subject to mechanics liens. Claimants on public projects file claims against retained funds and payment bonds, and the procedure differs for state projects, local projects, other public bodies, and INDOT highway work.
This page describes each document, who uses it, when it is due, and where it goes. It does not reproduce statutory text.
Indiana Preliminary Notices
Pre-Lien Notice (Residential Alteration or Repair)
- Who uses it
- Subcontractors and suppliers furnishing on credit to someone other than the occupying owner, on an owner-occupied single or double family dwelling
- When
- Within 30 days after first delivery of materials or labor
- Served on or filed with
- The occupying owner; not recorded
- Notarization
- Not required
- The notice must describe the delivery or work and state that lien rights exist. Missing it defeats the lien.
Ind. Code § 32-28-3-1(h)
Pre-Lien Notice (Original Residential Construction)
- Who uses it
- Claimants furnishing through someone other than the owner on original construction of a single or double family dwelling for owner occupancy
- When
- Within 60 days after first delivery or labor, for both furnishing and recording
- Served on or filed with
- Furnished to the record owner and a copy filed with the county recorder
- Notarization
- Not required
Ind. Code § 32-28-3-1(i)
Indiana Notices Before Filing a Lien
Personal Liability Notice to Owner
- Who uses it
- Subcontractors, equipment lessors, journeymen, and laborers
- When
- No fixed deadline; recovery is limited to sums due or to become due from the owner, so serve it early
- Served on or filed with
- The owner, or the owner's agent if the owner is absent; not recorded
- Notarization
- Not required
- It must state the claim amount, the services, the employer's debt, and that the owner is held responsible. It is a remedy separate from the lien.
Ind. Code § 32-28-3-9
Indiana Lien Claim and Service
Sworn Statement and Notice of Intention to Hold a Lien
- Who uses it
- Contractors, subcontractors, suppliers, and laborers
- When
- Within 90 days after last furnishing; within 60 days on Class 2 structures and auxiliary improvements on the same real estate
- Served on or filed with
- Recorded in duplicate with the county recorder where the property lies; the recorder mails the duplicate to the owner within 3 business days
- Notarization
- Required (sworn and verified)
- The notice states the amount, the claimant, the owner and its latest tax record address, and the legal description.
- On original construction, record before a good-faith purchaser's deed is recorded.
Ind. Code § 32-28-3-3
Indiana Enforcing the Lien
Complaint to Foreclose Mechanic's Lien
- Who uses it
- Lienholders
- When
- Within 1 year after recording, or within 30 days after receipt of a notice to file suit
- Served on or filed with
- Filed in the circuit or superior court of the county where the property lies
- Notarization
- Not required
- A written credit agreement signed by the lienholder and all record owners, recorded within the year, can extend the deadline.
Ind. Code § 32-28-3-6
Notice to File Foreclosure Action
- Who uses it
- Owners and other interested persons, including mortgagees and lienholders
- When
- Any time after the lien is recorded; the lienholder must sue within 30 days after receipt
- Served on or filed with
- The lienholder, by registered or certified mail to its recorded address
- Notarization
- Not required; the follow-up affidavit to clear the record is sworn
- If no suit is filed, the notice giver may record an affidavit with the county recorder to release the lien of record.
Ind. Code § 32-28-3-10
Indiana Releasing or Bonding Off a Lien
Release of Mechanic's Lien
- Who uses it
- Lienholders whose secured debt has been paid or satisfied
- When
- Within 15 days after a demand for release
- Served on or filed with
- Recorded with the county recorder where the lien was filed
- Notarization
- Not prescribed by the statute; county recording requirements apply
- A lienholder that fails to release after demand faces statutory damages.
Ind. Code § 32-28-6-1
Written Undertaking with Surety to Release Property
- Who uses it
- Foreclosure defendants, owners, or other interested persons
- When
- During a pending foreclosure action
- Served on or filed with
- Filed in the foreclosure action for court approval
- Notarization
- Not required
- The undertaking secures payment of any judgment, costs, and allowed attorney fees; on approval, the court releases the property.
Ind. Code § 32-28-3-11
Indiana Owner Notices and Forms
Affidavit for Release by Lapse of Time
- Who uses it
- Owners and other interested persons
- When
- 13 months after the lien notice was filed, if no foreclosure is pending
- Served on or filed with
- Filed with the county recorder
- Notarization
- Required (sworn affidavit)
Ind. Code §§ 32-28-6-1(c), 32-28-6-2
Recorded No-Lien Contract
- Who uses it
- Owners and principal contractors, only for Class 2 residential work and other categories the statute authorizes
- When
- Recorded within 5 days after execution
- Served on or filed with
- Recorded with the county recorder where the property lies
- Notarization
- Required (acknowledged as a deed)
- It cannot defeat liens for work furnished before recording, and is not available for ordinary commercial projects.
Ind. Code § 32-28-3-1(e)-(g)
Indiana Public Works and Payment Bond Claims
Verified Claim (State Public Works)
- Who uses it
- Subcontractors and suppliers on state projects
- When
- Within 60 days after last furnishing; to proceed on the bond, also send a copy to the surety
- Served on or filed with
- Filed with the division, with a copy delivered to the contractor
- Notarization
- Required (verified)
- Wait 30 days after filing and delivery before suing; sue on the bond within 1 year after final settlement.
Ind. Code §§ 4-13.6-7-10, 4-13.6-7-11
Claim and Duplicate Statements (Local Public Works)
- Who uses it
- Subcontractors, suppliers, laborers, and service providers on local projects
- When
- Within 60 days after last furnishing
- Served on or filed with
- Filed with the board, with a copy delivered to the contractor; the board forwards a duplicate to the surety
- Notarization
- Not required (signed statements)
- Wait 30 days after filing and delivery; sue the surety within 60 days after final completion and acceptance.
Ind. Code §§ 36-1-12-12, 36-1-12-13.1
Duplicate Verified Statements (Other Public Bodies)
- Who uses it
- Unpaid claimants on public work under Indiana Code § 5-16-5
- When
- Within 60 days after last furnishing
- Served on or filed with
- Filed with the public body, with a copy delivered to the contractor
- Notarization
- Required (verified)
- Wait 30 days; sue the surety within 60 days after final completion and acceptance.
Ind. Code § 5-16-5-2
Verified Itemized Statement (INDOT Highway Projects)
- Who uses it
- Unpaid claimants on state highway work
- When
- Within 60 days after last furnishing and within 30 days after final acceptance
- Served on or filed with
- Filed in triplicate with INDOT, which mails copies to the contractor and surety
- Notarization
- Required (verified)
- If the claim is rejected, sue within 90 days after receiving the rejection notice and forward the clerk's certificate to INDOT.
Ind. Code §§ 8-23-9-26, 8-23-9-30
Frequently Asked Questions
Is there a statutory mechanics lien form in Indiana?
No fill-in form. Indiana Code § 32-28-3-3 prescribes the content of the sworn statement and notice of intention to hold a lien: the amount claimed, the claimant's name and address, the owner's name and latest tax record address, and the legal description of the property.
Does an Indiana mechanics lien have to be notarized?
Yes. The notice of intention to hold a lien must be sworn and verified (Ind. Code § 32-28-3-3). The residential pre-lien notices do not require notarization.
Where do I file a mechanics lien in Indiana?
Record the sworn statement and notice in duplicate with the county recorder in the county where the property lies. The recorder mails the duplicate to the owner within three business days (Ind. Code § 32-28-3-3).
What is the Indiana residential pre-lien notice?
A written notice from a claimant that does not deal directly with the owner. For alteration or repair of an owner-occupied single or double family dwelling, give it to the occupying owner within 30 days after first furnishing. For original construction, furnish and record it within 60 days (Ind. Code § 32-28-3-1(h)-(i)).
What form releases a mechanics lien in Indiana?
A release recorded with the county recorder. Once the debt is paid, the lienholder must release the lien within 15 days after a demand (Ind. Code § 32-28-6-1). An owner may also clear a lien by affidavit after a notice to sue goes unanswered, or 13 months after filing if no suit is pending.
What form do I use for an Indiana public project bond claim?
It depends on the project. State projects use a verified claim filed with the division within 60 days; local projects use a claim filed with the board within 60 days; INDOT highway work uses a verified itemized statement filed in triplicate. Each has its own suit deadline.
Related Indiana Resources
Indiana Mechanics Lien Guide
Deadlines for every tier, filing steps, and FAQs.
Indiana Notice Requirements
Who must give notice, when, and how.
Indiana Lien Waivers
Statutory forms, waiver types, and enforceability rules.
Indiana Mechanics Lien Filing Deadlines
Recording deadlines and requirements.
This page provides general information about Indiana law, not legal advice. Requirements depend on the project, the claimant's role, and the facts.