Mechanics Lien Deadlines by State

Preliminary notice, lien filing, and enforcement deadlines for all 50 states and Washington D.C. in one chart. Each entry is drawn from the verified deadline table on that state's page.

The chart shows private-project rules for subcontractors and suppliers, with the prime contractor's lien deadline alongside. Public works claims run against a payment bond instead of the property; each state's page and forms page set out those rules. Select a state for the full rules by tier.

Alabama
Preliminary notice (subs and suppliers)
A Notice of Unpaid Balance must be served on the owner, and on any reasonably identifiable construction lender, before filing the mechanic lien. Alabama law does not set a specific deadline; the only requirement is that the notice is delivered before the Verified Statement is filed. Failure to serve it invalidates the lien. A material supplier that gave the advance full-price notice is exempt from this requirement.
Lien deadline (subs and suppliers)
Subcontractors and materialmen file the Verified Statement of Mechanic Lien within 4 months after the last date of furnishing labor or materials.
Lien deadline (prime contractor)
File the Verified Statement of Mechanic Lien with the judge of probate in the county where the property is located within 6 months after the last item of work or labor has been performed.
Enforcement
Commence suit to enforce the mechanic lien within 6 months after the date the entire amount became due.
Alaska
Preliminary notice (subs and suppliers)
Recording a Notice of Right to Lien before or within 15 days after a Notice of Completion preserves the ordinary 120-day lien filing deadline. Giving the owner a compliant notice before furnishing shifts the burden of proof to the owner on knowledge and consent; recording alone does not.
Lien deadline (subs and suppliers)
Record the Claim of Lien in the recording district where the property is located within 120 days after last furnishing labor or materials.
Lien deadline (prime contractor)
Record the Claim of Lien in the recording district where the property is located within 120 days after completing the contract or last furnishing labor or materials.
Enforcement
Commence suit to foreclose the Claim of Lien within 6 months after recording.
Arizona
Preliminary notice (subs and suppliers)
Serve the Preliminary 20-Day Notice on the owner, original contractor, construction lender, and the person with whom the claimant contracted within 20 days after first furnishing labor, professional services, materials, machinery, fixtures, or tools.
Lien deadline (subs and suppliers)
Record the Notice and Claim of Lien with the county recorder within 120 days after completion of the project.
Lien deadline (prime contractor)
Record the Notice and Claim of Lien with the county recorder within 120 days after completion of the project.
Enforcement
Commence an action to foreclose the mechanic lien within 6 months after the Notice and Claim of Lien is recorded. Record a lis pendens within 5 days of filing suit. Missing the 6-month deadline renders the lien unenforceable.
Arkansas
Preliminary notice (subs and suppliers)
On residential projects of four units or fewer, the residential contractor's Pre-Construction Notice to Owner protects every tier on the job. If the contractor fails to give it, any potential lien claimant may give the notice itself before its own furnishing, but a lien relying on that notice covers only work furnished after the notice takes effect.
Lien deadline (subs and suppliers)
File the Statement of Account and Claim of Lien with the circuit clerk of the county where the property is located within 120 days after last furnishing labor or materials. Serve the Notice of Intent to Lien at least 10 days before filing.
Lien deadline (prime contractor)
File the Statement of Account and Claim of Lien with the circuit clerk of the county where the property is located within 120 days after last furnishing labor or materials. Serve the Notice of Intent to Lien at least 10 days before filing.
Enforcement
Within 15 months after the lien was filed, commence suit to enforce the mechanic lien and file a lis pendens, then prosecute the action without unnecessary delay. Missing this deadline extinguishes the lien.
California
Preliminary notice (subs and suppliers)
Serve a Preliminary 20-Day Notice on the owner, direct contractor, and construction lender (if any) within 20 days of first furnishing labor, services, or materials.
Lien deadline (subs and suppliers)
Record the Claim of Mechanics Lien within 90 days after completion of the work of improvement.
Lien deadline (prime contractor)
Record the Claim of Mechanics Lien within 90 days after completion of the work of improvement.
Enforcement
Commence an action to foreclose the mechanics lien within 90 days after recording the Claim of Mechanics Lien. If the owner and claimant agree to extend credit and notice of the extension is recorded, suit is due within 90 days after the credit expires, but no later than 1 year after completion.
Colorado
Preliminary notice (subs and suppliers)
Serve a Notice of Intent to File Lien Statement on the owner and the prime contractor at least 10 full days before recording the Lien Statement.
Lien deadline (subs and suppliers)
Record the Lien Statement with the county clerk and recorder within 4 months after the last day labor or materials were furnished to the project.
Lien deadline (prime contractor)
Record the Lien Statement with the county clerk and recorder within 4 months after the last day labor or materials were furnished to the project.
Enforcement
Within 6 months after completion of the improvement or the last day labor or materials were furnished, whichever is later, commence an action to foreclose the Lien Statement and record a notice of lis pendens in the county where the property is located. Filing suit alone is not sufficient.
Connecticut
Preliminary notice (subs and suppliers)
Serve a Notice of Intent on the owner within 90 days after last furnishing labor or materials.
Lien deadline (subs and suppliers)
Record the Certificate of Lien with the town clerk in the town where the property is located within 90 days after last furnishing labor or materials.
Lien deadline (prime contractor)
Record the Certificate of Lien with the town clerk in the town where the property is located within 90 days after last furnishing labor or materials.
Enforcement
Commence a foreclosure action and record a Notice of Lis Pendens within 1 year after the Certificate of Lien is recorded, or within 60 days after final disposition of an owner's application to discharge or reduce the lien, if later. Missing this deadline discharges the lien as a matter of law.
Delaware
Preliminary notice (subs and suppliers)
Not required. Delaware does not require any pre-work or preliminary notice from subcontractors or suppliers as a condition of mechanic lien rights.
Lien deadline (subs and suppliers)
File the Statement of Claim with the Prothonotary of the Superior Court within 120 days after the date labor was last performed or materials were last furnished. A filing is also timely within 120 days after final payment, including retainage, is due to the claimant, or after final payment to the contractor with whom the claimant contracted.
Lien deadline (prime contractor)
File the Statement of Claim with the Prothonotary of the Superior Court within 180 days after completion of the structure.
Enforcement
In Delaware, the action to enforce the lien is incorporated into the Statement of Claim itself; filing the Statement of Claim in Superior Court commences the action.
Florida
Preliminary notice (subs and suppliers)
Serve a Notice to Owner (NTO) on the owner before commencing, or within 45 days after first furnishing, labor, services, or materials, and in any event before the owner's final payment.
Lien deadline (subs and suppliers)
Record the Claim of Lien with the county clerk within 90 days after last furnishing labor, materials, or services. Serve a copy on the owner before recording or within 15 days after recording.
Lien deadline (prime contractor)
Record the Claim of Lien with the county clerk within 90 days after last furnishing labor, materials, or services. Serve a copy on the owner before recording or within 15 days after recording.
Enforcement
Commence an action to enforce the lien within 1 year of recording the Claim of Lien.
Georgia
Preliminary notice (subs and suppliers)
Send the Notice to Contractor to the owner and the prime contractor by registered or certified mail or statutory overnight delivery within 30 days of first furnishing labor or materials, OR within 30 days after the filing of the Notice of Commencement, whichever date is later.
Lien deadline (subs and suppliers)
Record within 90 days after last furnishing.
Lien deadline (prime contractor)
Record within 90 days after last furnishing.
Enforcement
Commence action within 365 days of filing the Claim of Lien.
Hawaii
Preliminary notice (subs and suppliers)
Not required. Hawaii does not impose a pre-work preliminary notice obligation on any tier of claimant for private projects.
Lien deadline (subs and suppliers)
File the Application for Lien and Notice of Lien with the Circuit Court in the circuit where the property is located within 45 days after the date of completion of the improvement.
Lien deadline (prime contractor)
File the Application for Lien and Notice of Lien with the Circuit Court in the circuit where the property is located within 45 days after the date of completion of the improvement.
Enforcement
Commence suit to foreclose the lien within 3 months after the court enters the Order Directing Lien to Attach. The lien cannot be extended; failure to sue within this window extinguishes the lien.
Idaho
Preliminary notice (subs and suppliers)
Not required. Idaho does not impose a pre-work preliminary notice on first-tier subcontractors or suppliers on private projects.
Lien deadline (subs and suppliers)
Record the Claim of Lien with the county recorder within 90 days after completion of the labor or services, or the furnishing of materials.
Lien deadline (prime contractor)
Record the Claim of Lien with the county recorder within 90 days after completion of the labor or services, or the furnishing of materials.
Enforcement
Commence an action to foreclose the Claim of Lien within 6 months after it is recorded.
Illinois
Preliminary notice (subs and suppliers)
Within 90 days of the last date of furnishing labor or materials, serve a Section 24 Notice on the owner.
Lien deadline (subs and suppliers)
Within 4 months after the last date of furnishing labor or materials, record the mechanic lien with the county recorder to preserve priority against third parties.
Lien deadline (prime contractor)
Within 4 months after the last date of furnishing labor or materials, record the mechanic lien with the county recorder to preserve priority against third parties.
Enforcement
Within 2 years from the last date of furnishing labor or materials, commence a suit to foreclose the mechanic lien.
Indiana
Preliminary notice (subs and suppliers)
Alteration or repair of an owner-occupied single or double family dwelling: give the Pre-Lien Notice to the occupying owner within 30 days after first furnishing labor or materials.
Lien deadline (subs and suppliers)
Commercial projects: record the Notice of Intention to Hold a Mechanic's Lien with the county recorder within 90 days after the last date of furnishing labor or materials.
Lien deadline (prime contractor)
Commercial projects: record the Notice of Intention to Hold a Mechanic's Lien with the county recorder within 90 days after the last date of furnishing labor or materials.
Enforcement
Commence a suit to foreclose the mechanic lien within 1 year after recording the Notice of Intention to Hold a Mechanic's Lien.
Iowa
Preliminary notice (subs and suppliers)
On residential projects, post a Preliminary Notice to the Mechanic's Notice and Lien Registry (MNLR) before the owner has paid the prime contractor in full.
Lien deadline (subs and suppliers)
Record a Mechanic's Lien within 90 days after last furnishing labor or materials to preserve priority against the owner and subsequent purchasers or encumbrancers.
Lien deadline (prime contractor)
Record a Mechanic's Lien within 90 days after last furnishing labor or materials to preserve priority against the owner and subsequent purchasers or encumbrancers.
Enforcement
Commence an action to foreclose the Mechanic's Lien within 2 years and 90 days after last furnishing of labor or materials.
Kansas
Preliminary notice (subs and suppliers)
On residential property, mail the statutory warning statement to an owner, or hold the owner's signed acknowledgment, and attach the compliance affidavit to the lien statement. Not required if the total claim is $250 or less. Failure defeats the lien.
Lien deadline (subs and suppliers)
Record a Mechanic's Lien Statement with the clerk of the district court within 3 months after the last date of furnishing labor, equipment, materials, or supplies.
Lien deadline (prime contractor)
Record a Mechanic's Lien Statement with the clerk of the district court within 4 months after the last date of furnishing labor, equipment, materials, or supplies.
Enforcement
Commence a suit to foreclose the mechanic lien within 1 year after the Mechanic's Lien Statement is filed.
Kentucky
Preliminary notice (subs and suppliers)
Claims of less than $1,000: serve within 75 days after last furnishing labor or materials.
Lien deadline (subs and suppliers)
Record the Statement of Lien with the county clerk within 6 months after last furnishing labor or materials.
Lien deadline (prime contractor)
Record the Statement of Lien with the county clerk within 6 months after last furnishing labor or materials.
Enforcement
Commence an action to enforce the lien within 12 months after the Statement of Lien is filed.
Louisiana
Preliminary notice (subs and suppliers)
No mandatory preliminary notice before work begins. Best practice is to deliver a written Request for Notice to the owner so you receive notice of a Notice of Termination, substantial completion, or abandonment.
Lien deadline (subs and suppliers)
If a Notice of Contract was timely filed: file the statement of claim or privilege within 30 days after the filing of a Notice of Termination or, if none is filed, within 6 months after substantial completion or abandonment.
Lien deadline (prime contractor)
If a Notice of Contract was timely filed: file the statement of claim or privilege within 60 days after the filing of a Notice of Termination.
Enforcement
Institute suit to enforce the privilege within 1 year after filing the statement of claim or privilege, and record a notice of lis pendens within that year.
Maine
Preliminary notice (subs and suppliers)
Not required. Maine does not impose a pre-work preliminary notice obligation on subcontractors or suppliers.
Lien deadline (subs and suppliers)
Within 90 days after your last labor or materials were furnished, record a sworn Notice of Lien in the registry of deeds for the county where the property is located and mail a copy to the owner.
Lien deadline (prime contractor)
Not required to preserve the lien. A contractor in direct contract with the owner is exempt from the 90-day lien filing requirement and preserves the lien by commencing suit within 120 days after last furnishing.
Enforcement
Commence a lawsuit to enforce the lien within 120 days after last labor or materials were furnished.
Maryland
Preliminary notice (subs and suppliers)
Serve a Notice of Intention to Claim a Lien on the owner within 120 days after last furnishing labor or materials, by registered or certified mail (return receipt requested) or personal delivery.
Lien deadline (subs and suppliers)
File a Petition to Establish Mechanic's Lien in Circuit Court within 180 days after last furnishing labor or materials.
Lien deadline (prime contractor)
File a Petition to Establish Mechanic's Lien in Circuit Court within 180 days after last furnishing labor or materials.
Enforcement
File a motion to enforce the lien in the original lien action within 1 year after the Petition to Establish Mechanic's Lien was first filed, or the lien expires.
Massachusetts
Preliminary notice (subs and suppliers)
Must be recorded by the earliest of: 60 days after recording of a Notice of Substantial Completion, 90 days after recording of a Notice of Termination, or 90 days after the last day the general contractor, or anyone claiming through it, furnished labor or materials.
Lien deadline (subs and suppliers)
Must be recorded by the earliest of: 90 days after recording of a Notice of Substantial Completion, 120 days after recording of a Notice of Termination, or 120 days after the last day the general contractor, or anyone claiming through it, furnished labor or materials.
Lien deadline (prime contractor)
Must be recorded by the earliest of: 90 days after recording of a Notice of Substantial Completion, 120 days after recording of a Notice of Termination, or 120 days after the last day the general contractor, or anyone claiming through it, furnished labor or materials.
Enforcement
Commence a civil action to enforce the lien within 90 days after filing the Statement of Account, and file an attested copy of the complaint for recording within 30 days after commencing it. Missing the suit deadline dissolves the lien.
Michigan
Preliminary notice (subs and suppliers)
Serve a Notice of Furnishing on the designee named in the Notice of Commencement (or the owner or lessee if there is no designee) and on the general contractor within 20 days after first furnishing labor or materials.
Lien deadline (subs and suppliers)
Record the Claim of Lien with the register of deeds within 90 days after last furnishing labor or materials.
Lien deadline (prime contractor)
Record the Claim of Lien with the register of deeds within 90 days after last furnishing labor or materials.
Enforcement
Commence a suit to foreclose the construction lien within 1 year after the Claim of Lien is recorded, and record a notice of lis pendens.
Minnesota
Preliminary notice (subs and suppliers)
Serve the Pre-Lien Notice on the owner, personally or by certified mail, within 45 days after first furnishing labor or materials.
Lien deadline (subs and suppliers)
Record the Statement of Lien Claim with the county recorder within 120 days after the last date of furnishing labor or materials, and serve a copy on the owner by personal service or certified mail within the same 120-day window.
Lien deadline (prime contractor)
Record the Statement of Lien Claim with the county recorder within 120 days after the last date of furnishing labor or materials, and serve a copy on the owner by personal service or certified mail within the same 120-day window.
Enforcement
Commence a suit to enforce the mechanic lien within 1 year after the last date of furnishing stated in the lien statement, and record a notice of lis pendens when the action begins.
Mississippi
Preliminary notice (subs and suppliers)
Single-family residential projects: a subcontractor, supplier, or design professional not in contract with the owner must give the owner a written pre-lien notice at least 10 days before filing the lien. Owner payments made before receiving the notice reduce the lien.
Lien deadline (subs and suppliers)
Record the Claim of Lien with the chancery clerk within 90 days after last furnishing labor or materials.
Lien deadline (prime contractor)
Record the Claim of Lien with the chancery clerk within 90 days after last furnishing labor or materials.
Enforcement
Commence the payment action within 180 days after recording the Claim of Lien and file a notice of lis pendens at the same time. If the owner records a notice of contest, the deadline becomes the earlier of 90 days after the contest or 180 days after recording.
Missouri
Preliminary notice (subs and suppliers)
Serve a Ten-Day Notice of Intent to File Mechanic's Lien on the owner at least 10 days before filing the lien statement, stating the amount claimed and the party it is owed by. Serve it personally, or keep proof that the owner actually received it; proof of mailing alone is not enough.
Lien deadline (subs and suppliers)
File the mechanic's lien statement with the circuit clerk of the county where the property lies within 6 months after the indebtedness accrues, ordinarily the last day labor, materials, or services were furnished.
Lien deadline (prime contractor)
File the mechanic's lien statement with the circuit clerk of the county where the property lies within 6 months after the indebtedness accrues, ordinarily the last day labor, materials, or services were furnished.
Enforcement
Commence an action to enforce the mechanic's lien within 6 months after filing the lien statement, then prosecute it without unnecessary delay.
Montana
Preliminary notice (subs and suppliers)
Serve the Notice of Right to Claim a Construction Lien on the contracting owner within 20 days of first furnishing labor or materials to protect the full amount you are owed.
Lien deadline (subs and suppliers)
File the Construction Lien with the county clerk and recorder within 90 days after your last furnishing of labor or materials, or within 90 days after the owner files a notice of completion, whichever comes first.
Lien deadline (prime contractor)
File the Construction Lien with the county clerk and recorder within 90 days after your last furnishing of labor or materials, or within 90 days after the owner files a notice of completion, whichever comes first.
Enforcement
Commence an action to foreclose the Construction Lien within 2 years after the lien is filed. The clock runs from the filing date, not from your last day on the job.
Nebraska
Preliminary notice (subs and suppliers)
On residential projects for a protected-party owner, serve the optional written Notice of Right to Assert a Lien on the owner as early as possible. Against a protected party, a claimant not in direct contract is limited to the lesser of its own unpaid amount or the amount unpaid under the prime contract when the owner receives the notice.
Lien deadline (subs and suppliers)
Record the Construction Lien with the register of deeds within 120 days after the claimant's final furnishing of services or materials.
Lien deadline (prime contractor)
Record the Construction Lien with the register of deeds within 120 days after the claimant's final furnishing of services or materials.
Enforcement
Commence an action to enforce the Construction Lien within 2 years after the date of recording.
Nevada
Preliminary notice (subs and suppliers)
Serve a Notice of Right to Lien on the owner, personally or by certified mail, with an informational copy to the prime contractor, within 31 days of first delivery of labor or materials. A missing copy to the prime does not invalidate the notice to the owner.
Lien deadline (subs and suppliers)
Record the Notice of Lien with the county recorder within 90 days after the latest of completion of the work of improvement, the claimant's last delivery of material or equipment, and the claimant's last work.
Lien deadline (prime contractor)
Record the Notice of Lien with the county recorder within 90 days after the latest of completion of the work of improvement, the claimant's last delivery of material or equipment, and the claimant's last work.
Enforcement
Commence an action to foreclose the lien within 6 months after the Notice of Lien is recorded. Only a written extension signed by the affected owners and recorded within the 6 months can lengthen it, and never beyond 1 year after recording.
New Hampshire
Preliminary notice (subs and suppliers)
Give the owner written notice before performing labor or furnishing materials to protect the full amount. Later notice is valid but limited, as explained below.
Lien deadline (subs and suppliers)
Within 120 days after last furnishing labor or materials, commence a civil action and obtain an attachment of the property, recorded by lodging the attested writ and return with the registry of deeds.
Lien deadline (prime contractor)
Within 120 days after last furnishing labor or materials, commence a civil action and obtain an attachment of the property, recorded by lodging the attested writ and return with the registry of deeds.
Enforcement
The mechanic's lien expires 120 days after last furnishing of labor or materials unless secured by an attachment in a civil action commenced within that window. There is no later foreclosure deadline; the payment claim itself is subject to the general 3-year limitation measured from the act or omission complained of.
New Jersey
Preliminary notice (subs and suppliers)
Residential construction: lodge a Notice of Unpaid Balance and Right to File Lien (NUB) with the county clerk within 60 days after last furnishing, serve it within 10 days after lodging, and serve a demand for arbitration within 10 days after lodging.
Lien deadline (subs and suppliers)
Commercial projects: lodge the Construction Lien Claim with the county clerk within 90 days after last furnishing labor, materials, services, or equipment for which payment is claimed. Warranty calls and work after completion do not restart the clock.
Lien deadline (prime contractor)
Commercial projects: lodge the Construction Lien Claim with the county clerk within 90 days after last furnishing labor, materials, services, or equipment for which payment is claimed. Warranty calls and work after completion do not restart the clock.
Enforcement
Commence an action in Superior Court to enforce the Construction Lien Claim within 1 year after last furnishing, or within 30 days after receiving a written demand to commence suit, whichever is earlier.
New Mexico
Preliminary notice (subs and suppliers)
Not required. A mechanic or materialman who contracts directly with the original contractor is exempt, whatever the size of the claim.
Lien deadline (subs and suppliers)
Record the claim of lien with the county clerk within 90 days after completion of the building, improvement, or structure, or after completion of the alteration or repair. This is a project event, not the claimant's own last day of furnishing.
Lien deadline (prime contractor)
Record the claim of lien with the county clerk within 120 days after completion of the contract. The clock runs from completion of the original contractor's own contract, not from the last day on site.
Enforcement
Commence proceedings to enforce the lien within 2 years after the claim of lien is filed. The clock runs from the filing date, not from completion or last furnishing.
New York
Preliminary notice (subs and suppliers)
No preliminary notice is required in New York.
Lien deadline (subs and suppliers)
File the Notice of Mechanic's Lien with the county clerk during the work or within 8 months after completion of the contract or the last date of furnishing labor or materials.
Lien deadline (prime contractor)
File the Notice of Mechanic's Lien with the county clerk during the work or within 8 months after completion of the contract or the last date of furnishing labor or materials.
Enforcement
Within 1 year after the lien is filed, commence an action to foreclose it and file a notice of pendency. Commencing suit alone does not preserve the lien.
North Carolina
Preliminary notice (subs and suppliers)
Serve a Notice to Lien Agent within 15 days of first furnishing on projects where the owner has designated a lien agent.
Lien deadline (subs and suppliers)
First-, second-, and third-tier subcontractors may file a Claim of Lien on Real Property by subrogation to the contractor's lien with the clerk of superior court within 120 days after last furnishing labor or materials.
Lien deadline (prime contractor)
File the Claim of Lien on Real Property with the clerk of superior court in the county where the property is located, after the debt is due but no later than 120 days after last furnishing labor or materials.
Enforcement
Commence an action to enforce the lien within 180 days after last furnishing labor or materials.
North Dakota
Preliminary notice (subs and suppliers)
Mail the Notice of Intention to Claim a Construction Lien to the owner by certified mail at least 10 days before recording the Construction Lien.
Lien deadline (subs and suppliers)
Record within 90 days after last furnishing to preserve priority against good-faith purchasers and encumbrancers and against owner payments made to the contractor before recording.
Lien deadline (prime contractor)
Record within 90 days after last furnishing to preserve priority against good-faith purchasers and encumbrancers and against owner payments made to the contractor before recording.
Enforcement
Commence suit to foreclose and record a lis pendens within 3 years after the lien is recorded. If the owner delivers and files a written demand to enforce, the claimant must commence suit and record a lis pendens within 30 days after delivery or the lien is extinguished.
Ohio
Preliminary notice (subs and suppliers)
On projects where it applies, serve the Notice of Furnishing on the owner (or the owner's designee) within 21 days after first furnishing labor or materials. A subcontractor in direct contract with the original contractor need not serve that contractor.
Lien deadline (subs and suppliers)
Record the Affidavit for Mechanic's Lien with the county recorder within 75 days after last furnishing labor or materials on most projects.
Lien deadline (prime contractor)
Record the Affidavit for Mechanic's Lien with the county recorder within 75 days after last furnishing labor or materials on most projects.
Enforcement
Commence a suit to foreclose the mechanic's lien within 6 years after the lien is recorded.
Oklahoma
Preliminary notice (subs and suppliers)
Send a Pre-Lien Notice to the owner and the original contractor before filing the Lien Statement and no later than 75 days after last furnishing labor, materials, or equipment.
Lien deadline (subs and suppliers)
Record the Lien Statement with the county clerk within 90 days after last furnishing labor, materials, or equipment. The county clerk mails notice of the filing to the owner by certified mail within 5 business days.
Lien deadline (prime contractor)
File the verified Lien Statement with the county clerk where the land lies within 4 months after last furnishing labor, materials, or equipment.
Enforcement
Commence suit to foreclose the lien within 1 year after filing the Lien Statement.
Oregon
Preliminary notice (subs and suppliers)
Deliver a Notice of Right to a Lien to the owner no later than 8 business days after first delivering labor, materials, equipment, or services to the project. Material suppliers also give the mortgagee notice to protect lien priority.
Lien deadline (subs and suppliers)
Record the Claim of Lien with the county recording officer within 75 days after the claimant's last furnishing, or within 75 days after the project is complete, whichever occurs first.
Lien deadline (prime contractor)
Record the Claim of Lien with the county recording officer within 75 days after the claimant's last furnishing, or within 75 days after the project is complete, whichever occurs first.
Enforcement
Commence a suit to foreclose the mechanic lien within 120 days after recording the Claim of Lien. If the claim states a credit extension, suit is due within 120 days after the extension expires, but no later than 2 years after recording.
Pennsylvania
Preliminary notice (subs and suppliers)
On projects of $1.5 million or more where the owner has filed a Notice of Commencement with the State Construction Notices Directory (SCND), file a Notice of Furnishing with the SCND within 45 days of first furnishing labor or materials. Failure to substantially comply forfeits lien rights on qualifying projects. Before filing the Mechanic's Lien Claim, also serve a formal Notice of Intent to Lien on the owner at least 30 days before filing the lien claim.
Lien deadline (subs and suppliers)
File the Mechanic's Lien Claim with the prothonotary within 6 months after completion of the claimant's own work, then serve written notice of the filing on the owner within 1 month and file the affidavit of service within 20 days after service.
Lien deadline (prime contractor)
File the Mechanic's Lien Claim with the prothonotary within 6 months after completion of the claimant's own work, then serve written notice of the filing on the owner within 1 month and file the affidavit of service within 20 days after service.
Enforcement
Commence an action to obtain judgment on the lien within 2 years of filing the lien claim, unless the owner extends the time in writing. A verdict or judgment must be obtained within 5 years of filing.
Rhode Island
Preliminary notice (subs and suppliers)
Mail the Notice of Intention to the owner and record it in the land evidence records of the city or town where the property is located within 200 days after the claimant's last furnishing of labor or materials. The recorded notice covers only labor and materials furnished within the 200 days before recording and thereafter, so record it early in the project.
Lien deadline (subs and suppliers)
File the complaint to enforce in Superior Court and record a notice of lis pendens in the land evidence records within 40 days after the Notice of Intention is recorded.
Lien deadline (prime contractor)
File the complaint to enforce in Superior Court and record a notice of lis pendens in the land evidence records within 40 days after the Notice of Intention is recorded.
Enforcement
The complaint must be filed on the same day as the lis pendens or within 7 days afterward, and in any event within the 40 days after the Notice of Intention is recorded. Serve the citation at least 5 days before its return day.
South Carolina
Preliminary notice (subs and suppliers)
Subcontractors in direct contract with the prime are not required to serve this notice to preserve lien rights.
Lien deadline (subs and suppliers)
Serve the owner (or, if the owner cannot be found, the person in possession) with a sworn statement of the lien and file it in the county where the property is located within 90 days after last furnishing.
Lien deadline (prime contractor)
Serve the owner (or, if the owner cannot be found, the person in possession) with a sworn statement of the lien and file it in the county where the property is located within 90 days after last furnishing.
Enforcement
Commence suit to foreclose the Mechanic's Lien and file a notice of pendency of action within 6 months after the claimant's last furnishing of labor or materials on the project, or the lien dissolves.
South Dakota
Preliminary notice (subs and suppliers)
Not required. A first-tier subcontractor or supplier in direct contract with the prime contractor need not send a Notice of Furnishing or any other pre-work notice.
Lien deadline (subs and suppliers)
File the Mechanic's Lien Statement with the register of deeds in the county where the property is located within 120 days after last furnishing labor or materials.
Lien deadline (prime contractor)
File the Mechanic's Lien Statement with the register of deeds in the county where the property is located within 120 days after last furnishing labor or materials.
Enforcement
Commence suit to foreclose the Mechanic's Lien within 6 years after the claimant's last furnishing of labor or materials. If the owner serves a written demand to commence suit, the claimant must commence suit within 30 days after service or the lien is forfeited.
Tennessee
Preliminary notice (subs and suppliers)
On all projects other than one-to-four family residential units, serve a Notice of Nonpayment on the owner and the prime contractor within 90 days after the last day of each month in which labor or materials were furnished and remain unpaid, by registered or certified mail (return receipt requested) or another delivery method the statute permits. Failure to serve for a given month forfeits lien rights for that month's unpaid work. Retainage is exempt.
Lien deadline (subs and suppliers)
Serve a written Notice of Lien on the owner within 90 days after completion or abandonment of the improvement, and record the Sworn Statement with the County Register within the same 90 days to preserve priority against later purchasers and lenders.
Lien deadline (prime contractor)
To preserve priority against subsequent purchasers and encumbrancers, record a Notice of Lien (Sworn Statement of amount owed) with the County Register within 90 days after completion or abandonment of the improvement.
Enforcement
Commence an action to enforce the mechanic lien within 90 days after serving the Notice of Lien on the owner. File the sworn complaint seeking attachment within that period.
Texas
Preliminary notice (subs and suppliers)
Send a Notice of Claim for unpaid labor or materials to the owner and the original contractor by certified mail, personal delivery, or another traceable delivery method by the 15th day of the 3rd month after each month in which labor or materials went unpaid.
Lien deadline (subs and suppliers)
Record the Affidavit of Lien with the county clerk by the 15th day of the 4th month after the month the claimant last furnished labor or materials.
Lien deadline (prime contractor)
Record the Affidavit of Lien with the county clerk by the 15th day of the 4th month after the month the original contract was completed, terminated, or abandoned.
Enforcement
Commence suit to foreclose the lien within 1 year from the last day the lien affidavit could have been filed.
Utah
Preliminary notice (subs and suppliers)
File a Preliminary Notice with the State Construction Registry (SCR) within 20 days of first furnishing labor or materials.
Lien deadline (subs and suppliers)
Record the Notice of Construction Lien with the county recorder within 180 days after final completion of the original contract, OR within 90 days after a Notice of Completion is filed with the SCR, whichever is earlier. Deliver or mail a copy by certified mail to the owner within 30 days of recording; missing this forfeits costs and attorney fees against the owner, not the lien.
Lien deadline (prime contractor)
Record the Notice of Construction Lien with the county recorder within 180 days after final completion of the original contract, OR within 90 days after a Notice of Completion is filed with the SCR, whichever is earlier. Deliver or mail a copy by certified mail to the owner within 30 days of recording; missing this forfeits costs and attorney fees against the owner, not the lien.
Enforcement
Commence an action to enforce the lien and record a lis pendens within 180 days after recording the Notice of Construction Lien. A late action voids the lien.
Vermont
Preliminary notice (subs and suppliers)
Give the owner (or the owner's agent in charge) written notice that a lien is claimed, including the date payment is due if known. The lien reaches only the balance the owner still owes on its contract when the owner receives the notice, so send it before funds are paid out.
Lien deadline (subs and suppliers)
Record the Memorandum of Contractor's Lien (Notice of Lien) in the town clerk's office (town land records) within 180 days after payment became due for the last labor or materials furnished.
Lien deadline (prime contractor)
Record the Memorandum of Contractor's Lien (Notice of Lien) in the town clerk's office (town land records) within 180 days after payment became due for the last labor or materials furnished.
Enforcement
Commence suit and complete a court-ordered Writ of Attachment against the property within 180 days after recording the Notice of Lien, or, if payment was not yet due when the Notice of Lien was recorded, within 180 days after payment becomes due.
Virginia
Preliminary notice (subs and suppliers)
On one- or two-family residential dwelling units where the building permit designates a Mechanics Lien Agent, serve notice on the Mechanics Lien Agent within 30 days after first furnishing labor or materials, or within 30 days after the permit is issued if work began earlier. A late notice preserves the lien only for labor and materials furnished on or after the date of the notice.
Lien deadline (subs and suppliers)
Record the Memorandum of Mechanic's Lien in the circuit court clerk's office for the city or county where the property is located within 90 days after the last day of the month in which labor or materials were last furnished.
Lien deadline (prime contractor)
Record the Memorandum of Mechanic's Lien in the circuit court clerk's office for the city or county where the property is located within 90 days after the last day of the month in which labor or materials were last furnished.
Enforcement
Commence suit to enforce the mechanic lien within the later of 6 months after recording the Memorandum of Mechanic's Lien or 60 days after completion of the building or structure.
Washington
Preliminary notice (subs and suppliers)
On new construction of a single-family residence the notice protects only what was furnished after a date 10 days before it is mailed by certified or registered mail, or personally served, on the owner or reputed owner. Everything furnished earlier drops out.
Lien deadline (subs and suppliers)
Record the Claim of Lien with the county auditor within 90 days after last furnishing labor, professional services, materials, or equipment. Warranty work correcting your own defective work does not restart the clock; genuinely unfinished contract work can, whatever it is called.
Lien deadline (prime contractor)
Record the Claim of Lien with the county auditor within 90 days after last furnishing labor, professional services, materials, or equipment. Warranty work correcting your own defective work does not restart the clock; genuinely unfinished contract work can, whatever it is called.
Enforcement
File suit to foreclose within 8 calendar months after recording the Claim of Lien. The clock runs from the recording date, not from last furnishing.
Washington D.C.
Preliminary notice (subs and suppliers)
Not required. D.C. has no preliminary notice. Lien rights are preserved by recording a single sworn Notice of Intent, shown in the next column.
Lien deadline (subs and suppliers)
Record one sworn, notarized Notice of Intent with the D.C. Recorder of Deeds at any time during construction or within 90 days after the earlier of completion or termination of the project. The 90-day clock runs from project completion or termination, not from the individual claimant's last furnishing.
Lien deadline (prime contractor)
Record one sworn, notarized Notice of Intent with the D.C. Recorder of Deeds at any time during construction or within 90 days after the earlier of completion or termination of the project. The 90-day clock runs from project completion or termination, not from the individual claimant's last furnishing.
Enforcement
Commence a suit to enforce the mechanic's lien within 180 days after the Notice of Intent is recorded.
West Virginia
Preliminary notice (subs and suppliers)
Not required. West Virginia does not impose a pre-work preliminary notice obligation on subcontractors or suppliers.
Lien deadline (subs and suppliers)
Record the Notice of Mechanic's Lien with the county clerk within 100 days after completing your subcontract (suppliers: after you last furnish materials; laborers: after your work ends).
Lien deadline (prime contractor)
Record the Notice of Mechanic's Lien with the county clerk of the county where the property is located within 100 days after completing the work provided for in the contract.
Enforcement
Commence suit to enforce the lien within 6 months after recording the Notice of Mechanic's Lien. A timely suit by another lienholder on the same property also preserves the lien, and other lienholders may intervene.
Wisconsin
Preliminary notice (subs and suppliers)
A Notice of Intent to File Claim for Lien must be served on the owner at least 30 days before recording the Claim for Lien.
Lien deadline (subs and suppliers)
Record the Claim for Lien with the clerk of circuit court in the county where the property is located within 6 months after last furnishing labor or materials.
Lien deadline (prime contractor)
Record the Claim for Lien with the clerk of circuit court in the county where the property is located within 6 months after last furnishing labor or materials.
Enforcement
Commence a suit to foreclose the Claim for Lien within 2 years after the Claim for Lien is recorded.
Wyoming
Preliminary notice (subs and suppliers)
Send a Notice of Right to File a Lien to the record owner or the owner's agent within 30 days after first furnishing labor or materials, with a copy to the contractor you are working for. This applies on residential and commercial projects alike. Before filing the Lien Statement, also send a Notice of Intent to Lien to the owner at least 20 days before recording the lien.
Lien deadline (subs and suppliers)
Record the Lien Statement within 120 days after the earlier of your last furnishing of labor or materials or substantial completion of the project. A recorded written extension agreement can extend the period.
Lien deadline (prime contractor)
Record the Lien Statement within 150 days after the earlier of your last furnishing of labor or materials under the contract or substantial completion of the project. A recorded written extension agreement can extend the period.
Enforcement
Commence action within 180 days after filing the Lien Statement.

General information, not legal advice. Deadlines depend on the claimant's role, the project type, and the dates of furnishing. Cite as: National Lien & Bond, Mechanics Lien Deadlines by State, mechanicslien.com/mechanics-lien-deadlines-by-state.

Frequently Asked Questions

What is the shortest mechanics lien deadline in the United States?

Hawaii's 45 days after completion of the improvement is among the shortest, and Ohio and Oregon allow 75 days on most projects. Several states shorten the period further once an owner records a notice of completion or termination. Check the state's own page, because the trigger date (last furnishing, completion, or a recorded notice) matters as much as the number of days.

Do subcontractors and prime contractors have the same lien deadline?

Not always. Many states give the prime contractor a longer period or start its clock from completion of the contract, while subcontractors and suppliers count from their own last furnishing. The chart shows both columns for that reason.

Does a preliminary notice deadline apply in every state?

No. Some states require no preliminary notice from subcontractors, some require it only on residential work, and some require a notice of intent shortly before filing instead. The notice column states the rule for subcontractors and suppliers on private work.

How current is this chart?

Each cell is generated from the deadline table on the state's own page, which was verified against the state's statutes and case law in November 2026. When a state page changes, the chart is regenerated from it.

Can I cite this chart?

Yes. Cite it as National Lien & Bond, Mechanics Lien Deadlines by State, with a link to this page. It is general information, not legal advice; confirm deadlines for a specific project on the state's page or with counsel.

Deadlines Are Unforgiving